BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Forest Heath District Council v ISG Jackson Ltd [2010] EWHC 322 (TCC) (22 February 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/322.html Cite as: [2010] EWHC 322 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Forest Heath District Council |
Claimant |
|
- and - |
||
ISG Jackson Limited |
Defendant |
____________________
Mr Piers Stansfield (instructed by Prettys) for the Defendant
Hearing dates: 3rd February 2010
____________________
Crown Copyright ©
The Hon. Mr. Justice Ramsey:
Introduction
"I am persuaded that the change to a site painting philosophy for the pool hall steelwork resulted in the requirement for a Birdcage Scaffold in the pool hall to carry out the protective paint finish.
In addition, I am persuaded that the root cause of this change in philosophy was the late finalisation of the steelwork design.
In my view the delay caused by the requirement for the Birdcage Scaffold is an Employer responsible event, and as such is a Relevant Event under the Contract".
" that the decision to paint the pool hall steelwork on site rather than off site was taken by the Defendant in October 2006 and was not taken as a result of the late finalisation of the steelwork design."
Background
"1. The original steel frame scheme was drawn and issued for approval on 3rd August 2006.
2. Comments regarding this issue were not received from WSP until 27th September 2006, which we are now in the process of looking at and subsequent changes are being actioned as necessary.
3. Revised GA's will be issued in due course.
4. Also on the 8th September 2006 we received from WSP up-dated drawings incorporating cladding rails added to elevation against the existing building. We confirm we are also in the process of adding these into the structure.
5. WSP have confirmed further revised drawings are due showing additional cold rolled.
Finally you have confirmed more changes are in the pipeline, however these cannot interrupt the manufacture and therefore will be carried out as site work."
(1) The steelwork design did not change after 17 July 2006, except to accommodate Jackson's request to substitute Leighs Paints.
(2) Jackson's Information Required Schedule confirms that they had all the information and Jackson did not ask at any stage for the colour of the top coat for the pool steelwork.
(3) Whilst the Council contends that Revision A of the specification was issued to Jackson in July 2006, even if it was issued on 29 August 2006 as Mr Mason contends, that was over five weeks before Jackson asked WSP for an instruction permitting the substitution of the specified paint with Leighs Paints.
(4) WSP responded promptly to Jackson's request, issued on 5 October 2006, to change the steelwork paint.
(5) No complaint was made by Jackson at the time.
Part 8 Proceedings for a declaration
"Accordingly, so far as the CPR are concerned, the power to make declarations appears to be unfettered. As between the parties in [this action], it seems to me that the court can grant a declaration as to their rights, or as to the existence of facts, or as to a principle of law, where those rights, facts or principles have been established to the court's satisfaction. The court should not, however, grant any declarations merely because the rights, facts or principles have been established and one party asks for a declaration. The court has to consider whether in all the circumstances, it is appropriate to make such an order
…
It seems to me that, when considering whether to grant a declaration or not, the court should take into account justice to the claimant, justice to the defendant, whether the declaration would serve a useful purpose and whether there are any other special reasons why or why not the court should grant the declaration."
"i) The correct approach to the question of whether to grant negative declarations was one of discretion rather than jurisdiction. ii) The use of negative declarations should be scrutinised and their use rejected where it would serve no useful purpose, but where such a declaration would help ensure that the aims of justice were achieved, the court should not be reluctant to grant a negative declaration.
iii) Before a court can properly make a negative declaration, the underlying issue must be sufficiently clearly defined to render it properly justiciable."
The Application for a Declaration
Is there a substantial dispute of fact?
"7. By September 2006 the project was already in substantial delay, as a result of contamination issues (asbestos and hydrocarbons). Despite this delay, the steelwork design had been provided late and was incomplete.
8. At the Site Progress Meeting held in 20 September 2006, as I recall, there was a general consensus between those present that the urgency to procure the steelwork was the overriding consideration. The consideration as to whether the steelwork would be painted offsite or on site was discussed but very much secondary. It was accepted that the instruction to place the order for the steelwork at that point in conjunction with the urgency to deliver to site, the incomplete design and uncertainty as to the paint specification made on site painting inevitable.
9. The reasons why the order for the steelwork was placed by Jackson, without shop painting of the top coat was that:
(1) There was a pressing need, as a result of late design information relating to the steelwork, to procure steelwork and to deliver it to site as the erection of the steelwork in Grids 1-7 (non-pool hall area) was the first steel operation on the critical path
(2) The design of the steelwork was incomplete making variations inevitable. It appeared it was likely that some form of access would be required after the initial erection of steelwork to deal with changes;
(3) At the time the instruction to order the steelwork was given (20 September 2006) there was uncertainty as to the paint specification generally. As a consequence, the top coat colour for the steelwork had not been specified.
There was an additional factor that may have encouraged the Council to instruct Jackson to place the order in September 2006, namely the rising price of steel due to high demand from China and the Far East.
Is this an appropriate case for the Declaration sought?
(1) | 26 November 2007 to 7 January 2008: | Erection of Birdcage Scaffold; |
(2) | 7 January 2008 to 7 February 2008: | Scaffold used to inspect primer; |
(3) | 7 February 2008 for three weeks: | Painting of steelwork; |
(4) | 16 weeks: | Changes to wall render; |
(5) | 16 May 2008 to 11 June 2008: | Dismantling of Birdcage Scaffold. |
Conclusion