BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Vinergy International (PVT) Ltd v Richmond Mercantile Limited FZC [2016] EWHC 525 (Comm) (15 March 2016) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2016/525.html Cite as: [2016] EWHC 525 (Comm) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Rolls Building, 7 Rolls Buildings Fetter Lane, London EC4A 1NL |
||
B e f o r e :
____________________
VINERGY INTERNATIONAL (PVT) LIMITED |
Appellant |
|
- and - |
||
RICHMOND MERCANTILE LIMITED FZC |
Respondent |
____________________
Richard Mawrey QC (instructed by Duval Vassiliades Solicitors) for the Respondent
Hearing dates: 25 February 2016
____________________
Crown Copyright ©
Mr. Justice Teare :
"secretly contracted for the supply of cargo from Hazel and carried those transactions out by three shipments over a period of three months. On any view, the amount of cargo was not de minimis and this breach, alone, entitled Richmond to treat Vinergy as in repudiatory breach and the contract as terminated and the Tribunal so finds and holds (see paragraphs 54 and 59(c) and (d) of the Tribunal's reasons).
"shall exclusively purchase its entire Product import requirements for the Indian market from [Richmond]".
"will therefore purchase the Product from the third party source and will supply the same directly to" [Vinergy] .. [Richmond] "will add its agreed margin of US$10 per mt."
"It is the intention of the parties that the Activities will be performed by [Richmond] on a "cost plus" basis and that therefore, [Richmond] will not charge [Vinergy] anything more than the cost it incurs for the Activities plus the amount due to it pursuant to clause 2.3 and [Richmond] will furnish to [Vinergy] invoices and other documents in support of such costs it incurs for the Activities. In the event it is discovered that [Richmond] has breached the provisions of this clause, (1) [Richmond] shall within 3 days of demand from [Vinergy], reimburse the excess to [Vinergy] and (2) without prejudice to the foregoing or to any other right or remedy available to [Vinergy] under this Agreement or at law, [Vinergy] shall, notwithstanding clause 17 of this Agreement, be entitled to forthwith terminate this Agreement."
"17.1 Either party may terminate this Agreement immediately upon:
17.1.1 failure of the other party to observe any of the terms herein and to remedy the same where it is capable of being remedied within the period specified in the notice given by the aggrieved party to the party in default, calling for remedy, being a period not less than twenty (20) days; .
17.1.2 the other party suffering an Insolvency Event ."
"18.2 Termination of this Agreement, including but not limited to Termination in accordance with Clause 17, will not prejudice the rights of action or remedy of [Vinergy] or [Richmond] in respect of any antecedent breach by the other party of any of such party's obligations under this Agreement."
"Richmond pleaded termination under Clause 17 as well as at common law but in their arguments before the Tribunal they placed the emphasis of their argument on the latter. It was clear that some of the claims, such as those for non-payment, were capable of remedy and the notice of termination on 20th July 2012 was premature given that the initial notice to remedy was served on 2nd July and Clause 17.1.1 requires the parties to give notice of not less than 20 days to remedy before termination. This is, however, of limited relevance since Richmond also have common law rights to terminate on the ground of a repudiatory breach and these rights (and rights in respect of antecedent breaches generally) are expressly preserved by Clause 18.2 of the MSA."
The first question of law
"Whether Richmond was able to rely on an unhindered common law right to terminate the MSA by reason of a repudiatory breach so as to completely bypass the notice and remedy requirements in the termination clause."
"Those provisions themselves must in my judgment form part of an appreciation of the benefit the parties were intended to derive from the contract. Thus circumstances otherwise within the scope of the termination provisions but falling short of the precise terms would in my judgment not give rise to the right to terminate at common law for the very reason that the parties agreed when and how such circumstances should have that consequence: see Lockwood Builders v Rickwood."
" in deciding whether by its conduct a party evinces an intention not to be bound by the terms of the contract, the way in which parties agreed to treat breaches within the terms of their contract must be a factor to take into account. In particular, if a breach of a term had to reach a degree of seriousness before a contractual termination clause could be applied, it is unlikely that a breach which was less serious would, by itself, amount to a repudiatory breach."
"In my view it is wrong to treat the right to terminate in accordance with the terms of the contract as different in substance from the right to treat the contract as discharged by reason of repudiation at common law. In those cases where the contract gives a right of termination they are in effect one and the same."
"Equally, the fact that for a particular breach the contract provided that there should be a period of notice to remedy the breach would indicate that the breach without the notice would not, in itself, amount to a repudiatory breach."
"My own view -- returning to the facts of the instant case -- is that cl 2 and the common law right to accept a repudiatory breach can exist side by side, but only in circumstances where the contractor displays a clear intention not to be bound by his contract, for example, by walking off the site long before completion (as suggested during the course of argument by Hirst LJ) or, by way of further illustration, failing to comply with plans in a very fundamental way, for example, by not building a third storey when contractually bound to do so. But such cases are far removed from the instant one. On the facts of this case, I, for my part, would be prepared to hold that cl 2 created the only effective way in which Mr Rickwood could determine this agreement. It is difficult to understand why the clause should be there at all if that were not the true position."
"In my judgment, this cl 2 did impliedly preclude Mr Rickwood from terminating the contract on the facts of the present case otherwise than by the exercise of his rights under cl 2 since the complaints made fell squarely within the scope of cl 2, ie complaints as to the quality of materials and workmanship. However, cl 2 would not have done so in relation to breaches outside the ambit of cl 2, eg. by Mr Ryan walking off the site when the works were still substantially incomplete."
"1366. I do not read those decisions [Lockland Builders v Rickwood and Amoco v BAOL] as laying down any hard and fast rules. Rather, in deciding whether by its conduct a party evinces an intention not to be bound by the terms of the contract, the way in which parties agreed to treat breaches within the terms of their contract must be a factor to take into account. In particular, if a breach of a term had to reach a degree of seriousness before a contractual termination clause could be applied, it is unlikely that a breach which was less serious would, by itself, amount to a repudiatory breach. Equally, the fact that for a particular breach the contract provided that there should be a period of notice to remedy the breach would indicate that the breach without the notice would not, in itself, amount to a repudiatory breach.
1367. In this case, the fact that there was a failure to meet a Major Milestone must be viewed in the light of Clause 16.2 which provides:
"Notwithstanding Clause 16.1, if a Milestone (with the exception of the first and last Milestones) is not Accepted under Clause 8.2 on the relevant date the parties have agreed that the Contractor shall not be deemed to be in material breach of the Agreement until three months after the relevant date and the provisions of Clause 11 or Clause 22.2 shall not apply to such delay prior to that date."
1368. The effect of this is that until three months after the relevant milestone date there is not a material breach of the Prime Contract. In the light of that provision, I consider that there could be no question of a repudiatory breach in relation to acceptance of a Milestone until that period of three months had elapsed. In terms of material breach, then clause 22.2 of the Prime Contract provides:
"Termination for Material Breach
In the event of any material breach of this Agreement by either party, the other party may give to the party in breach notice specifying the same, requiring its remedy and stating that this Agreement may be terminated if the material breach in question is not remedied in accordance with this Clause 22.2. If the party in receipt of such notice fails to remedy the breach within 30 days of receipt of the notice the party who served the notice may by further notice, forthwith terminate this Agreement, whereupon the provisions of Clauses 22.3 and 22.4 shall apply."
1369. That merely deals with a case where there has been a material breach and would cover breaches which could have a whole range of seriousness. I do not consider that this means that before any breach can be treated as being repudiatory it must be the subject of a notice requiring the breach to be remedied and cannot lead to termination unless there has been a failure to remedy the breach within 30 days. Take, for instance, a case where a party says that it will no longer perform the contract or acts in such a way. I do not consider that in such a case the innocent party must give notice and wait 30 days before it can terminate the contract at common law based on a repudiatory breach. In the case of less serious breaches, the failure to give any notice may well mean that the breach in itself cannot be treated as repudiatory but a failure to comply with a notice to remedy the breach may be.
1370. In the present case, the conduct has to be viewed in relation to the Prime Contract and the Letter of Agreement. It must be remembered that the Letter of Agreement was entered into because EDS was in breach of its obligations under the Prime Contract. The provision of resources, completion on time and proper performance were all matters which were of importance in relation to the Letter of Agreement.
1371. However, I have come to the conclusion that viewed objectively neither the breaches alone nor the combination of breaches amounted to a repudiatory breach of the Prime Contract, as varied. The contemporaneous correspondence is inconsistent with that view and the delay to the milestones had not reached a stage where I consider that it amounted to a repudiatory breach. As I have said most of the failures on the behalf of EDS reflected delay in performance."
The second ground of appeal
The third and fourth grounds of appeal
"While the Tribunal has upheld the Respondent's case that it is entitled to discretionary rebates, that item was the subject of a without prejudice agreement subject to which the Claimant provided an agreed fixed discount of US$5 per metric ton to the Respondent pending a decision in arbitration. The purpose of that agreement was to retain the status quo between the parties pending that decision. Although the tribunal has now determined that issue in favour of the Respondent and made a finding that an additional sum is due to the Respondent as a result, the Claimant is not thereby in breach of its obligation to perform the MSA."
"At an early stage the parties were in dispute on the issue of rebates. They had intended to put the matter to an arbitrator for early determination, pending which they agreed on a without prejudice basis that Richmond would provide a discount of US$5 pmt but that this would be adjusted later in accordance with the arbitrator's determination. In the event this process was not progressed at that early stage and neither party took the dispute to arbitration at that time. Hence it was that Richmond provided a discount of US$5 pmt to Vinergy from shipment 21 in January 2010 forwards, irrespective of the level of rebate earned or received by Richmond from Pasargad. That discount resulted in a total credit of US$153,238.47 to Vinergy."
Conclusion