BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Jim Ennis Construction Ltd v Combined Stabilisation Ltd [2009] EWHC B37 (TCC) (20 November 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/B37.html Cite as: [2009] EWHC B37 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
MANCHESTER DISTRICT REGISTRY
TECHNOLOGY & CONSTRUCTION COURT
B e f o r e :
sitting as a Judge of the High Court
____________________
JIM ENNIS CONSTRUCTION LIMITED | Claimant | |
and | ||
COMBINED STABILISATION LIMITED | Defendant |
____________________
Mr Andrew Singer (instructed by DWF LLP) for the Defendant
____________________
Crown Copyright ©
JUDGE RAYNOR QC
The facts
"A payment will be processed in conjunction with our expected payment from BLL. We anticipate (subject to your agreement), that we would be in a position to release payment to you on, if not before, the completion of the current calendar month.
Retention Value would be reduced to 1.5% in conjunction with the payment detailed above (Resultant retention amount £10,500.00)."
On 22 July 2009 Mr Duffy offered an increased amount of £705,000.
"We wish to confirm that the agreement excludes the issue with respect to damage to the CSL roller which is subject to a separate settlement.
Please can you confirm back your acceptance of this and that the sum due for payment within the next 7-10 days (10 days the maximum duration) is £142,901.13".
It will be noted that Mr Duffy in his e-mail did not provide any confirmation regarding the time for payment. His explanation for this is set our in paragraph 32 below.
It will be noted that that letter made no reference to Mr Hart's e-mail of 24 July, albeit, as I have stated, that a copy of that e-mail was attached to the covering letter.
"CERTIFICATE OF FINAL AGREEMENT FOR
Unity College, Burnley
Sub Contract Reference: C796/SC/003
This is to certify that we have carefully examined the final statement of account, which shows the total value of these works at:
£707,500.00 (Seven Hundred and seven thousand, five hundred pounds) Nett
We agree accordingly that this sum is accepted by us to include all omissions, additions, variations, claims and other amendments requiring cost adjustment properly effected under the terms of the sub-contract, and is full and final settlement of all sums due to us under the terms of the above mentioned sub-contract. This is subject to us retaining as our responsibility, liability for all defects, shrinkages, or other faults occurring in the sub-contract works, in accordance with the terms of the sub-contract, the Main Contract and at Common Law."
"Further our discussion yesterday we require your acknowledgement of CSL liability in respect of the damage to the gas main laid by PN Daly on behalf of Bovis Lend lease. We are not in a position to confirm a final cost for the remedy of same but as an interim measure we propose to adjust the Final Account Figure to £701,000.00. Upon receipt of a definitive charge from BLL this Final Account figure will be adjusted accordingly".
"We wish to note that the Final Account Agreement expressly states that the "Agreement" is subject to caveats as attached to the letter with respect to payment of sums due and dates of payment.
We note that Ennis have failed to comply with either of the requirements and therefore request a meeting in order to reassess the account status and gain resolution of the account for works undertaken at Unity".
In evidence Mr Duffy stated that he inferred from this e-mail that Mr Hart was saying that the final account agreement was off.
"We note from the email and subsequent telephone conversation that Ennis we not be releasing sums due with respect to the previously agreed Final Account to the above stated project.
As a direct consequence of Ennis's failure we [will] comply with the agreed terms of the Final Account CSL consider that the settlement is now null and void".
"Our Client asserts that the figure referred to in the Certificate of Final Agreement did not accurately reflect the value of the work and indeed there had been ongoing discussions with your Client prior to agreement being reached.
Agreement was eventually reached due to our Client being under economic constraints and as such attached certain conditions to the agreement.
We enclose herewith copy letter from our Client which states that the Certificate was only signed on the basis that the email which was enclosed was incorporated. This clearly made the agreement conditional.
The conditions were that the final sum of £143,901.13 was transferred within 7-10 days. This meant that payment should have been made no later than 4th August 2009. Payment did not arrive until 7th August 2009 and the sum of money paid in was short by £6000 of the agreed sum.
On that basis as the conditions of the agreement were not adhered to the Certificate of Final Agreement is void and therefore our Client is entitled to re-evaluate the cost of works carried out".
It will be seen that this letter is premised on an agreement having been made, albeit conditionally.
The issues
(a) It asserts that no binding contract was concluded between the parties because their agreement was incomplete, in that no agreement was reached on an essential term, namely the time for payment.
(b) It is asserted that CSL's e-mail and attachments sent on 28 July 2009 amounted to a counter offer, which was not accepted by JEC, who did not accept CSL's proposals as to the time for payment or the amount to be paid.
(c) Alternatively, it is alleged that if there was a binding final account agreement:
(i) the agreement to accept the final account value, on its true construction, was conditional, being an agreement by CSL to accept the sum of £707,500 as the final account value in return for the payment (not merely the promise of payment) of £142,901.13; that JEC wrongfully repudiated that agreement, which repudiation was accepted by CSL, thereby determining the agreement as to the final account; or
(ii) that it was a condition of such agreement that the sum of £142,901.13 would be paid in full, and that in breach of that condition only £135,538.25 was paid with JEC making it clear that it refused to pay the balance. CSL alleges that as a result of the breach of condition it was entitled to determine and be discharged from the final account agreement.
Incomplete agreement
Counter offer
(a) by implication, as already stated, the agreement made provision as to the time for payment; and
(b) it is common ground that £142,901.13 was payable under the final account agreement (paragraph 24(6)(a) of the Particulars of Claim).
Conditional agreement and repudiation
(a) Whether its initial refusal to pay the balance entitled CSL to be discharged from the agreement; and
(b) Whether JEC was guilty of a repudiatory breach of contract as alleged by CSL.
"8-02 Given the normal meaning, the purpose and effect of a compromise, the natural inference is that the common intention of the parties is that the compromise will henceforth govern their legal relationship in connection with the disputes in which they had been engaged and that, accordingly, those disputes would still be regarded as "dead" even in the event of breach of the compromise. In these circumstances, it is submitted that recourse to the original claims will not be permitted unless, upon a true construction of the compromise, it is clear that this is what the parties intended. In this context, whilst the matter is primarily one of construction, the nature of the consideration furnished by the party answering the claims being made by the claimant will operate as a pointer.
Promised or actual acts
8-03 In the discussion on consideration, attention was drawn to the fact that the usual consideration furnished in the context of a compromise is that promised or actual forbearance of one party to pursue a claim against another in return for some promised or actual act by the other. If the promised or actual forbearance to pursue the claim is construed as being in return for the promised performance of some act by the other party, such agreement will be regarded as one involving the immediate discharge of the claim. Where, however the promised or actual forbearance is construed as being in return for the actual performance of some act by the other party, the claim forborne will not be discharged until such performance takes place. The propositions may be illustrated by reference to two simple examples:
(a) A agrees not to pursue his claim against B in return for B's promise to pay A the sum of £1,000 within 28 days;
(b) A agrees not to pursue his claim against B if B pays to A the sum of £1,000 within 28 days.
If B fails to make the payment within the period specified, A's remedy under (a) would merely be to sue B for damages upon the compromise. Under (b) he would have the option of accepting B's repudiation of the agreement, treating himself as discharged from further performance of his obligations and reasserting his original claim, or of affirming the compromise and suing upon it.
8-07 Generally speaking, therefore, an agreement of compromise will discharge all original claims and counterclaims unless it expressly provides for their revival in the event of breach. Where a party wishes to be able to revive his original claim in the event of the other party's failure to comply with his obligations under the compromise, he would be well-advised to insist that a term to that effect should be incorporated."
(a) As stated by Lord Keith (at page 294)
"In deciding the issue of repudiation which arises in this appeal, the guiding principle is that enunciated by Lord Coleridge, CJ in Freeth v Burr, LR 9 CP 208, 213:
"… in cases of this sort, where the question is whether the one party is set free by the action of the other, the real matter for consideration is whether the acts or conduct of the one do or do not amount to an intimation of an intention to abandon and altogether to refuse performance of the contract".
The matter is to be considered objectively:"
(b) As stated by Lord Scarman (at page 298)
"To be repudiatory, the breach, or threatened breach, must go to the root of the contract. If an anticipatory breach is relied on, the renunciation must be "an intimation of an intention to abandon and altogether to refuse performance of the contract"; or, put in other but equally clear words, "the true question is whether the acts and conduct of the party evince an intention no longer to be bound by the contract": Lord Coleridge CJ in Freeth v Burr LR 9 CP 208, 213."
(c) Invoking a provision of a contract in good faith but in error is not in general a repudiatory act: see the Woodar case itself.
(a) £135,538.25 of the agreed sum (ie 95%) was paid and paid promptly (within 10 days of the making of the agreement).
(b) I am satisfied, as stated by Mr Duffy, that JEC (acting by him) considered in good faith that the provisions of the final account agreement (and in particular the provisions set out in its final sentence of the Certificate of Final Agreement ) entitled it to apply the set off. Although as a matter of law I do not consider that the withholding of the sum was in accordance with the contract (because in my judgment the sum of £142,901.13 was to be paid thereunder, as indeed averred by JEC – see paragraph 24(6) of the Particulars of Claim) I do not consider that the application of the set off at the same time as paying 95% of the agreed sum amounted to a repudiatory act.
Breach of condition
Conclusion