BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Pearl Petroleum Company Ltd & Ors v The Kurdistan Regional Government of Iraq [2015] EWHC 3361 (Comm) (20 November 2015) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2015/3361.html Cite as: [2015] WLR(D) 476, [2015] 2 CLC 877, [2016] 2 All ER (Comm) 807, [2016] 4 WLR 2, [2016] 1 Lloyd's Rep 441, [2016] 3 All ER 514, [2015] EWHC 3361 (Comm) |
[New search] [Printable RTF version] [View ICLR summary: [2015] WLR(D) 476] [Buy ICLR report: [2016] 4 WLR 2] [Help]
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) Pearl Petroleum Company Limited (2) Dana Gas PJSC (3) Crescent Petroleum Company International Limited |
Claimants |
|
- and - |
||
The Kurdistan Regional Government of Iraq |
Respondent |
____________________
Graham Dunning QC and Anton Dudnikov (instructed by Wilmer Cutler Pickering Hale and Dorr LLP) for the Respondent
Hearing dates: 28, 29 and 30 October 2015
____________________
Crown Copyright ©
Mr Justice Burton :
"A. The KRG has entered into a Strategic Alliance Protocol ("SAP") dated 4th April 2007 with Dana and . . . [Crescent] (. . . the "Companies") whereby the Companies will carry out optimization of the development and utilization of natural gas resources in the [KRI].
B. The KRG wishes to appoint Dana to carry out certain works in the field of Khor Mor . . . and in the field of Chemchemal . . . in the [KRI]. The work is urgently required to fulfil energy requirements in the [KRI] and in particular to provide urgent gas supplies for use at the power stations under construction at Erbil and Bazian, and thereby help to relieve the electrical power shortage affecting all the people of Iraq.
C. The KRG has endorsed a federal draft Oil and Gas Law for Iraq that requires petroleum contracts issued by federal and regional entities, including by the KRG, to meet agreed commercial criteria, in addition to other relevant provisions pursuant to the KRG and the Constitution of Iraq.
. . .
F. The KRG, desirous of rapid and optimal economic development of the petroleum gas resources of the [KRI], gas-related industries, and job creation for the benefit of the people of Iraq and the [KRI], has declared its intention to associate and contract with Dana . . . to take the lead in the development of the gas resources of the [KRI], both for domestic gas utilization as a priority, as well as for export."
The following clauses are of particular relevance:
"9. The KRG hereby grants Dana the exclusive right during the term of these HoA [minimum 25 years] . . . to develop and produce Petroleum within the Khor Mor HoA Area and the Chemchemal HoA Area.
. . .
16. For the purpose of this Article, "Dispute" shall mean any dispute, controversy or claim (of any and every kind or type . . .
If the Dispute cannot be resolved by negotiation within sixty (60) days after the date of the receipt by each party to the Dispute of the Notice of Dispute any party to the Dispute may seek settlement of the dispute by mediation in accordance with the London Court of International Arbitration (LCIA) Mediation Procedure, which Procedure shall be deemed to be incorporated by reference into this Article, and the parties to such Dispute shall submit to such mediation procedure:
(a) If the Dispute is not settled by mediation within sixty (60) days of the appointment of the mediator, or such further period as the parties to the Dispute may otherwise agree in writing, any party to the Dispute may refer the Dispute to, and seek final resolution by, arbitration under the LCIA Rules, which Rules shall be deemed to be incorporated by reference into this Article.
(b) Any arbitration shall be conducted by three (3) arbitrators.
. . .
(e) Arbitration shall take place in London, England. The language to be used in any prior negotiation, mediation and in the arbitration shall be English. During the arbitration procedure and until the arbitral decision, neither entity shall act in a manner that may affect the rights of the other Party under these HoA . . . The arbitral award may include an award of specific performance and may be enforced by any court of competent jurisdiction, including the Kurdistan Region. Any award shall be expressed in US Dollars."
There were (inter alia) the following "Key Commercial Terms" contained in Annexure 2:
"? In the event Dana is unable to export and market the LPG's [or] Condensates by any act or omission of government (including foreign neighbouring governments) and/or for political reasons beyond the control [of] Dana then the KRG shall purchase and lift (or arrange for the lifting by the domestic companies/users) and pay for the liquid petroleum products at international FOB Med market prices as quoted by Platts Oilgram Report or similar journals within 30 days from the month ends. [Identified by the parties as "Bullet 7"].
? The KRG waives on its own behalf and that of the KRG any claim to immunity for itself and assets."
The history
"2. The Claimants seek an order to compel the Respondent . . . to restore the status quo ante and prevent further escalation of the dispute during the pendency of the present arbitration, by resuming payment for on-going deliveries of condensate and liquefied petroleum gas (LPG) and releasing and/or procuring the release of funds to the Claimants which were withheld by the KRG or on the KRG's instructions following the Claimants' commencement of mediation on 24 July 2013.
3. Absent the cash flows from the sale of condensate and LPG to the Claimants until their abrupt curtailment by the KRG with effect from July 2013, Dana . . . which operates the gas processing facilities at Khor Mor jointly with Crescent on behalf of Pearl, will face a cash crisis and is expected to run out of cash by the fourth quarter of 2014. As a consequence, Dana . . . will default on its debt obligations and the company will be forced into insolvency during the pendency of the present arbitration, causing irreparable damage to [Dana's] . . . stakeholders, including its over 200,000-strong regional and international shareholder base.
4. The insolvency of Dana . . . is likely to result in the KRG's take-over of operations and the destruction of the rights under the Contract that are the subject matter of this dispute.
. . .
8. Prior to the initiation of the mediation on 24 July 2013, the KRG was making regular (albeit deficient) payments (either directly or through third parties) for condensate and LPG, which were and continue to be critical to the Contractor's ability to continue operating the gas production facilities at Khor Mor and Dana Gas's ability to service its home office costs and debt obligations.
9. In an act of retaliation to the Claimants' commencement of mediation proceedings on 24 July 2013, the KRG deliberately withheld all contractually-due payments it had previously been making on a regular basis for the supply to it of Khor Mor condensate. Moreover, and in order to 'turn off' entirely the tap of the Claimant's revenue streams from the uninterrupted production that it continues to provide, the KRG altered the terms upon which it auctions the right to lift LPG to third parties by diverting payments away from the Claimants. The basis for the KRG's retaliatory action is a set of contrived counterclaims which, despite allegedly amounting to nearly US$5 billion and being based on allegations dating back several years, had never previously been raised, let alone quantified or used as a basis for withholding payments to the Claimants.
. . .
11. In the circumstances, and in the light of recent press reports regarding the KRG's intentions to this effect, the Claimants have good reason to believe that the KRG's conduct is part of a concerted strategy to manufacture excuses for a precipitate and unlawful termination of the Contract, take-over of operations and subsequent sale of the valuable exclusive rights under the Contract to a third party, the latter having already been attempted by the KRG in the recent past. The Claimants' belief has been further reinforced by the KRG's constant attempts at obfuscation and delay, first in resisting expedited formation of the arbitral tribunal, and then in its lengthy and repetitive objections to having preliminary issues heard and challenge to the jurisdiction of the Arbitral Tribunal.
12. The KRG's recent conduct and resulting alteration of the status quo ante will lead to the collapse of Dana . . . will aggravate the present dispute and will likely result in an expropriation of the subject matter of this arbitration long before the Arbitral Tribunal will have an opportunity to render a final award. To prevent this, the Claimants require assistance from the Arbitral Tribunal in the form of the interim measures set out in Section IV below.
. . .
14. In order to address its purported concern all the KRG needs do is to continue what it has been doing in recent years, namely make and/or direct payments to the Contractor for Khor Mor condensate and LPG lifted by it or on its behalf.
. . .
50. Article 25.1 of the LCIA Rules does not set out any explicit standards for the grant of interim measures. Nonetheless, in international arbitration practice arbitral tribunals typically take into account the following factors when considering a request for interim measures:
(a) whether the applicant has a prima facie case on the merits;
(b) whether the application is likely to suffer serious harm if the measures are not granted;
(c) whether the request is urgent;
(d) whether granting the request would prejudge the merits of a case; and
(e) the harm the applicant is likely to suffer in the absence of interim measures as compared with the harm likely to result to the respondent if the measures are granted.
. . .
56. Thirdly, many international tribunals require the requesting party to demonstrate urgency, which is closely related to the requirement of serious or substantial harm. The requirement of urgency has been construed sufficiently broadly by tribunals to justify interim measures designed to avoid the aggravation of the dispute that is the subject matter of the arbitration.
[Citations of various international tribunals' decisions were set out in footnotes].
. . .
74. . . . In any event, the fact that Dana . . . is being forced irretrievably to dispose of core assets in distressed sales is sufficiently serious to warrant interim measures of protection from the Arbitral Tribunal.
. . .
76. With Dana . . . unable to fund the Contractor and the latter having run out of funds required to continue operating the Khor Mor facilities, the KRG will likely seek to step in (as it has already threatened to do), leading to the Claimants effectively losing their rights under the Contract, the very subject matter of the dispute.
77. Such a scenario, which is entirely avoidable, would not only threaten the procedural integrity of these proceedings but also cause the Claimants irretrievably to lose the benefit of Article 16(e) of the Contract which specifically (1) obliges the parties to maintain the status quo ante during the pendency of an arbitration by not "act[ing] in a manner that may affect the right of the other Party"; and (2) confers upon the parties a right to specific performance of the Contract."
"5. First, the Claimants' requested interim measures would fundamentally alter the status quo . . . The Claimants' application proceeds on the premise that there was an established "payment regime" in which it was commonly agreed or understood that the Claimants would continue to receive payments indefinitely on some undefined basis. In reality, however there was no such status quo. The KRG has never accepted or agreed that any of the Claimants would be entitled to the proceeds of the condensates and LPGs that the KRG has sold."
Further:
"109. The Claimants rely on the financial position of Dana as a basis for interim measures, but, on their own case, Dana has purportedly novated all of its rights or obligations under the HoA (and thus has no existing funding obligations under the HoA). As such, there is no basis for concluding that Dana's financial status is even relevant, much less decisive, with regard to the purported inability of the Claimants to continue operations.
. . .
111. . . . there is no evidence that Pearl will run out of funds required to continue operations in the absence of KRG payments. The Claimants have adduced very little evidence on Pearl's financial condition (which, it is common ground, is the Claimants' burden to prove). Absent such evidence, it is impossible to conclude that the Claimants will be unable to continue operations under the HoA at Khor Mor.
. . .
122. . . . the Claimants argue that Dana's "risk of insolvency" constitutes "truly irreparable harm," but this is both unproven and irrelevant. As set out above the evidence submitted by the Claimants does not establish that there is a true risk of insolvency. In any event, insolvency does not prevent the Claimants from pursuing their claims in arbitration, and therefore cannot constitute harm "not adequately reparable" by damages."
In paragraphs 160 to 173 of its Response the Respondent contended that the ordering of payments and of a mandatory injunction as an interim measure would prejudicially alter the status quo, and concluded at paragraph 183 that:
"Accordingly, the Claimants' Request must be denied because it would entail pre-judgment of both the Claimants' claims and the KRG's counterclaims."
"1. Preservation of the dynamic status quo ante
95. First, as indicated in the Claimants' Request, the KRG is contractually and legally obliged to maintain the status quo pending determination of this dispute pursuant to Article 16(e) of the Contract and Article 50(Second)(4) of the KROGL. Notwithstanding the Respondent's smokescreen, the undisputed fact remains that the Respondent was making (or authorising third parties to make) regular payments to the Claimants in respect of products delivered over a five year period, whether under the Contract, or otherwise.
96. The Claimants only seek preservation of the commercially important "dynamic status quo" which can be achieved simply by the KRG releasing (or authorising third parties to release) payments for condensate and LPG it is taking from the Claimants.
97. The fact remains that, even on the KRG's own case, nothing has changed factually since July 2013 except that the Claimants have initiated mediation and then arbitration proceedings, which have been met by pressure tactics by the Respondent. There is no singular fact which justified the sudden change in the status quo.
98. Indeed, restoring the dynamic status quo is commercially imperative in order to ensure the continuation of operations at Khor Mor and thus the supply of electricity to the residents of the Kurdistan Region, continuation of the Claimants' rights under the Contract and the continuation of Dana . . . as a solvent company. It also means protection of value for both parties including because it accelerates the Claimants' cost recovery and Remuneration Fee payments and, therefore, the point at which the Respondent will earn its 90% of the Aggregate Revenues under the Contract."
"21. The relevance of actions which seek to alter the status quo to the advantage of a party is underlined by Article 16(e) of the HoA itself:
"During the arbitration procedure and until the arbitral decision, neither entity shall act in a manner which may affect the rights of the other party under these HoA/Service Agreements".
. . .
42. It appears to us unlikely that there will be a hearing followed by an award in this arbitration before the middle of 2015. On the evidence before us, there is an appreciable risk that Dana will become insolvent or at any rate suffer unnecessary loss through distressed sales of assets if payments are not resumed before the award.
. . .
45. It is unusual to have an application for provisional measures in which both sides do not claim to be seeking to maintain the status quo and this is no exception. In this case, however, we think that the status quo was that the KRG had for a lengthy period been buying the Claimants' LPPs and paying for them. There may have been a dispute over the price properly payable but payments were being made. By stopping paying, they have altered the status quo, just as someone who cuts off the supply of electricity and plunges the house into darkness.
. . .
47. The ultimate question for the Tribunal is: which course of action is more likely to promote justice, in the broadest sense: to grant the provisional measures or to refuse them? We think that there is a greater risk of injustice if the KRG are allowed to continue to receive the Claimants' condensates (or their proceeds) and not pay for them. The KRG claims that the Claimants are free to export and market their liquid petroleum products in accordance with the HoA. If the KRG is able to procure the necessary licences for the Claimants to be able to do so, well and good. No further action as to the future is required. But if they cannot, and continue instead to have them lifted on their behalf, then we consider that pending a final resolution of this dispute they should pay for them.
(j) Conclusion
48. The practice of the KRG before July 2013 was, we are informed by counsel for the Claimants, to pay about 70% of the invoiced prices (i.e. the international FOB Med prices) of the liquid petroleum products, which were lifted on their behalf. This is a very rough and ready figure, which can be recalculated after a full hearing. In the meanwhile, however, we consider that the KRG should, as from the date of the Claimants' application for interim measures (21 March 2014), pay the Claimants 70% of the international FOB Med prices of liquid petroleum products lifted by them or for their account. If at any time the KRG is able to procure the necessary permits and consents for the Claimants to export and market these products themselves, they may apply to discharge this order."
"16. At the hearing on 5 September, Mr Partasides (for the Claimant) asked why the KRG did not simply reinstate the previous arrangement with PowerTrans, under which the KRG sold the products through PowerTrans, but accounted to the Claimants for what was assumed to be the price received. The KRG had similar arrangements with other international oil companies in Kurdistan. The answer of Mr Born, on behalf of the KRG, must be quoted in full:
"Finally, the claimants asked repeatedly why doesn't the KRG do what it does with other IOCs? This case is the answer for why the KRG doesn't do what it does with other lOCs. It doesn't have arbitrations for bitter disputes with other lOCs. It does have such a dispute with the claimants."
17. It should make no difference to the KRG whether the Claimants sell their products to Quaiwan for the lower price or through PowerTrans at a higher price. In neither case would the KRG be receiving the proceeds. The KRG does not deny that it could reinstate the previous PowerTrans arrangements. But it refuses to do so simply to disoblige the Claimants.
18. The Tribunal is not in a position to express any view on the merits of the "bitter disputes" between the parties. It has however expressed the view in its order for provisional measures that justice requires that provisionally and pending a full hearing, the Claimants should not be deprived of the cash flow, which they had been deriving from their products. The KRG is in a position to enable them to do so. Instead, it claims that they are, and always have been, in a position to export their products but for some irrational and quixotic reason have been unwilling to do so. The Tribunal is not persuaded that the Claimants are in practice in a position to export their products. They do not think that any rational producer, having been for over a year been in a position to export their products, would have chosen instead to apply at this stage for an order for interim measures.
. . .
23. The Tribunal accepts, first, that the preservation of the status quo requires it to have regard to the position at the time when the KRG ceased payments and that going further back into history would not ordinarily be particularly relevant. It was therefore reasonable to have regard to the position under the arrangements with PowerTrans, which were in place from March to July 2013. Secondly, the Tribunal considers that one cannot calculate the percentage of invoiced price which the Claimants were receiving without knowing the shipments to which those prices related. Invoices may have been sent during the period in question which related to earlier shipments. The calculations of Ernst & Young were not challenged in the earlier proceedings and the Tribunal therefore does not think it was misled by Mr Pollock's figure.
. . .
24. The KRG submits that recent events in Iraq have created a political and military crisis in Kurdistan that has changed the balance of convenience. The territory is defending itself against attack and finds itself responsible for the support of large numbers of refugees. It cannot afford to make payments to the Claimants. The KRG also claimed that the financial position of Dana was not as bad as it claimed because a press release of 10 September showed that it had been able to borrow $100 million to finance its UAE gas project. The Claimants replied that this was borrowing for a particular project and distinct from its general corporate debt.
25. The Tribunal is of course aware of the difficult circumstances in which the KRG finds itself in the current situation in the area and has great sympathy for the plight of its people and those who have taken refuge it its territory. But it considers that it is in no position to estimate the significance of these momentous events and that they lie altogether outside the matters to which a Tribunal can have regard in considering what is conventionally called the balance of convenience in an interlocutory application. In such a case, the Tribunal's concern is to weigh the effect of granting or refusing the order on the potential outcome for the parties if one or the other should be successful . The purpose of the interlocutory order is to enable the Tribunal's final order to do practical justice between the parties. It does not consider that the effect upon political events in Kurdistan, which the Tribunal is completely unable to calculate, can fall within the matters it can properly take into consideration.
. . .
29. The KRG says that they have not failed to comply. They have applied for the discharge of the order and while that application was pending, they were not obliged to do anything. We do not think that is right. Any discharge of the order would not have been on the ground that it should not have been made but on the ground that the KRG had enabled the Claimants to export their products and thereby obtain a revenue stream in substitution for that which had previously been paid to them by or at the direction of the KRG. There was no question of the order being discharged retrospectively. As the Tribunal said in its ruling on provisional measures: "If the KRG is able to procure the necessary licences for the Claimants to be able to do so, well and good. No further action as to the future is required." The KRG has . . . failed altogether to comply with the order for payment for liftings from 21 March 2014 to the present day. The Tribunal therefore has jurisdiction under section 41(5) to make a peremptory order.
30. The Tribunal's order for interim measures required payment of 70% of the "the international FOB Med price of liquid petroleum products" on the basis that this was the benchmark employed by the parties in the HoA and should be capable of being employed to calculate the amounts to be paid. It appears however from the submissions at the hearing of this application to discharge that there may be a dispute over what counts as the "international FOB Med price" of condensate and LPG. This dispute may at some stage have to be resolved by the Tribunal but in order to avoid further delay, the Tribunal will fix a provisional figure for payment which it considers to be the least which would give effect to its order to date.
31. The Ernst & Young report to which the Tribunal has referred in paragraph 23 above found that, in respect of the shipments they were considering, the Claimants had received 71% of the invoiced price. Whether the invoiced price had been correctly calculated or not, that was what they were receiving. That was the status quo. The evidence exhibited to the Claimants' application for a peremptory order showed that in the period 21 March to 27 July 2014 the invoiced price of condensate and LNG shipped by the Claimants was US$232,284,453. 70% of this sum is US$162,599,117. The Tribunal considers that an immediate payment of US$100,000,000 should be the subject of a peremptory order. A possible further peremptory order can be considered later. The Tribunal therefore makes an order in the following terms:
"Without prejudice to its order of 10 July 2014, the Tribunal orders that the Respondent shall within 30 days of this order pay to the Claimants US$100 million (to be set off against its liability under the order of 10 July 2014) and if the said sum shall be unpaid after 30 days, makes a peremptory order to the same effect.""
"The KRG undertakes that, if no enforceable final payment award is made prior to the determination of its counterclaim, it will pay the Claimants for liftings of condensates and LPGs delivered to the KRG an equivalent amount per tonne as it pays other IOCs in the Kurdistan Region who currently deliver their petroleum to the KRG. These payments would be provisional and subject to any final award, but would continue until any final award is rendered."
No explanation has been given by the Respondent for this letter to the Arbitrators, save that in his second witness statement of 12 October Mr Speller of the Respondent's solicitors referred to that letter as one by which the Respondent "made clear that, going forward, it would be willing to treat the Claimants no less favourably than other [international oil companies]".
The Issues
Issue 1 Was the peremptory order properly made within the jurisdiction of the Arbitrators vested in them by s.41 of the 1996 Act and Article 25 of the LCIA Rules, and therefore does the Court have jurisdiction to make an order under s.42 of the 1996 Act? There were two sub-issues:
a) Was it a requirement of the making of a peremptory order that the Respondent had failed to comply with an order to do something necessary for the proper and expeditious conduct of the arbitration, and if so was that its purpose?
b) Was the Respondent given the opportunity to show sufficient cause for non-compliance before the making of the Order?
Issue 2 Does the Respondent have immunity pursuant to the SIA? It is accepted that the burden of proof is on the Respondent to establish this. The sub-issues are:
a) Do the proceedings relate to anything done by the Respondent in the exercise of sovereign authority (s.14(2) SIA).
b) If so, was it an exercise of sovereign authority of the State (the Republic of Iraq) or of the Respondent as a separate entity see paragraph 2 above. It is common ground that the former is necessary (BCCI v Price Waterhouse (a firm) [1997] 4 All ER 108 at 112 and Pocket Kings Ltd v Safenames Ltd [2009] EWHC 2529 (Ch)).
c) If so, were the circumstances such that a State would have been immune (s.14(2)(b) SIA)? The issues are whether, as a result of s.9 SIA ("where a State has agreed in writing to submit a dispute which has arisen, or may arise, to arbitration, a State is not immune as regards proceedings in the courts of the United Kingdom which relate to the arbitration") the Respondent is immune to these proceedings under s.42; and whether, by virtue of s.14(3) SIA, the Respondent is entitled to the protection of s.13(2)(a) SIA ("relief shall not be given against a State by way of injunction") in respect of the s.42 order:
i) Has the Respondent submitted to the jurisdiction within s.14(3) by virtue of s.9, such as to retain the benefit of s.13 SIA?
ii) Even if so, do s.42 proceedings fall within s.9 and are they covered by s.13(2)(a)?
d) Whether the Respondent has waived its immunity in respect of s.14(2) and, assuming it is entitled to such immunity, that granted by s.13(2)(a) by reference to s.13(3) SIA.
Issue 3 Whether in the exercise of the Court's discretion the order sought should be made: it is common ground that the Court does not "act as a rubber stamp on orders made by the tribunal" (Emmott v Michael Wilson & Partners Ltd [2009] EWHC 1 (Comm) at paragraph 59 per Teare J).
Issue 1: Section 42 of the 1996 Act
"(1) The parties are free to agree that the tribunal shall have power to order on a provisional basis any relief which it would have power to grant in a final award.
(2) This includes, for instance, making –
(a) a provisional order for the payment of money or the disposition of property as between the parties . . ."
As set out in paragraph 6 above, as Mr Dunning accepts, by Article 25 of the LCIA Rules, to which the parties have agreed, the Arbitrators had power (inter alia) to make a provisional order for the payment of money. Although the heading of s.39 in the statute refers to "Power to make provisional awards", it is not in any doubt that the words of s.39 itself are what is decisive, and plainly give the Arbitrators the power to make an order for interim measures, not simply an award.
"If without showing sufficient cause a party fails to comply with any order or directions of the tribunal, the tribunal may make a peremptory order to the same effect, prescribing such time for compliance with it as the tribunal considers appropriate ".
"(1) The parties shall do all things necessary for the proper and expeditious conduct of the arbitral proceedings.
(2) this includes –
(a) complying without delay with any determination of the tribunal as to procedural or evidential matters, or with any order or directions of the tribunal. . ."
This rubric "necessary for the proper and expeditious conduct" of the arbitral proceedings is then expressly repeated in s.41 relating to the "powers of tribunal in case of party's default":
"(1) The parties are free to agree on the powers of the tribunal in case of a party's failure to do something necessary for the proper and expeditious conduct of the arbitration."
Such powers, Mr Dunning submits, are the only powers for the arbitral tribunal which the parties are free to agree.
"38. it is not at all clear why s.42 of the Arbitration Act 1996 was incorporated into the Scheme [for Construction Contracts]".
I understand that this has subsequently been amended out of the Scheme.
He concluded:
It may be that Parliament intended that the court should be more willing to grant a mandatory injunction in cases where the adjudicator has made a peremptory order than where he has not. The court should be slow to grant a mandatory injunction to enforce a decision requiring the payment of money by one contracting party to another.
39. . . I am not persuaded that I ought to exercise my discretion in favour of granting an injunction. "
Mr Dunning submits that, adopting the approach of Dyson J, in this case also the Claimants could and should have followed the course not of applying under s.42, but by way of s.44 of the 1996 Act or s.37 of the Senior Courts Act 1981 for a mandatory injunction.
i) As Mr Pollock pointed out, Dyson J was dealing with a case where the adjudicator had concluded that a sum was due under the contract which could have been the subject of an application for summary judgment. That is not the case here. It is plain that this was not a provisional award, nor an interim payment. As was emphatically stated by Mr Pollock, the Arbitrators were not, as Mr Dunning contended, "enforcing a putative substantive obligation on an interim basis".
ii) There is no purpose in there having been an application under s.44 or s.37 for a mandatory injunction, when there had been a straightforward order made by the Arbitrators, after considering the matter in great depth and hearing detailed submissions, leading them to make an order by way of interim measures. In any event, from the point of view of enforcing compliance, a Court order under s.42 and an injunction under s.44 would have the same effect (and would lead to identical or similar remedies if not complied with).
iii) Dyson J concluded that he was exercising a discretion not to make a s.42 order, not that he had no jurisdiction to make one.
iv) As is clear from s.41(5), referred to above, it provides for the making of a peremptory order where there is a failure by a party to comply with "any order or directions of the tribunal". Mr Dunning sought to point to s.41(1) as giving context. But that ignores s.40, upon which he relies for his argument, the General duty of parties. S.40(1) requires such parties to do "all things necessary for the proper and expeditious conduct of the arbitral proceedings" but that is then explained in terms in s.40(2), namely that "this includes complying with . . . any order . . . of the tribunal" [my underlining].
i) First that if the order is now to be interpreted as one which required the Arbitrators to have been satisfied that the making of such order was for the proper and expeditious conduct of the arbitral proceedings or that the Respondent's failure to comply with it was a failure to do all things necessary for the proper and expeditious conduct of the arbitration, that was not spelt out. If the basis for the Arbitrators' conclusion was that if the order were not made Dana could be 'driven from the judgment seat', the Respondent would, and it is suggested could, have addressed that point, or at any rate addressed it differently from the manner in which they made the submissions they did. I am however entirely satisfied that the parties before the Arbitrators knew what the issues were, and knew that the Claimants' case was that if the status quo ante of payment for the products were not restored there could be catastrophic effects, including the inability of the Claimants to proceed with the arbitration and/or the loss of the Claimants' rights under the 25 year contract. Opportunity to make representations to the contrary was fully taken up by the Respondent.ii) The second contention is by reference to the precise wording of the 17 October Ruling at paragraph 30. It is important to appreciate that the previous order of 10 July 2014 had not been complied with, and remained in force, and what the Arbitrators were attempting to do was to put the Claimants at least in part into the position they would have been in if the earlier order had been complied with. Mr Dunning complains that the order that was made effectively turned into a peremptory order after 30 days, without giving the Respondent any further opportunity to make submissions. However, it is quite clear that what it was, however phrased, was a peremptory order that was effectively suspended for 30 days, to give the Respondent a last opportunity to make payment before it took effect. All the submissions that could possibly have been expected had been made, and the position could only be exacerbated if there had still been no payment (as in fact was the case) after another 30 days. It is quite plain that the Respondent was given the fullest opportunity to show sufficient cause.
Issue 2
- I turn to the question of state immunity, to which the Respondent submits that it is entitled as a separate entity (see paragraph 2 above). It consequently denies that the Claimants are entitled to any relief against it and asserts its own entitlement to a declaration pursuant to CPR Part 11. The relevant sections of the SIA are as follows:
i) The starting point is s.14:"(1) The immunities and privileges conferred by this Part of this Act apply to any foreign or commonwealth State other than the United Kingdom; and references to a State include references to—(a) the sovereign or other head of that State in his public capacity;(b) the government of that State; and(c) any department of that government,but not to any entity (hereafter referred to as a "separate entity") which is distinct from the executive organs of the government of the State and capable of suing or being sued.(2) A separate entity is immune from the jurisdiction of the courts of the United Kingdom if, and only if—(a) the proceedings relate to anything done by it in the exercise of sovereign authority; and(b) the circumstances are such that a State (or, in the case of proceedings to which section 10 above applies, a State which is not a party to the Brussels Convention) would have been so immune.(3) If a separate entity (not being a State's central bank or other monetary authority) submits to the jurisdiction in respect of proceedings in the case of which it is entitled to immunity by virtue of subsection (2) above, subsections (1) to (4) of section 13 above shall apply to it in respect of those proceedings as if references to a State were references to that entity.. . .(5) Section 12 above applies to proceedings against the constituent territories of a federal State; and Her Majesty may by Order in Council provide for the other provisions of this Part of this Act to apply to any such constituent territory specified in the Order as they apply to a State.(6) Where the provisions of this Part of this Act do not apply to a constituent territory by virtue of any such Order subsections (2) and (3) above shall apply to it as if it were a separate entity."ii) Arbitration is provided for by s.9:
"(1) Where a State has agreed in writing to submit a dispute which has arisen, or may arise, to arbitration, the State is not immune as respects proceedings in the courts of the United Kingdom which relate to the arbitration."iii) S.13 provides in material part as follows:
"(2) Subject to subsections (3) and (4) below—(a) relief shall not be given against a State by way of injunction or order for specific performance or for the recovery of land or other property; and(b) the property of a State shall not be subject to any process for the enforcement of a judgment or arbitration award or, in an action in rem, for its arrest, detention or sale.(3) Subsection (2) above does not prevent the giving of any relief or the issue of any process with the written consent of the State concerned; and any such consent (which may be contained in a prior agreement) may be expressed so as to apply to a limited extent or generally; but a provision merely submitting to the jurisdiction of the courts is not to be regarded as a consent for the purposes of this subsection."iv) So far as material s.2 provides:
"(1) A State is not immune as respects proceedings in respect of which it has submitted to the jurisdiction of the courts of the United Kingdom.(2) A State may submit after the dispute giving rise to the proceedings has arisen or by a prior written agreement; but a provision in any agreement that it is to be governed by the law of the United Kingdom is not to be regarded as a submission."
i) Was the 25 year Heads of Agreement with the Claimants entered into by the KRG in the exercise of sovereign authority?ii) Was that sovereign authority its own sovereign authority, or that of Iraq (see Issue 2(b) in paragraph 16 above).
iii) If so, pursuant s.14(2)(a) do these proceedings relate to anything done by KRG in the exercise of such sovereign authority?
I shall take the first two of these questions together.
Sovereign Authority
"28. On the other hand BNC and BCC entered into what was in form a private law contract and completed it as such. There is no evidence that the sale was pursuant to any legislative or executive direction. In this respect the agreement is in a quite different position from the rest of the reorganisation which was effected by legislation. In the language of Lord Wilberforce in Congreso del Partido [1983] 1 AC 244, 263, everything was done as between vendor and purchaser: there was no exercise and no need for exercise of sovereign powers. The private law character of the transaction is not discoloured by the context in which the agreement was executed, i.e. the fact that the parties to it regarded the transfer of the shares to BCC as an obvious and necessary sequel to the statutory reorganisation. Nor is its private law character controverted by the purpose or motive behind the transaction of serving the interests of the state in bringing to fruition the completion of the reorganisation of banking in the final form which it sought. I therefore hold that BCC's entry into the completion of the agreement were commercial rather than governmental (albeit the parties to the agreement were both state-owned entities) and that accordingly BCC enjoys no immunity in respect of the transaction in question."
"9. The Kurdistan Region is governed by the Presidency of the Kurdistan Region and the KRG. The capital city of the Kurdistan Region, and the seat of the KRG, is Erbil. The KRG was formed in 1992 by the Kurdistan National Assembly (later the Kurdistan Parliament), the first democratically-elected parliament in Kurdistan (and in Iraq). The KRG exercises executive power according to the Kurdistan Region's laws, as enacted by the Kurdistan Parliament, and the Iraqi Federal Constitution. The Council of Ministers performs the KRG's executive functions. The Council is composed of the Prime Minister, the Deputy Prime Minister, and 22 further cabinet Ministers. The current government, led by Prime Minister Nechirvan Barzani, took office in June 2014.
10. The Iraqi Federal Constitution was negotiated in 2005. The Iraqi people ratified it by referendum on 15 October 2005 and it entered into force in 2006.
11. Iraq is a federal state. The Iraqi Federal Constitution describes a federal, de-centralized system of government. Sovereignty is shared between the federal government of Iraq, the KRG (which is recognised in Article 117 of the Iraqi Federal Constitution) and the various provinces or "governorates" of Iraq. . .
12. The Kurdistan Region and the KRG have a special status under the Iraqi Federal Constitution. Article 117, First of the Iraqi Federal Constitution provides:
"This Constitution, upon coming into force, shall recognize the region of Kurdistan, along with its existing authorities, as a federal region." . . .
13. Although the Iraqi Federal Constitution contemplates the creation of further regions as components of the federation, only the Kurdistan Region is recognised in the Iraqi Federal Constitution as a federal region exercising sovereign powers conferred under the Iraqi Federal Constitution.
14. The KRG is the lawful, democratically-elected government of the Kurdistan Region. It acts on behalf of the Kurdistan Region and has sovereign powers derived from and conferred by the Constitution. Article 121 First and Fifth of the Iraqi Federal Constitution provide:
"The regional powers shall have the right to exercise executive, legislative, and judicial powers in accordance with this Constitution, except for those authorities stipulated in the exclusive authorities of the federal government." . . .
"The regional government shall be responsible for all the administrative requirements of the region, particularly the establishment and organization of the internal security forces for the region such as police, security forces, and guards of the region." . . .
15. Further, Article 121, Second, states:
"In case of a contradiction between regional and national legislation in respect to a matter outside the exclusive authorities of the federal government, the regional power shall have the right to amend the application of the national legislation within that region." . . ."
"Article 111:
Oil and gas are owned by all the people of Iraq in all the regions and governorates.
Article 112:
First: The federal government, with the producing governorates and regional governments, shall undertake the management of oil and gas extracted from present fields, provided that it distributes its revenues in a fair manner in proportion to the population distribution in all parts of the country, specifying an allotment for a specified period for the damaged regions which were unjustly deprived of them by the former regime, and the regions that were damaged afterwards in a way that ensures balanced development in different areas of the country, and this shall be regulated by a law.
Second: The federal government, with the producing regional and governorate governments, shall together formulate the necessary strategic policies to develop the oil and gas wealth in a way that achieves the highest benefit to the Iraqi people using the most advanced techniques of the market principles and encouraging investment.
. . .
Article 115:
All powers not stipulated in the exclusive powers of the federal government belong to the authorities of the regions and governorates that are not organized in a region. With regard to other powers shared between the federal government and the regional government, priority shall be given to the law of the regions and governorates not organized in a region in case of dispute."
"23. It is public knowledge that since the coming into force in May 2006 of current Iraq Constitution (approved by national referendum in 2005) there have been important disagreements between the FGI and the KRG as to the control of Iraq's oil and gas resources and how the revenues derived therefrom are to be shared. In summary, the FGI and the KRG disagree on many issues including: (a) the jurisdiction and power of the KRG to award petroleum contracts; (b) the scope of cooperation between the FG1 and the KRG in relation to the management of petroleum fields; and (c) the jurisdiction and power of the KRG to export petroleum produced in the Kurdistan Region. The dispute between the FGI and the KRG is pending before the Federal Supreme Court of Iraq and has been raised in several other legal fora in response to the KRG's attempts since 2014 to undertake petroleum exports independently of the FGI.
24. . . the FGI does not recognise the petroleum contracts granted by the KRG and considers the Federal Ministry of Oil and its subsidiary agency and marketing arm, the State Oil Marketing Organisation (SOMO), as the sole entity empowered to export petroleum produced anywhere in Iraq."
The Claimants have exhibited a letter sent to Crescent by the Iraqi Federal Minister of Oil dated 17 December 2007 asserting that all contracts recently signed with the Ministry of Energy and Natural Resources of KRG without authorisation and approval of the Government of Iraq were "in violation of the prevailing Iraqi law".
"19. Article 112, First, regulates oil and gas "extracted from present fields". It gives the federal government management powers in relation to that oil and gas, subject to three important qualifications. First, the management is to be undertaken "with the producing governorates and regional governments", which I take to mean jointly and in cooperation with those governorates or governments or at least with their approval. Secondly, the joint management appears to be limited to oil and gas after it has been extracted, on which basis the management of the extraction and production process itself falls outside the federal joint management power. Joint federal power in respect of such oil and gas will be limited, presumably, to processing, transportation and export. Thirdly, revenues from present fields must be distributed in a fair manner, as stipulated in the Article.
20. On its ordinary interpretation, the term "present fields" means fields already under production. This is indicated by the word "extracted" and by the reference to "producing" governorates. The clear inference is that Article 112, First, covers oil and gas extracted from fields presently in production. By contrast, areas merely being explored, e.g. by seismic survey, are not "present fields"; indeed they are not fields at all but large tracts of territory, most or all of which will never produce any hydrocarbons. On this basis, fields not producing, developed or even discovered - and the oil and gas yet to be extracted from them - fall outside Article 112, First. They fall under the Constitution to be managed by the relevant regional government alone.
21. The time for determining whether a field is "present" or otherwise is the date of the entry into force of the Constitution (viz, 2006). I am instructed that at that date there were no producing fields in the present territory of the Kurdistan Region, i.e. no "present fields" in the sense indicated above. It follows that the provision for joint management under Article 112, First, has no application. On the other hand there are oil and gas contracts with the KRG entered into prior to the coming into force of the Constitution and providing for future exploration, appraisal and, potentially, production. Under Article 141 all such contracts, entered into by Kurdistan since 1992, are considered valid in accordance with their terms (save and to the extent that they contradict some express provision of the Constitution)."
His Executive Summary includes the following:
"(1) Article 112 of the Constitution of Iraq gives only a qualified right to the Federal Government to "undertake the management of oil and gas extracted from present fields". This right is to be exercised "with the producing governorates and regional governments", and is subject to a condition of fair distribution of revenue on a basis regulated by law. As to non-producing and future fields, there is under Article 112, Second, no federal right to manage, although regional management of such fields has to respect strategic policies to be formulated by the federal government "with" the KRG.
. . .
(3) The KRG is itself bound by Article 111: it is not open to it unilaterally and permanently to take over management of present (i.e. producing) fields in the absence of any arrangements for revenue sharing. As to fields other than present fields, the federal government has no unilateral rights under Article 112, Second, and in the absence of agreed strategic policies, the KRG is entitled to proceed in the exercise of its own constitutional authority and in compliance with its own constitutional duties."
If there was state immunity, has it in any event been lost by virtue of s.9 SIA?
i) The first question is whether the s.42 application is a proceeding in the Courts of the United Kingdom which relates to the arbitration. Direct assistance can be drawn from the judgment of Moore-Bick LJ in Svenska Petroleum referred to above. The question in that case specifically referred to an application to enforce an award as a judgment:"117. Arbitration is a consensual procedure and the principle underlying section 9 is that, if a state has agreed to submit to arbitration, it has rendered itself amenable to such process as may be necessary to render the arbitration effective . . . In our view an application . . . for leave to enforce an award as a judgment is . . . one aspect of its recognition and as such is the final stage in rendering the arbitral procedure effective. Enforcement by execution on property belonging to the state is another matter, as section 13 makes clear."Mr Dunning refers to ETI Euro Telecom International NV v Republic of Bolivia [2009] 1 WLR 665, where an application was made pursuant to s.25 of the Civil Jurisdiction and Judgments Act 1982 for a freezing order in support of the bringing of an arbitration in New York. The Court of Appeal upheld the defendant's immunity because (per Lawrence Collins LJ):". . . it is plain that there is nothing in section 9 which overrides the prohibition in section 13. Proceedings for a freezing order to preserve the position pending execution of an award are within section 13, and are not 'proceedings which relate to the arbitration' for the purposes of section 9."It is plain however that, although the Court noted that there might have been, but was not, an application under s.44 of the 1996 Act, these were proceedings external to the arbitration. The proceedings in this case however, initiated with the permission of the Arbitrators and pursuant to the 1996 Act and in order to enforce an order of the Arbitrators, plainly do relate to the arbitration.ii) Has the Respondent submitted to the Courts of the United Kingdom? This is only relevant to a sophisticated argument between the parties with regard to the effect of s.14(3). If the Respondent has submitted to the jurisdiction, as provided for by s.14(3), then though a separate entity, it is entitled to the protection of s.13. Mr Dunning submitted that it has submitted and Mr Pollock that it has not: he submitted that s.9 does not operate by virtue of any submission to the jurisdiction, but simply records a loss of immunity, as with ss. 5, 6, 7 and 8 SIA. If Mr Pollock be right, then s.14(3) does not engage, and thus, given that by virtue of s.9 SIA the Respondent has lost its immunity, and it is not a State, and so is thus not automatically entitled to s.13 protection, it would seem that as a separate entity in such circumstances it would not have the benefit of s.13. There is no direct authority on this point, and the silent assumption that s.13 would apply even where s.9 applies in, for example, Svenska Petroleum can be explained by the fact that the defendant in that case was a State, not a separate entity. However Mr Dunning draws my attention to academic authority that consent to submit to arbitration constitutes a submission to any proceedings brought in the United Kingdom Courts in relation to such an arbitration (Fox & Webb The Law of State Immunity (3rd Ed) 188 and Dickinson: State Immunity at 4.069). It seems to me clear that it cannot have been intended to exclude a separate entity agreeing to arbitration from the protection of s.13, and I have no doubt that s.14(3) should be so construed.
S.13(2) SIA
i) Mr Dunning relies on the words of Dyson J in Macob, which I have set out in paragraph 23 above. Dyson J described a s.42 order as a mandatory injunction in paragraph 35 and in paragraph 38 (3 times), and in paragraph 36, although he contrasted a s.42 order with an injunction granted pursuant to s.37 of the Supreme (now Senior) Courts Act 1981, he again described a s.42 order as a "mandatory injunction to enforce a payment obligation". He plainly deprecated the use of such an order in the field of building contracts adjudication, not least in carrying with it the potential for contempt proceedings and, as I have said in paragraph 23 above, I understand that a s.42 order is no longer available within the Scheme for Construction Contracts. It is not clear whether there was any argument before him based upon any distinction between a s.42 order and a mandatory injunction. None appears in the course of his judgment: all that is said in paragraph 33 is that "there was some limited discussion as to whether, s.42 apart, the appropriate procedure was by way of writ and an application for summary judgment, or by way of a claim for a mandatory injunction", so that it at least looks as though in the course of argument a s.42 order was not being equated with a mandatory injunction. However such was the decision of a Judge who was then in charge of the new Technology and Construction Court, albeit a first instance Judge.ii) Mr Pollock however relies upon the decision of the Court of Appeal, Soleh Boneh International Limited v Government of the Republic of Uganda [1993] 2 Lloyd's Law Rep 208 CA, in which Staughton LJ gave the judgment, with which Neill and Roach LJJ agreed. The Ugandan Government complained that an order requiring them to provide security of US$5 million, in return for obtaining an adjournment of enforcement proceedings, was an injunction, and relied upon s.13(2)(a). Its Counsel had pointed out that a copy of the order was endorsed with a penal notice, directed at the High Commissioner of Uganda in the United Kingdom personally. Staughton LJ accepted at 213 the Defendant's contrary "robust" submission that the order was "plainly not an injunction". He concluded that "in the context of s.13(2)(a). . . I would not hold that a simple order for the payment of money from no specified source is an injunction". In case he was wrong, he varied the order, but his conclusion was in my judgment a binding finding of the Court of Appeal, and one directly applicable to this case.
Waiver
"The KRG waives on its own behalf and that of the KRG any claim to immunity for itself and assets"
It seems clear that the second reference to KRG must be a reference to KRI. These words, though concise, are robust. It is common ground that a waiver must be construed strictly and sensibly, and, as is stated in s.14(3) a written consent "may be expressed so as to apply to a limited extent or generally". There is no issue between the parties that this waiver of immunity clause removes from the Respondent any adjudicative immunity, as it was referred to in the course of the hearing, nor was any issue raised at this hearing (though KRG reserved its position), because of the reference to assets, as to any immunity against execution. But what Mr Dunning submits is that it does not waive the immunity against injunctive relief (if that is, contrary to my conclusions above, what s.42 constitutes) or indeed against the other forms of relief specified in s.13(2), specific performance and recovery of land or other property. Therefore the question for me is whether the wording of the waiver in this case would exclude immunity against what one might call 's.13(2)(a) relief', including relief by way of injunction:
i) Mr Pollock refers to the decision of Saville J in A Company Ltd v Republic of X [1990] 2 Lloyds Law Rep 520. In that case there was a waiver to the effect: "The Ministry of Finance hereby waives whatever defence it may have of sovereign immunity for itself or its property (present or subsequently acquired)". A Mareva injunction was sought against the defendant, which claimed sovereign immunity. Saville J concluded that the waiver "does amount to the agreement and consent of the State that its property can be made the subject of a Mareva injunction" (at 523). Mr Pollock submits that this is directly persuasive. Mr Dunning points out: (i) that Saville J may have been affected by the fact that, as he specifically stated at 523, the contract of which this waiver formed part was "undoubtedly a commercial bargain between the parties": (ii) that a Mareva injunction does have an obvious impact upon a defendant's property, such that it could be said to fall expressly within the wording: (iii) that Saville J said (also at 523) "it is not, of course, necessary to decide whether clause 6 does amount to consent to other forms of injunction".
ii) Mr Pollock refers to Sabah Shipyard (Pakistan) v Pakistan [2002] EWCA Civ 1643. The waiver clause there provided that the defendant "waives any right of immunity which it or any of its assets . . . now has or may in the future have in any jurisdiction . . . and . . . consents generally in respect of the enforcement of any judgment against it . . . to the giving of any relief or the issue of any process in connection with such proceedings (including without limitation, the making, enforcement or execution against or in respect of any of its assets)". In that case the Court of Appeal upheld an anti-suit injunction "to maintain the status quo pending judgment" (paragraph 23). Again this was a clause contained in what Waller LJ described as "an ordinary commercial transaction"; it is plain however that the Court concluded that, albeit not specifically mentioned in the relatively long list of examples, there was waiver of immunity in respect of an anti-suit injunction. Mr Dunning refers however to Arab Banking Court v International Tin Council [1986] Int LR 1 where the Defendant was found to be immune from a Mareva injunction. There was there a very general clause submitting to the jurisdiction of the English Courts, and Article 6(1)(a) of the International Tin Council (Immunities and Privileges) Order of 1972 provided that the Council was immune from suit and legal process except to the extent that "it shall have expressly waived its immunity in a particular case". By reference to the then wording of Dicey & Morris, The Conflict of Laws (10th Ed) Vol 1 p. 176 to the effect that "waiver of immunity from jurisdiction in civil or administrative proceedings does not imply waiver of immunity in respect of execution of the judgment, for which a separate waiver is required", Steyn J concluded that what he called the "narrower construction" of the jurisdiction clause should be accepted.
"The immunity from injunctive relief and execution is distinct from immunity from suit, and applies even if one of the jurisdictional exceptions applies. Thus, even though a State is not immune as respects proceedings relating to a commercial transaction, the State cannot be enjoined from breach of the contract. But the immunity from injunctive relief and execution is subject to two important exceptions. First, such relief may be given or process may be issued with the written consent (which may be contained in a prior agreement) of the State [Footnote reference is made to the Tin Council case and to Sabah where "waiver of immunity in a contractual submission to the English jurisdiction was held to extend to an anti-suit injunction restraining proceedings in Pakistan"]. It has been held that a waiver of immunity in relation to property will allow a freezing injunction to be made against a foreign State, but that a contractual waiver of immunity from execution will not be regarded as extending to diplomatic premises." [There is a footnote reference to Saville J's judgment in A Company, with a note that on the latter (but not the former) point there was criticism by FA Mann in 1991 107 LQR 362].
Issue 3
i) Mr Pollock submits that the Court should be supportive of the Arbitrators and not frustrate their intention. Mr Dunning, mindful of his arguments which I have addressed in Issue 1 above, submits that this should only be where the Arbitrators have acted for the purpose of the proper and expeditious conduct of the arbitration. As appears above, I am in any event satisfied that that was indeed the purpose of the Arbitrators.ii) Both sides accept that, subject to the question of change of circumstances, the court should not re-visit the argument before the Arbitrators provided that, as I am satisfied that they did here, the Arbitrators have addressed the correct questions. Mr Pollock submits that reconsideration should only arise where there has been an error of law or a serious irregularity by the Arbitrators i.e. something analogous to where the Court could intervene by reference to ss.67 or 68 of the 1996 Act. That does not seem to me to put the point in any different way.
iii) I am entitled to consider any material change of circumstances.
i) It is suggested that there has been a change of circumstance by virtue of the fact that the Respondent's counterclaims have been considered to be sufficiently arguable to be the subject of debate at the 21 September hearing as to whether they amount to or constitute a set-off. It is clear however that, not least because the Arbitrators had previously concluded that the counterclaims were sufficiently arguable not to be disposed of summarily, there has been no material change in the approach of the Arbitrators in accordance with their conclusions in the 10 July Ruling and the 17 October Ruling. The question which the Arbitrators resolved was the restoration of the status quo, irrespective of the defence of set-off, i.e. the requirement that the previous arrangement of the Respondent paying for what was lifted should be restored.ii) Mr Dunning submits that, on the evidence before me, there has been a change of circumstance in relation to the circumstances of the Claimants. I am satisfied, however, that the evidence before me does not show any improvement in the financial position of Dana (or of the SPV, Pearl). Indeed it seems clear that such financial position is more precarious because since the 17 October Ruling, as appears in paragraphs 14 and 15 above, the Respondent has shut off the source of payment to the Claimants which it had temporarily permitted.
iii) Mr Dunning also relies on the position of the Respondent. The Respondent, which appears to continue to be deprived of resources from the FGI, has a continuing, and, no doubt, increasing, responsibility for arming the Peshmerga, its military arm, and coping with an increasing flood of refugees, quite apart from a budget deficit. Mr Dunning refers to paragraph 25 of the 17 October Ruling (set out in paragraph 11 above) in which the Arbitrators, while sympathising with the plight of the KRG, considered that they were "in no position to estimate the significance of these momentous events", and that they lay outside the matters to which the Tribunal could conventionally have regard. The issue is whether, then or now, there are financial circumstances, possibly deteriorating such circumstances, which either the Arbitrators should have taken, or I should now take, into account. Mr Dunning places reliance on an Order dated 24 August 2015 by the Prime Minister of Kurdistan, which recorded a determination by the Council of Ministers that, in the light of the "strong and competing demands on the Kurdistan Region's financial resources and the limitations on the financial resources available to the KRG", the absence of a budgetary law for the two years of 2014 and 2015, the volatile national security situation and the continued budgetary dispute between the KRG and the FGI, "there are no funds available to allocate" to payment of the peremptory Order, and that "funds could not be paid to the above named companies without prejudicing the urgent demands on the KRG's financial resources and priorities". This, Mr Dunning submits, is a change of circumstance, equivalent to a subsequent Act of State, such as is referred to by Lord Hope in Kuwait Airways Corporation v Iraqi Airways Co (Nos 4 and 5) [2002] 2 AC 883 at 1108, being a "legislative or other governmental act . . . of a recognised foreign state or government within the limits of its own territory [which] the English Courts will not adjudicate upon, or call into question". I agree however with Mr Pollock that he is not inviting me to take either of those courses. The Respondent's Council of Ministers has concluded that there "are no funds available to allocate to the Payment". The Arbitrators however plainly took notice, as do I, that in fact, had it so chosen, the Respondent could have secured payment to the Claimants without actually laying out any money themselves (see paragraphs 16 and 17 of the 17 October Ruling, set out in paragraph 11 above). The fact remains that, as set out in paragraph 14 above, since the 17 October Ruling and indeed since the Order by the Prime Minister of 24 August 2015, the Respondent has made and authorised very substantial payments to other international oil producers, but not to the Claimants. It is also noteworthy that the Respondent plainly was in a position to pay substantial monies to the Claimants in September 2015 when, as set out in paragraph 15 above, stating that it was only prepared to make payments if the Arbitrators agreed to the unorthodox step there proposed. There is no basis for any case, whether by way of change of circumstances or otherwise, for my taking a different view about the balance of justice in relation to the Respondent than was taken by the Arbitrators.
i) Now is not the time to speculate as to what remedy may be available on a contempt application, if such becomes necessary.ii) No assumption should be made at this stage that the Respondent will in fact fail to comply with an order of the Commercial Court as done in relation to the orders of Arbitrators.
iii) This is the only way to enforce the Arbitrators' orders, which will otherwise remain uncomplied with.
iv) He submits that it is more than likely that a public declaration by this Court of failure to comply and of non-payment will be of effect upon the Respondent, given its role and profile internationally.
Conclusion