BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> S & W Process Engineering Ltd v Cauldron Foods Ltd [2005] EWHC 153 (TCC) (28 January 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/153.html Cite as: [2005] EWHC 153 (TCC) |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
S & W PROCESS ENGINEERING LTD |
Claimant |
|
- and - |
||
CAULDRON FOODS LTD |
Defendant |
____________________
Mr Piers Stansfield (instructed by Osborne Clarke for the Defendant)
Hearing Dates: 6 and 7 December 2004
____________________
Crown Copyright ©
HIS HONOUR JUDGE PETER COULSON Q.C.
[1] INTRODUCTION
[2] BACKGROUND TO THE CONTRACT
"In order to estimate the target or ceiling price of the overall Project, it is intended to prepare an unambiguous specification and tender document for specific and key areas of the re-development project".
Section 5 of the same document introduced the possibility of 'Partnering Concepts', pursuant to which a target price would be indicated and any savings against that price would be shared by the parties and any overspend against that price would be funded by S&W.
"S & W confirmed that the orders would be placed on a fixed price basis with all variations carefully managed and approved prior to any financial commitment. Subsequently, and on the above terms, the ITB Package will be issued."
"Following completion of Phases 1 and II of the pre-live phase Feasibility Studies, the following report will detail the transition from "Orders of Costs" through the analysis of competitive tenders towards presenting the optimum costs pertaining to the successful redevelopment of Cauldron Foods' facilities at Bristol.
For the purposes of presenting realistic and accurate costs, it has been subsequently agreed that specific areas providing "uncertainties" or risk areas to the project budget should be accompanied by a contingency factor. Typically, the level of contingency applied would be 5% unless specifically stated otherwise. All areas including contingency have been highlighted on the attached report ….".
[3] THE CONTRACT
"Commercial Arrangements – Phase 1(a)
Commercial Tracking: Open Book (Target Price)
In order to identify all project costings under the 'Open Book' framework, we would propose to use the following unique reference numbers against the areas detailed. Subsequent phases of the project (following official notification) will also be managed on this basis. The main invoice reference number will be utilised on all financial correspondence between both parties (invoices etc).
Main Invoice reference number 87508(accounts use only)
Builders Works 87509
Fryer System 87510
Tofu Filter Press 87511
Sausage Cooking Machine 87512
Mezzanines and structural steel works 87513
Preliminaries 87514
Temporary Dry Goods Store 87515
Against the previously listed reference numbers, monthly interim statements of account will be produced detailing all expenditure, forecasts to complete and accruals. All under spends will be transferred to the Project Account and overspends (if applicable) justified (in writing) prior to any financial commitment. Final invoices will be amended to suit the actual costs incurred.
All payments unless specifically described otherwise are to be made within 28 days of the date of submission of the invoice".
"Thank you for now confirming your instructions to proceed with phases 1(a) and (b) of the Expansion Project. We look forward to receiving written confirmation of phase 1(b) work shortly.
For reference the Target Order Values for both phases are as follows:
Phase 1(a) £1,102,706.80 plus VAT
Phase 1(b) £3,496,402.01 plus VAT
We would propose to introduce a system to track the procurement phases of the project in line with the Datum Point Budget as issued within Feasibility Study III. Such a system would incorporate the production of Authorisation for Capital Expenditure Certificates. Where estimated costs consist mainly of labour services, we would propose to issue interim evaluations and forecasts to complete (as reported on the monthly financial report).
As explained during out meeting, this will effectively enable the overall project of circa £4.6 million to be managed as approximately 56 significantly smaller value contracts, hence reducing the financial risks through individual and detailed costs analysis.
In summary, all requests for Capital Purchases within the previously pre-defined Project Budget would be authorised by yourselves by signing an Authorisation for Capital Expenditure Form. An example of the format of this form is attached for reference and review.
The forms will be sequentially numbered to record all proprietary plant and services purchases and any overspends or under spends to the budget. Any significant variance to the budget will be discussed prior with rationales provided.
The forum for presenting the Authorisation for Capital Expenditure Certificates will be the main weekly Project Review Meeting on site at Cauldron Foods.
In addition, the monthly financial reports tracking the costs of the project against the Target costs will now include a reference to the Authorisation for Capital Expenditure Certificate.
Any variances to the Project scope and from the Datum Point Budget will be fully discussed in the weekly Project Review Meetings and agreements minuted for future reference".
"As outlined in your letter dated 12 June 2002 all capital purchases within the above defined project budget will be authorised by Cauldron Foods by the signing of an appropriate Capital Expenditure Form".
"Any increases to the scope of supply or potential overspends to the Target Costs would be fully discussed prior to any financial commitment and again be authorised through the Authorisation for Capital Expenditure System. Similarly underspends or scope reductions ie savings to Project Budget would be declared and funds accrued".
[4] VARIATION TO THE CONTRACT
[5] LATER EVENTS
[6] PRELIMINARY ISSUE 1.1/FORMATION OF CONTRACT
"How is the contract formed and, in particular, was it made orally and/or is it contained in or evidenced by writing?"
[7] PRELIMINARY ISSUE 1.2/EXPRESS AND IMPLIED TERMS
"What were the express and/or implied terms of the Contract?"
The express terms can only arise from the documents set out in Section 3 above; the implied terms are said to arise as a matter of law. I deal with each category of terms below.
Express Terms
(a) S&W would carry out and procure the work on an open book cost plus basis, subject to the other terms of the Contract.
(b) The base cost of the work to Cauldron would be £4,599,108.81, being the total of the Target Order Values (as set out in the Datum Point Budget issued within Feasibility Study III), subject to the other conditions of the Contract.
(c) Any proposed changes to or increases in the scope of supply or potential overspends on items within the Target Order Values would be discussed at the weekly Project Review Meetings with agreements as to changes/increases in scope and/or any additional expenditure being minuted for future reference.
(d) Any such agreed changes to or increases in scope of supply or agreed overspends on items within the Target Order Values would then be the subject of an Authorisation for Capital Expenditure Certificate.
(e) Any such agreed changes to or increases in scope of supply or potential overspends on items within the Target Order Values would be recorded in the monthly interim statements ("Cost Reports") produced by S&W.
(f) The project would be managed as 56 small value contracts in order to reduce the financial risks through individual and detailed cost analysis.
(g) Invoices were to be raised by S&W on the basis expressly set out in the letter of 21 June 2002 and would be paid within 28 days of the submission of those invoices.
Variation to the Express Terms of the Contract
Implied Terms
(a) The goods supplied would be of satisfactory quality.
(b) If goods were selected by S&W for a particular purpose then those goods would be fit for that purpose.
(c) S&W would carry out the works with reasonable skill and care.
(d) S&W would perform its professional duties with the skill and care of a project manager experienced in construction projects.
[8] PRELIMINARY ISSUE 2/TARGET ORDER VALUES
"What is the relevance and effect "if any" of the Target Order Values referred to in the letter of 12 June 2002?"
[9] PRELIMINARY ISSUES 3 AND 4/AUTHORISATION OF WORK AND EXPENDITURE
"Was the existence of a signed Authorisation for Capital Expenditure Form a condition precedent to the Claimant's right to be paid?"
The parties have agreed that the answer to this question is No. I consider that the parties are right for two separate reasons. First, I do not think, taking the relevant letters as a whole, that the completion of an ACE Certificate was a condition precedent to payment even prior to the variation to the Contract in practice. That can be tested in this way. As set out above, the financial commitment to any change to or increase in the scope of supply or overspends on items within the Target Order Values would be made by Cauldron at the weekly meetings. If, say, at such a meeting Cauldron agreed to an increase in the scope of supply and were told that that increase would cost £10,000, to which they also agreed, and those agreements were minuted and typed up, then the absence of an ACE Certificate, even before the Contract was varied, would be of no account. In my example the financial commitment by Cauldron was triggered by their oral agreement to both the increase in scope and its attendant cost. That commitment would be minuted and would be binding on the sides. In any event, since they were the party responsible for approving an ACE Certificate, Cauldron could hardly rely on the absence of such an approved certificate as a defence to a claim for the £10,000. Accordingly, I find that the relevant authorisation of work and costs came –as it was always going to- at the weekly meetings.In addition, of course, that position was merely underlined when the use of the ACE Certificate was scrapped by agreement.
"If the answer to Issue 3 is no, by what means was work/expenditure under the contract to be authorised?"
The answer is as set out above. Additional work and additional expenditure were to be authorised by an express oral agreement, minuted by S&W, and reached at the weekly Project Review meetings.
[10] PRELIMINARY ISSUE 7/QUANTUM MERUIT
[11] SUMMARY