BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Jim Ennis Construction Ltd v Premier Asphalt Ltd [2009] EWHC 1906 (TCC) (24 July 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/1906.html Cite as: [2009] 41 EG 116, [2009] CILL 2745, 125 Con LR 141, [2009] EWHC 1906 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
MANCHESTER DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
1 Bridge Street West, Manchester, M60 9DJ |
||
B e f o r e :
____________________
JIM ENNIS CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
PREMIER ASPHALT LIMITED |
Defendant |
____________________
Mr Charles McDermott (of Bermans LLP, Liverpool) for the Defendant
____________________
Crown Copyright ©
Introduction
Factual background
(1) The Claimant was employed by Taylor Woodrow as subcontractor to construct the road works to the main entrance of a Tesco supermarket at Centenary Way, Burnley, Lancashire. Taylor Woodrow was the main contractor and the employer was Lancashire County Council ('LCC').
(2) By an order dated 9 April 2002 the Claimant sub-sub-contracted the supply, laying and rolling of the bituminous macadam surfacing to the Defendant.
(3) The resultant contract contained no express adjudication provision, so that by virtue of s.108(5) and s.114(4) HGCRA the adjudication provisions of Part I of the Scheme for Construction Contracts ('the Scheme') were incorporated as implied terms of the contract.
(4) On 29 May 2002 LCC's Engineer wrote to Taylor Woodrow complaining about the base course laid by the Defendant. The Claimant removed it and on 18 June 2002 the Defendant replaced it. At that stage there was no agreement as to who, if anyone, should bear the costs associated with this work.
(5) Some months later, on 17 December 2002, the Defendant made what appears to have been its final application for payment, within which was included a claim for £16,821.94 (net of 2.5% discount) for the cost of the replacement works. The Claimant refused to pay that claim, asserting that the Defendant was not entitled to be paid for the replacement works because they were necessary to remedy the Defendant's original defective work. Furthermore, the Claimant also claimed to be entitled to deduct from the Defendant's final account its cross-claims for loss and damage alleged to have been caused by the laying of the original base course. The total amount deducted from the Defendant's final account amounted to £38,647.22.
(6) The Defendant did not take any steps by way of adjudication or litigation to challenge that deduction at the time, but almost 6 years later, on 15 September 2008, it referred the dispute about the deduction to adjudication. This was of course within the applicable 6 year limitation period for a claim in contract founded on the non-payment of its final application for payment, but was outside the 6 year period for the Claimant to advance a claim for damages for breach of contract in relation to the alleged defects in the Defendant's original work.
(I should record that the Claimant, rightly in my opinion, does not advance a case to the effect that by waiting until September 2008 the Defendant was deliberately seeking to secure the benefit of a limitation defence in any subsequent litigation; that would be to attribute to the Defendant a Machiavellian degree of anticipation of future events.)
(7) An adjudicator was duly appointed and on 13 November 2008 he gave his decision, which upheld the Defendant's claim and required the Claimant to pay the principal sum of £38,647.22 together with interest thereon of £14,829.10, a total of £53,476.32.
(8) Although the Claimant did not accept the adjudicator's decision, it recognised that by virtue of paragraph 23(2) of the Scheme the decision was binding on it and that it was obliged to comply with the decision until the dispute was finally determined by legal proceedings, arbitration (if applicable) or agreement, so that it paid the £53,476.32 to the Defendant.
(9) On 18 December 2008 the Claimant sent a letter of claim to the Defendant pursuant to the Pre-Action Protocol for Construction and Engineering Disputes, advising of its intention to seek a final determination of the dispute by legal proceedings. There being no agreement, on 15 April 2009 the Claimant issued the instant proceedings in the Manchester Technology and Construction Court.
Procedural history
(1) The cause of action in contract arises pursuant to an implied term. As pleaded, the Claimant contends that it was an implied term of the contract that where a dispute arises which is referred to adjudication then the 'losing party' who complies with the adjudicator's decision and pays sums to the winning party is entitled to reclaim those sums in legal proceedings, or (as pleaded as an alternative formulation) to re-argue the dispute in subsequent court proceedings and, if successful, to be repaid all sums paid.
(2) On a true analysis, the cause of action arises not earlier than either the date of the adjudicator's decision or the date of payment in compliance with that decision.
(3) In the alternative, on a true analysis the cause of action is restitutionary, which is a claim for equitable relief, and s.36 Limitation Act operates to disapply s.5 and s.9 in such case
(4) In the further alternative, by waiting until after 6 years from the date of its breach before referring the dispute to adjudication the Defendant has either waived its right to plead limitation as a defence or is estopped from relying on the limitation defence.
The respective submissions
(1) repeated its case that the claim was one for damages for breach of contract occurring before 29 May 2002, to which s.5 Limitation Act applied;
(2) contended in relation to any alternative claim in restitution that since the adjudicator decided that the Defendant was entitled to have been paid its December 2002 application in January 2003, any cause of action ran from that date;
(3) contended that the Claimant was not compelled by law to comply with the adjudicator's decision, and did so voluntarily, as opposed to awaiting enforcement proceedings in the TCC.
(1) The decision of the adjudicator gives rise to an independent cause of action, separate and distinct from the underlying cause of action in respect of the dispute submitted to adjudication.
(2) The implied term contended for by the Claimant either ousts the provisions of the Limitation Act by agreement or creates a new cause of action at the time of payment in compliance with the adjudicator's decision.
(3) There is a cause of action in restitution, which does not arise until the date of payment in compliance with the adjudicator's decision, or alternatively to which there is no applicable limitation period.
(4) By referring the dispute to adjudication more than 6 years after the date of the breaches complained of by the Claimant the Defendant is estopped from raising the limitation defence in the subsequent court proceedings.
(5) Unless the Claimant is able to challenge the adjudicator's decision, his rights under Article 6(1) ECHR will have been breached, and the relevant statutory provisions should be construed in such a way as to avoid such a state of affairs from arising.
(6) On the facts of this case, there is nothing that the Claimant could have done to protect itself from the result contended for by the Defendant, and to find for the Defendant in this case would throw the construction industry into turmoil by encouraging parties to wait until just before the limitation period before referring disputes to adjudication, the fear of which might itself result in parties in a position similar to the Claimant in this case issuing defensive proceedings for declaratory relief purely to guard against the risk of this happening. It would also be inconsistent with the approach taken by the courts to date in robustly enforcing the decisions of adjudicators on the grounds that however rough and ready the process and however wrong the decision there is no injustice because the losing party can always challenge the decision (and hence recover his money) by subsequent legal proceedings or arbitration.
Discussion
Adjudicator's decision gives rise to an independent cause of action
'14. The nature of enforcement of adjudicators' decisions is contractual. Clause 39A.7.2 here requires the parties to 'comply with the decision of the Adjudicator'. The Adjudicator's decision may be right or wrong but, whether right or wrong, it is to be complied with. The failure … to comply with the decision of the Adjudicator and pay the sum ordered was a breach of Clause 39A.7.2.
15. Thus, the cause of action upon which Ringway had to rely and indeed did rely in their Particulars of Claim is the breach of Clause 39A.7…
16. Thus … the date when the cause of action arose was the date when Vauxhall failed to honour the Adjudicator's decision. The Adjudicator ordered Vauxhall to pay the sums which he decided were due no later than 21 August 2007. Accordingly, by 22 August 2007, the cause of action had arisen upon which Ringway not only did rely but had to rely.'
Implied Term
(a) It must be reasonable and equitable;
(b) It must be necessary to give business efficacy to the contract so that no term will be implied if the contract is effective without it;
(c) It must be so obvious that it goes without saying;
(d) It must be capable of clear expression;
(e) It must not contradict any express term of the contract.
Limitation period applicable to the claim founded on the implied term
Restitution
Limitation period applicable to the claim in restitution
Estoppel
Conclusion