BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Connex South Eastern Ltd v MJ Building Services Group Plc [2004] EWHC 1518 (TCC) (25 June 2004) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2004/1518.html Cite as: [2004] EWHC 1518 (TCC), [2004] BLR 333 |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CONNEX SOUTH EASTERN LIMITED |
Claimant |
|
- and - |
||
MJ BUILDING SERVICES GROUP PLC |
Defendant |
____________________
Mr. Anthony Speaight Q.C. (instructed by Fenwick Elliott) for the Defendant
Hearing dates : 21st, 22nd June 2004
____________________
Crown Copyright ©
Judge Richard Havery Q.C:
(1) that there is no agreement between the claimant and the defendant as alleged in the defendant's notice of adjudication dated 24th February 2004 whose terms, or whose material terms, are recorded in writing as required by section 107 of the Act; and/or(2) that the defendant no longer has any statutory right to adjudication under section 108 of the Act; and/or
(3) that the defendant's said notice of adjudication is an abuse of process.
(1) Has there been an agreement to which the claimant and the defendant have been parties and which is an agreement "in writing" within the meaning of s.107 of the Act?(2) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication under s.108 of the Act on 24th February 2004 if the agreement has previously been discharged by the acceptance of the claimant's repudiation?
(3) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication under s.108 of the Act notwithstanding the letter of agreement dated 11th February 2002?
(4) If the answers to questions (1), (2) and (3) are all yes,
a. Is the defendant's notice of adjudication dated 24th February 2004 an abuse of process?b. If so, what is the consequence?
You are invited to tender for the Phase 9 installation works consisting of 50… stations across the Connex South Eastern and South Central Networks…..Due to the nature of the works and short programme involved, it is our client's intention to let all 50… stations to a single contractor….. A formal written order from our client will be placed with the successful tenderer…..All works to be carried out in accordance with the master Specification for the installation of CCTV.
The phase 9 CCTV contract
Since Govia's takeover of South Central, the Client has worked with you to restructure the scope of works to reach a mutually acceptable solution.
The final shape of the contract is now clear. We list below the works instructed to date and the budgeted works awaiting instruction.
We would now like to formalise your mutual agreement with the Client that the works below now represent the full extent of the "Phase 9" contract. The forecast value of Works that have been instructed or will be instructed totals £937,847.
Please note that we do expect to be able to instruct some additional works on the Epsom Downs line, which might have a value of around £60,000 but for budgetary reasons this is not certain and you should regard this as a bonus.
We would be grateful if you would please sign the bottom of this letter and return to me in order to confirm your agreement.
The letter was marked as being copied to Mr. Blaquiere – South Central Facilities. Mr. McAnallen signed the letter at the bottom, as requested.
Towards the end of 2001 and beginning of 2002 I did however continue to deal with Eric Smith of Condes in relation to the South Central element of Phase 9. By February 2002 we had completed work on all the stations in the South Central franchise to their satisfaction, and South Central had agreed our account. In order to record this, I signed Condes' letter of 11th February 2002. This counter-signed letter refers only to stations in the South Central area.
Negotiations continued throughout early 2002 with [MJ] as to what was to happen with the remainder of Phase 9. Some time during 2002 [MJ] completed to the satisfaction of South Central Limited all the works which they were being required to carry out within the [SC] franchise area and the account of MJ had been agreed. Therefore, on 11th February 2002 Eric Smith wrote to [MJ] in order to confirm these matters.
The dispute referred to is [MJ's] claim for payment from [SC] and/or [SE] of damages…..in respect of the contract for the execution of installation works at 50 stations in the Connex South Eastern and Connex South Central franchise areas, known as the "Phase 9 Works". The dispute arose following the refusal/failure by [SE] and [SC] to make payment [of the sum of £362,914.12 plus interest] on request by [MJ] and as recorded in correspondence from Fenwick Elliott to [SE] and [SC].
(1) Has there been an agreement to which the claimant and the defendant have been parties and which is an agreement "in writing" within the meaning of s.107 of the Act?
Answer: Yes.
(2) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication under s.108 of the Act on 24th February 2004 if the agreement has previously been discharged by the acceptance of the claimant's repudiation?
Answer: Yes.
(3) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication under s.108 of the Act notwithstanding the letter of agreement dated 11th February 2002?
Answer: Yes, but only to the extent indicated in paragraph 32 above.
(4) If the answers to questions (1), (2) and (3) are all yes,
a. Is the defendant's notice of adjudication dated 24th February 2004 an abuse of process?
Answer: No.
b. If so, what is the consequence?
Answer: Not applicable.