BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Stratton & Anor v Patel & Anor [2016] EWHC 2031 (TCC) (03 August 2016) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/2031.html Cite as: [2016] EWHC 2031 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
(Sitting as a Deputy High Court Judge
____________________
JOHN MICHAEL STRATTON (2) MUHAMMAD AZEEM KHAN-SHERWANI |
Claimant |
|
- and - |
||
MAHESH SHANTILAL PATEL - and - MP BUILDING LIMITED |
Defendant |
____________________
Mr Matt Hutchings (instructed by Kidd Rapinet) for the Defendant
The Third Party was not represented
Hearing dates: 1 July 2016
____________________
Crown Copyright ©
Mr Roger ter Haar QC :
"The claim arises partly out of a fire which occurred on the 22nd February 2010 causing damage to the demised premises which rendered the premises unusable, but also out of leaks at and into the premises through the roof and blockage of an internal drain. All of these problems were caused by the manner in which the Third Party carried out a contract between itself and the Defendant for redevelopment of the parts of the Defendant's building which were not demised to the Claimants.
In summary the claims put forward by the Claimants were as follows:
(1) Damages in the amount of the cost of remedial works (finally estimated at about £310,000 for all works other than works to the kitchen plus just under £100,000 in respect of the kitchen);
(2) Alternatively an order for specific performance in respect of those works;
(3) Loss of profits in an amount of £180,000 plus continuing losses;
(4) Exemplary damages;
(5) Damage to goodwill in the sum of about £30,000;
(6) Costs of re-launching the restaurant premises.
In the event, I accepted that the Claimants were entitled to have the premises including the kitchen back into a useable state of repair, albeit I adjourned the assessment of damages to see whether the Defendant complies with an undertaking to carry out those works. If and to the extent that the Defendant does not do so (and I have no reason to suppose that he will not) then not only will the Defendant be liable for the consequences of his breach of undertaking, but substantial damages may well be awarded for the costs of these works. If, as is to be expected, the Defendant does comply with his undertaking, damages under this head are likely to be nil.
I rejected the claims for los of profits, loss of goodwill and exemplary damages.
It remains to be seen whether the Claimants will relaunch the business."
"The assessment of the quantum of damages (if any) under the following heads is adjourned with liberty to the Claimants to apply to fix a date for the assessment:
1.1 The quantum of any residual reinstatement works to the premises
1.2 The quantum of any residual reinstatement works to or supply of the kitchen equipment and customer serving and accommodation facilities
1.3 The quantum of any business re-launch expenses and loss of income during the re-launch period and the period to be paid if any."
"On condition that the Claimants shall provide all reasonable access and cooperation, to procure that the reinstatement works described in the schedule hereto and any agreed variation thereto agreed between Mr. Birchall and Mr. Moor are diligently carried out."
"(a) The Claimants' expert Mr. Greg Moor be permitted to file and serve a statement report with regard to the progress report of Mr. Birchall dated 12.02.16 by 26.02.16.
(b) The Parties file and serve witness statements of fact relied upon with regard to the Assessment of Damages by 5.00 p.m. on the 11.03.16.
(c) That there be disclosure of all such documents upon which each party relies with regard to the Assessment of Damages by 5.00 p.m. on 01.04.16 and inspection if so sought by 22.04.16.
(d) Permission to the Claimants to obtain a detailed report from the Claimants' Accountants RDP Newmans detailing the Claimants losses of income from 01.08.14 to include details of the expenses and loss of income arising during any re-launch period, such report to be filed and served by 18.03.16.
(e) The parties shall file and serve Skeleton Arguments by 08.04.2016.
(f) The matter be listed for Assessment of Damages hearing with a time estimate of 1-2 days on the first open date after 08.04.2016.
(g) Alternatively that the matter be set for case management directions on the first open date after 28.02.16 with a time estimate of 2 hours."
The Claimants sought orders as follows:
"(h) The Defendant is in breach of his Undertaking in failing to carry out the remedial works, whether in accordance with the Agreed Specification of Works and/or by 12.02.2015 alternatively within a reasonable time;
(i) That the Defendant is in breach of Paragraphs 1 and/or 3 and/or 4 of the Order dated 01.08.2014 in that he failed:
(i) To take all necessary steps and to carry out the detailed works set out in the Agreed specification to reinstate the Claimants' restaurant premises;
(ii) To take all necessary steps and carry out all such works to reinstate the Claimants' installed and free standing kitchen equipment and customer serving and accommodation facilities
Whether by 12.02.2015 or within a reasonable time;
(j) That upon the court determining that the re-launch period for the Claimants' business is a minimum of 8 weeks, the Defendants pay to the Claimants damages together with interest thereon, as follows:
(i) The sum of £241,329.23 being the Claimants' loss of income from 01.08.2015 until 04.02.16.
(ii) A sum to be assessed for the Claimants' loss of income from 13.02.15 until payment.
(iii) A sum to be assessed being the cost of residual reinstatement works pursuant to paragraph 2.1 of the Order dated 01.08.2014.
(iv) A sum to be assessed being the cost of the residual reinstatement works or supply of kitchen equipment pursuant to paragraph 2.2 of the Order dated 01.08.2014.
(v) A sum to be assessed being the Claimants' re-launch expenses.
(vi) The sum of £40,456.55 being the Claimants' loss of income during the re-launch period or such other sum as the Court may determine.
(vii) The Defendant shall pay the Claimants' cost of the proceedings for the Assessment of Damages."
"By way of further directions, we would seek your confirmation that:
(a) No further progress reports are required from the experts;
(b) Following agreement between the experts that the reinstatement works had been completed, handover took place on 15 December 2016;
(c) The Claimants have now relaunched their business;
(d) The parties have reached agreement as to full and final settlement and are bound by the terms of that agreement; and
(e) Our client, the Defendant, has complied with the terms of his Undertaking throughout and, barring payment of any further reasonable fees from Mr. Moor (an invoice is awaited in this regard), the Defendant is now ready to be discharged from his Undertaking."
"Post trial the Claimants have chosen to pursue directions and additional claims arising from or incidental to the Defendant's reinstatement works. These are now termed "the Claimants' post-trial claims". The Defendant is making an application in respect of the following:
I To strike out the Claimants' post-trial claims;
II Alternatively, summary judgment thereon;
III The Defendant seeks to be discharged from his Undertaking to the Court herein;
IV Alternatively the Defendant requests that the following be dealt with as Preliminary Issues:
(i) The nature and effect of the Defendant's Undertaking to the Court it is the Defendant's case that this undertaking does not confer upon the Claimants any rights to damages. [On the facts the Defendant strenuously denies any breach of Undertaking. He prays in aid both the contents of the report dated 12 February 2016 of his expert Mr. Richard Birchall and also the report dated 3 March 2016 from the Claimants' expert Mr. Gregory Moor.]
(ii) The Claimants' claim for loss of profits is no less than an attempt to relitigate the finding at paragraph 434 of the Judgment of Roger ter Haar Q.C. sitting as a Deputy High Court Judge in the High Court of Justice delivered on 1 August 2014. This held that the Claimants were not running a profit-making business.
(iii) Insofar as the Claimants may have had any claims for damages respecting relaunch costs, outstanding works or matters incidental thereto these were settled and comprehensively so on 3 February 2016.
(iv) In any event the Defendant:
(a) Has already paid or agreed to pay a sum in respect of relaunch expenses and has voluntarily provided the Claimants with a rent-free and insurance-free period the combined effect of which far exceeds the amount of any possible claim in respect of relaunch; and
(b) Has/is timeously and competently attending to all snagging items arising from the reinstatement works aforesaid."
Application to discharge the Undertaking
"Further to receipt of notice of completion of the works following the end of the Defects Rectification Period, a joint inspection was undertaken on the 23 June 2016 with Mr. Birchall to confirm that all remaining works had been completed. There was agreement that all works were complete with the exception of two items:
(i) a residual issue with the Air Handling Unit (AHU) controller and
(ii) lack of clarity in the labelling of the electrical consumer unit."
Re-Launch Expenses and Loss of Income During the Re-Launch Period
The Other Claims for Loss of Profits
i) Loss of profits from the date of the fire to the date of judgment;ii) Loss of profits from the date of judgment until the end of a reasonable period for execution of the remedial works;
iii) Loss of profits from the date when remedial works should, with due expedition have been completed and the date when they were in fact substantially completed.
"Where the existence or non-existence of a cause of action has been decided in earlier proceedings, to allow a direct challenge to the outcome, even in changed circumstances and with material not available before, offends the core policy against the re-litigation of identical claims."
" an undertaking to the court, unless the circumstances are such that it has some collateral contractual operation between the parties concerned, confers no personal right or remedy upon any other party. The giver of the undertaking assumes thereby an obligation to the court but nobody else.
.
Where the giving of an undertaking to the court forms part of a bargain between the parties to litigation, the giver of the undertaking may assume not only an obligation to the court but also a contractual obligation to the other party to the bargain to observe or implement the undertaking ."
Conclusion