BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Joseph Gleave & Son Ltd v Secretary of State for Defence [2017] EWHC 238 (TCC) (17 February 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/238.html Cite as: [2017] WLR(D) 116, [2017] EWHC 238 (TCC), [2017] PTSR 607 |
[New search] [Printable RTF version] [Buy ICLR report: [2017] PTSR 607] [View ICLR summary: [2017] WLR(D) 116] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Joseph Gleave & Son Limited |
Claimant |
|
- and - |
||
Secretary of State for Defence |
Defendant |
____________________
Sarah Hannaford QC and Ewan West (instructed by Treasury Solicitor) for the Defendant
Hearing date: 3 February 2017
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1 INTRODUCTION
2. THE FACTUAL BACKGROUND
3. SPEED IN PROCUREMENT CASES
"Whereas the opening-up of public procurement to Community competition necessitates a substantial increase in the guarantees of transparency and non-discrimination; whereas, for it to have tangible effects, effective and rapid remedies must be available in the case of infringements of Community law in the field of public procurement or national rules implementing that law…
Whereas, since procedures for the award of public contracts are of such short duration, competent review bodies must, among other things, be authorized to take interim measures aimed at suspending such a procedure or the implementation of any decisions which may be taken by the contracting authority; whereas the short duration of the procedures means that the aforementioned infringements need to be dealt with urgently…"
"Article 1
Member States shall take the measures necessary to ensure that, as regards contracts…decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in the following Articles 2-2F of this Directive…
Article 2
1. The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers to:
…
(b) either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure…"
"General time limits for starting proceedings
92. (1) This regulation limits the time within which proceedings may be started where the proceedings do not seek a declaration of ineffectiveness.
(2) Subject to paragraphs (3) to (5), such proceedings must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.
(3) Paragraph (2) does not require proceedings to be started before the end of any of the following periods:—
(a) where the proceedings relate to a decision which is sent to the economic operator by facsimile or electronic means, 10 days beginning with—
(i) the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;
(ii) if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;
(b) where the proceedings relate to a decision which is sent to the economic operator by other means, whichever of the following periods ends first:—
(i) 15 days beginning with the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;
(ii) 10 days beginning with—
(aa) the day after the date on which the decision is received, if the decision is accompanied by a summary of the reasons for the decision; or
(bb) if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;
(c) where sub-paragraphs (a) and (b) do not apply but the decision is published, 10 days beginning with the day on which the decision is published.
(4) Subject to paragraph (5), the Court may extend the time limits imposed by this regulation (but not any of the limits imposed by regulation 93) where the Court considers that there is a good reason for doing so.
(5) The Court must not exercise its power under paragraph (4) so as to permit proceedings to be started more than 3 months after the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.
(6) For the purposes of this regulation, proceedings are to be regarded as started when the claim form is issued…
Starting proceedings
94. (1) Where proceedings are started, the economic operator must serve the claim form on the contracting authority within 7 days after the date of issue.
(2) Paragraph (3) applies where proceedings are started—
(a) seeking a declaration of ineffectiveness; or
(b) alleging a breach of regulation 87, 95 or 96(1)(b) where the contract has not been fully performed.
(3) In those circumstances, the economic operator must, as soon as practicable, send a copy of the claim form to each person, other than the contracting authority, who is a party to the contract in question.
(4) The contracting authority must, as soon as practicable, comply with any request from the economic operator for any information that the economic operator may reasonably require for the purpose of complying with paragraph (3).
(5) In this regulation, "serve" means serve in accordance with rules of court, and for the purposes of this regulation a claim form is deemed to be served on the day on which it is deemed by rules of court to be served.
Contract-making suspended by challenge to award decision
95. (1) Where—
(a) a claim form has been issued in respect of a contracting authority's decision to award the contract,
(b) the contracting authority has become aware that the claim form has been issued and that it relates to that decision, and
(c) the contract has not been entered into,
the contracting authority is required to refrain from entering into the contract.
(2) The requirement continues until any of the following occurs—
(a) the Court brings the requirement to an end by interim order under regulation 96(1)(a);
(b) the proceedings at first instance are determined, discontinued or otherwise disposed of and no order has been made continuing the requirement (for example in connection with an appeal or the possibility of an appeal).
(3) This regulation does not affect the obligations imposed by regulation 87.
Interim orders
96. (1) In proceedings, the Court may, where relevant, make an interim order—
(a) bringing to an end the requirement imposed by regulation 95(1);
(b) restoring or modifying that requirement;
(c) suspending the procedure leading to—
(i) the award of the contract, or
(ii) the determination of the design contest,
in relation to which the breach of the duty owed in accordance with regulation 89 or 90 is alleged;
(d) suspending the implementation of any decision or action taken by the contracting authority in the course of following such a procedure.
(2) When deciding whether to make an order under paragraph (1)(a)—
(a) the Court must consider whether, if regulation 95(1) were not applicable, it would be appropriate to make an interim order requiring the contracting authority to refrain from entering into the contract; and
(b) only if the Court considers that it would not be appropriate to make such an interim order may it make an order under paragraph (1)(a).
(3) If the Court considers that it would not be appropriate to make an interim order of the kind mentioned in paragraph (2)(a) in the absence of undertakings or conditions, it may require or impose such undertakings or conditions in relation to the requirement in regulation 95(1).
(4) The Court may not make an order under paragraph (1)(a) or (b) or (3) before the end of the standstill period.
(5) This regulation does not prejudice any other powers of the Court."
"27. Mr Lewis submits that neither the loss nor the risk of loss was caused by the breach of regulation 21(3) until Jobsin was excluded from the tender process on 17th November. I reject that submission for the following reasons. First, it gives no meaning to the words "risks of suffering loss or damage" in regulation 32(2). It seems to me that those words are of crucial significance. They make it clear that it is sufficient to found a claim for breach of the regulations that there has been a breach and that the service provider may suffer damage as a result of the breach. It is implicit in this that the right of action may and usually will arise before the tender process has been completed.
28. That brings me to the second reason. It would be strange if a complaint could not be brought until the process has been completed. It may be too late to challenge the process by then. A contract may have been concluded with the successful bidder. Even if that has not occurred, the longer the delay, the greater the cost of re-running the process and the greater the overall cost. There is every good reason why Parliament should have intended that challenges to the lawfulness of the process should be made as soon as possible. They can be made as soon as there has occurred a breach which may cause one of the bidders to suffer loss. There was no good reason for postponing the earliest date when proceedings can begin beyond that date. Mr. Lewis suggests that there is such a reason. He points out that if, in a case such as this, the limitation period runs from the date of publication of the tender documents, it will be possible for the contracting authority to rule out any real possibility of a challenge by issuing an invitation in breach of the regulations and then not taking any further steps in relation to tenders until after the three months period has expired. I confess that I find this an unlikely state of affairs, but I can see that it might conceivably happen. If it did, a service provider who wished to bring proceedings might have a good case for an extension of time: it would all depend on the facts. In my view, this cannot affect the plain meaning of regulation 32(2). I would therefore hold that the right of action which Jobsin asserts in the present case first arose on or about 14th August 2000. The essential complaint which lies at the heart of the proceedings is that there was a breach of regulation 21(3), in that the Briefing Document did not identify the criteria by which the DOH would assess the most economically advantageous bid."
"41. In the case of the Regulations, there is undoubtedly a public interest purpose in the requirement for promptness as is shown by the European Directives, pursuant to which the Regulations were made. It is self-evident and also appears from other decisions on comparable regulations that, in the procurement context, the need for speed in raising complaints and dealing with them is vital, since the whole process of procurement is otherwise rendered uncertain and hopelessly disrupted. The need for a rapid and effective review and enforcement is predicated on the need for prompt complaint. Without prompt complaint and review, lists of contractors may be drawn up and the tendering process progressed or even completed, with alteration of position by other contractors, as well as the utility company…
53. As to prejudice to STW, the Court of Appeal decisions in Jobsin (ibid) at paragraph 40 and Matra v Home Office [1999] 3 AER 562 (per Buxton LJ at page 1663) make it plain that it is not necessary to adduce particular evidence of prejudice to third parties. As Dyson LJ says, it is inherent in the process itself that delay may well cause prejudice to third parties as well as detriment to good administration. One of the major purposes of proceedings is to enable procurement procedures to be corrected and for the Court to review and enforce any remedy required. Although Holleran's claim is now limited to damages and the claim for any other relief has been abandoned, the effect of a damages claim on a complex contracts process and its unsettling disruption of it is prejudice enough."
4. PARTICULAR FEATURES OF THIS CASE
5. EXPEDITION: PRINCIPLES
(a) The issue as to whether to grant expedition, and if so how much and on what terms, is a matter essentially for the discretion of the judge: see Wembley National Stadium v Wembley (unreported, Court of Appeal, 28 November 2000). It is partly a matter of principle and partly a matter of practice: see Daltel v Makki [2004] EWHC 1631 (Ch).(b) All cases should be brought to court as soon as reasonably possible, consistently with the overriding objective: see Daltel.
(c) In exercising its discretion, the court has to take into account the requirements of other litigants: see Law Debenture Trust Corp PLC v Elektrim SA [2008] EWHC 2187 (Ch).
(d) The applicant must satisfy the court that there is an objective urgency to deciding the claim: see Daltel.
(e) The procedural history in any case is a relevant factor to take into account: see CPC Group Limited v Qatari Diar Real Estate Investment Company [2009] EWHC 3204 (Ch).
6. EXPEDITION: ANALYSIS
"(12) Unless justified by the subject-matter of the contract, technical specifications shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific origin or production with the effect of favouring or eliminating certain undertakings or certain products.
(13) But such reference is permitted on an exceptional basis, where a sufficiently precise and intelligible description of the subject-matter of the contract in accordance with paragraph (11) is not possible, in which case the reference shall be accompanied by the words "or equivalent"."
"(1) All documents, including all internal communications, relating to:
(i) The effectiveness historically of the MoD procuring hand tools by reference to ISIS and/or generic descriptors…
(iv) The drawing up of the technical specifications for the tools which were the subject of the Invitation to Tender dated 17 February 2016;
(v) The decisions taken to withdraw and/or abandon the mini-competitions initiated under the Framework;
(vi) The drawing up of the technical specifications for the tolls listed in Annex A, including documents relating to (a) the MoD's requirement; and (b) any assessment of those tools by reference to the MoD's requirements…
(2) All documents and/or information held by the MoD, the UK National Codification Bureau and/or any body under the control of the MoD relating to the tools in Annex A."
In respect of the equivalents, she noted that the documents sought related to similarly wide categories of documents.
7. APPLICATION FOR A STAY
(a) Is a stay in accordance with the overriding objective?(b) Is the potential detriment to the claimant caused by delay outweighed by the benefits of a stay to one or both parties and/or to the other users of the court?