BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> JSM Construction Ltd v Western Power Distribution (West Midlands) Plc [2020] EWHC 3583 (TCC) (31 December 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/3583.html Cite as: [2020] EWHC 3583 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND & WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane, London EC4A 1NL |
||
B e f o r e :
____________________
JSM CONSTRUCTION LIMITED |
Claimant |
|
- and |
||
WESTERN POWER DISTRIBUTION (WEST MIDLANDS) PLC |
Defendant |
____________________
Gaynor Chambers (instructed by Osborne Clarke LLP) for the Defendant
Hearing date: 8 July 2020
____________________
Crown Copyright ©
THE HONOURABLE MR JUSTICE PEPPERALL:
THE CONTRACT
THE CONTRACT PRICE
3.1 the agreed hourly rates for additional or substitute work undertaken on a daywork basis (Schedule 2);
3.2 that extra materials would be charged at cost plus 12½%;
3.3 the additional sums payable per metre for digging through solid rock, reinforced concrete or other hard substances (Schedule 3); and
3.4 the additional sums payable per metre for extra wide, or per cubic metre for extra deep, trenches (Schedule 4).
"WPD shall ascertain and determine the value of work done in accordance with the Contract using the rates and prices and the method of valuation stated in the Pricing Schedule. The prices in the Pricing Schedule shall remain fixed for the Contract Period."
"(a) based [its] rates and prices on [its] own inspection and examination as aforesaid and on all information whether obtainable by [it] or made available by WPD; and
(b) satisfied [itself] before submitting [its] rates and prices as to their correctness and sufficiency stated by [it] in the Pricing Schedule which shall (unless otherwise provided in the Contract) cover all [its] obligations under the Contract."
"If in the opinion of WPD such obstruction or condition could not reasonably have been foreseen by an experienced contractor then WPD shall certify a fair and reasonable sum and WPD shall pay such sum to cover the cost to the Contractor of performing any additional work or using any additional plant or equipment as a result of:
i. complying with any instructions which WPD may issue; and/or
ii. taking proper and reasonable measures to overcome or deal with the obstruction or condition in the absence of instructions from WPD.
Failing agreement of such sums WPD shall determine the fair and reasonable sum to be paid."
"8.3 Delay and extra cost
If WPD issues instructions which involve the Contractor in delay or disrupt [its] arrangements or methods of carrying out [its] obligations so as to cause [it] to incur cost beyond that reasonably to have been foreseen by an experienced contractor at the time of tender, then WPD shall take such delay into account in determining any extension of time to which the Contractor is entitled under Clause 5.4 and the Contractor shall, subject to Clause 17 be paid in accordance with Clause 18 the amount of such cost as may be reasonable, except to the extent that such delay and extra cost result from the Contractor's default
17.1 Valuation of ordered variations
The valuation of variations ordered by WPD shall be ascertained and agreed by WPD and the Contractor using the appropriate rates and prices in the Pricing Schedule and added to the Contract Price
17.3 WPD to determine additional sums and deductions
If the Contractor:
(a) carries out additional works instructed in writing by WPD, or
(b) intends to make any claim for additional payment, or
(c) incurs additional cost including any costs arising from delay or disruption to the progress of the Works
then [it] shall give notice to WPD to that effect as soon as reasonably practicable and in any event within 14 days of the commencement of the relevant event such notice to be accompanied by the Contractor's estimate of the cost which the Contractor will incur or intends to claim from WPD.
The Contractor shall regularly update WPD should the Contractor's estimate of cost change and shall provide WPD with such information and details as WPD may reasonably require in support of the Contractor's claim and/or to substantiate such estimate.
Provided the Contractor has complied with the obligations in this Clause 17.3 including without limitation to give notice within such 14 day period (which for the avoidance of doubt shall be a condition precedent to the entitlement of the Contractor to claim any additional cost) and provided in respect of matters falling within paragraph (c) above the Contractor has taken all reasonable steps to avoid or minimise the cost incurred as a result of the delay or disruption, WPD shall determine a fair and reasonable adjustment to the Contract Price to reflect the cost incurred by the Contractor
17.4 Valuation of additional work
In determining a fair and reasonable sum under Clause 17.3 for additional work WPD shall have regard to the rates and prices contained in the Pricing Schedule."
PAYMENT TERMS
"18.2 Where it is not stated in the Contract Agreement that interim and/or milestone payments will apply, the Contractor shall be entitled to payment on completion of the Works and the Contractor shall within 7 days of the Practical Completion Date for the Works issue a VAT invoice to WPD for the Contract Price less the Retention.
18.3 Where it is stated in the Contract Agreement that interim/milestone payments will apply, details of the interim/milestone payments shall be set out in the Contract Agreement. The Contractor shall, within 7 days of each interim payment date or milestone payment date stated in the Contract Agreement issue a VAT invoice to WPD for the relevant amount of the Contract Price less the Retention. Where it is stated in the Contract Agreement that interim/monthly payments are to apply but no further detail is provided in the Contract Agreement, the Contractor shall be entitled to interim monthly payments and the Contractor shall within 7 days of the end of the month following the month in which the Works Commencement Date occurs and at monthly intervals thereafter, issue a VAT invoice to WPD for the relevant amount of the Contract Price less the Retention
18.5 Notwithstanding any interim/milestone payments set out in the Contract Agreement, the Contractor shall only be entitled to submit invoices for payment of the Contract Price in instalments commensurate with actual progress of the Works.
18.6 Payment shall become due 5 days after receipt by WPD of the relevant invoice and any supporting documents in accordance with Clause 18.4.
18.7 Not later than 5 days after payment has become due in accordance with Clause 18.6, WPD shall notify the Contractor of the sum that WPD considered to have been due at the payment due date in respect of the Contractor's invoice and the basis on which that amount is calculated.
18.8 The final date for payment by WPD to the Contractor of sums due shall be 57 days after the date on which payment becomes due."
"18.12 Payment of retention money
(a) Where it is stated in the Contract Agreement that Retention is to apply, one half of the Retention Money shall be certified by WPD and shall be paid to the Contractor, subject to receipt by WPD of an invoice for the amount of Retention certified, by the end of the month following the month in which the Practical Completion Date is achieved.
(b) The final date for payment of the remainder of the Retention money to be paid to the Contractor is, subject always to receipt by WPD of an invoice for the remainder of Retention certified, by the end of the month following the month in which WPD issues the Defects Liability Certificate."
12.1 In the absence of contrary provision, the default machinery at clause 18.3 applied. JSM was therefore entitled to raise invoices within 7 days of the end of the month following the month in which works commenced, and monthly thereafter.
12.2 By clauses 18.3 and 18.5, each monthly invoice was limited to the proportion of the unpaid contract price commensurate with actual progress less the agreed 5% retention.
THE PAYMENT APPLICATIONS
Value of the Works upon re-measurement |
|
4,471,914.96 |
Add variations |
|
692,607.12 |
Gross value of the Works |
|
5,164,522.08 |
Less retention at 1.5% |
|
(77,467.83) |
Net value after retention |
|
5,087,054.25 |
Add interest |
|
83,589.00 |
Add additional costs incurred due to variations and instructions |
|
83,370.59 |
Add additional costs incurred by WPD's failure to issue extensions of time |
|
95,172.54 |
Add additional costs incurred in carrying out the remeasurement due to WPD's failure properly to measure and/or remeasure |
|
161,324.51 |
Total |
|
5,510,510.89 |
Less previously paid |
|
(3,983,302.63) |
Net sum payable |
|
1,527,208.26 |
VAT |
|
305,441.65 |
Application 12 |
|
£1,832,649.91 |
THIS CLAIM
18.1 Western Power failed to provide a contract commencement date or a contract period; and
18.2 the Pricing Schedule provided only for an incomplete and inaccurate design such that "as a pricing mechanism [it] has only limited application to pricing the works as constructed."
19.1 At paragraph 8 of its Particulars of Claim, JSM pleads:
"(1) the period for completion of the Works as constructed was to be a reasonable time, pursuant to a term implied by section 14 of the Supply of Goods and Services Act 1982. A reasonable time for completion of the works as constructed was from 16 January 2017 to 27 November 2017;
(2) the Claimant is entitled to a reasonable sum for the Works as constructed, pursuant to a term implied by section 15 of the Supply of Goods and Services Act 1982. A reasonable sum, based on a remeasure, using contract rates in the Pricing Schedule where applicable, but otherwise applying the principles set out in CESMM 4, and taking into account sums already paid by the Defendant gives a balance due to the Claimant of £1,359,762.58, which it hereby claims, along with damages of £161,324.51, and interest."
19.2 At paragraphs 38-39, JSM pleads that since Western Power was both the employer and contracted on the basis that it would value and certify any claimed variations, it owed a duty to act fairly, impartially, reasonably, and not arbitrarily, capriciously, perversely or irrationally.
19.3 At paragraphs 46-52, JSM pleads that Western Power was "required" promptly to certify practical completion.
19.4 At paragraphs 53-54, JSM pleads:
"53. The Contract is a construction contract for the purposes of the Housing Grants, Construction & Regeneration Act 1996 ('the Act'). Section 110 of the Act requires every construction contract to which the Act applies to provide an adequate mechanism for determining 'what payments become due under the contract, and when'. Although the Contract provides for interim (stage) payments there is no provision in the Contract for a final payment for the completed Works.
54. In these circumstances a term or terms are implied into the Contract pursuant to paragraphs 3, 5 and/or 7 and 8(1) of Part II of the Scheme for Construction Contracts ('the Scheme').
3. Where the parties to a construction contract fail to provide an adequate mechanism for determining either what payments become due under the contract, or when they become due for payment, or both, the relevant provisions of paragraphs 4 to 7 shall apply...
5. The final payment payable under a relevant construction contract, namely the payment of an amount equal to the difference (if any) between:
(a) the contract price, and
(b) the aggregate of any instalment or stage or periodic payments which have become due under the contract,
shall become due on the expiry of:
(a) 30 days following completion of the work, or
(b) the making of a claim by the payee,
whichever is the later...
7. Any other payment under a construction contract shall become due
(a) on the expiry of 7 days following the completion of the work to which the payment relates, or
(b) the making of a claim by the payee,
whichever is the later.
8. (1) Where the parties to a construction contract fail to provide a final date for payment in relation to any sum which becomes due under a construction contract, the provisions of this paragraph shall apply.
(2) The final date for the making of any payment of a kind mentioned in paragraphs 2, 5, 6 or 7 shall be 17 days from the date that the payment becomes due."
THE APPLICATION
ARGUMENT
DISCUSSION
THE PROPER APPROACH TO THIS APPLICATION
Striking out: no reasonable grounds for bringing the claim
24.1 The whole or part of a statement of case may be struck out pursuant to r.3.4(2)(a) if it does not disclose a ground of claim or defence known to law (e.g. Price Meats Ltd v. Barclays Bank plc [2000] 2 All ER (Comm) 346) or where the court is otherwise certain that the claim or defence is bound to fail (Harris v. Bolt Burdon [2000] CP Rep 70; Hughes v Colin Richards & Co. [2004] EWCA Civ 266, [2004] PNLR 35).
24.2 As Clarke LJ (as he then was) observed in Royal Brompton Hospital NHS Trust v. Hammond [2001] EWCA Civ 550, at [108], the focus in applications under r.3.4(2)(a) is upon the statement of case rather than the evidence. In that respect, the approach differs from applications for summary judgment under Part 24. Accordingly, on this application, the court must assume the truth of the Claimant's pleaded case.
24.3 The hurdle is, as one would expect, high. Striking out is an exceptional course and most cases should simply be defended on their merits. The court must be certain that the case is hopeless before it can be struck out under r.3.4(2)(a).
Summary judgment
"i) The court must consider whether the claimant has a 'realistic' as opposed to a 'fanciful' prospect of success: Swain v. Hillman [2001] 1 All ER 91.
ii) A 'realistic' claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products v. Patel [2003] EWCA Civ 472 at [8].
iii) In reaching its conclusion the court must not conduct a 'mini-trial': Swain v. Hillman.
iv) This does not mean that the court must take at face value any without analysis everything that a claimant says in his statements before the court. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents: ED & F Man Liquid Products v. Patel at [10].
v) However, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial: Royal Brompton Hospital NHS Trust v Hammond
vi) Although a case may turn out at trial not to be really complicated, it does not follow that it should be decided without the fuller investigation into the facts at trial than is possible or permissible on summary judgment. Thus the court should hesitate about making a final decision without a trial, even where there is no obvious conflict of fact at the time of the application, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case: Doncaster Pharmaceuticals Group Ltd v Bolton Pharmaceutical Co 100 Ltd [2007] FSR 63.
vii) On the other hand it is not uncommon for an application under Part 24 to give rise to a short point of law or construction and, if the court is satisfied that it has before it all the evidence necessary for the proper determination of the question and that the parties have had an adequate opportunity to address it in argument, it should grasp the nettle and decide it. The reason is quite simple: if the respondent's case is bad in law, he will in truth have no real prospect of succeeding on his claim or successfully defending the claim against him, as the case may be. Similarly, if the applicant's case is bad in law, the sooner that is determined, the better. If it is possible to show by evidence that although material in the form of documents or oral evidence that would put the documents in another light is not currently before the court, such material is likely to exist and can be expected to be available at trial, it would be wrong to give summary judgment because there would be a real, as opposed to a fanciful, prospect of success. However, it is not enough simply to argue that the case should be allowed to go to trial because something may turn up which would have a bearing on the question of construction: ICI Chemicals & Polymers Ltd v TTE Training Ltd [2007] EWCA Civ 725."
HOUSING GRANTS, CONSTRUCTION & REGENERATION ACT 1996
"109 Entitlement to stage payments
(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless
(a) it is specified in the contract that the duration of the work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
110 Dates for payment
(1) Every construction contract shall-
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
(b) provide for a final date for payment in relation to any sum which becomes due.
The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment
(3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1), the relevant provisions of the Scheme for Construction Contracts apply."
Stage payments
"At the heart of these provisions is the attempt to ensure that every construction contract contains a transparent and straightforward mechanism for the payment to the contractor of interim payments on account (sometimes called instalments or progress payments)."
31.1 Clause 18.8 specified when the monthly stage payments fell due.
31.2 Clause 18.12 specified when the retention monies fell due for payment.
"I reject this submission for three reasons. First, the express words used make it clear that the parties were only agreeing a regime of interim payments up to the contractual date for practical completion .. Secondly, it is impossible to deduce from the hybrid arrangement what would be the dates for valuations, payment notices, pay less notices and payments after July 2015. These were essential matters for the reasons previously stated. Thirdly, this is a classic case of a party making a bad bargain. The court will not, and indeed cannot, use the canons of construction to rescue one party from the consequences of what that party has clearly agreed."
Final payments
"Of course, this is not the only type of payment mechanism which will satisfy the test, and parties should not rely entirely on differences between the Scheme's provisions and those of the contract in order to demonstrate inadequacy in the latter. The only binding obligation is to comply with the terms of the Act, which is drafted in far less prescriptive terms than the Scheme. The lack of one or all of the [elements of the Scheme] will not necessarily be fatal."
"The purpose of these provisions is clear: to ensure that every construction contract contained a transparent and straightforward mechanism for payment to the contractor by way of stage payments, ending with the final payment, all to be made pursuant to a clear contractual timetable. I would venture to suggest that it was not designed to invalidate a particular type of stage payment or instalment regime; it was simply intended to ensure that there was such a regime in place which met certain minimum standards."
"24. Thus what the engineer has to certify and Alstom to pay is not the true final value of the work in fact done and materials in fact supplied etc, but what in the opinion of the engineer is due on the basis of the monthly statement. If Boot omits an item of work from the statement, even if the work has been done, the engineer is not obliged to include its value in the certificate .
56. In my view, the cause of action in respect of an engineer's failure to include a sum in an interim certificate is not the same as the cause of action in respect of the failure to include a sum in the final certificate, even if the two sums happen to be the same. This is because interim certificates are no more than provisional estimates of the sum to which Boot is entitled by way of instalment payments."
"Certification may be a complex exercise involving an exercise of judgment and an investigation and assessment of potentially complex and voluminous material. An assessment by an engineer of the appropriate interim payment may have a margin of error either way. It may be subsequently established that it was too generous to the contractor just as it may subsequently be established that the contractor was entitled to more. Further the sum certified may be made up from a large number of constituent figures, some of which may likewise be assessed favourably to one party or the other. It may be that a contractor can say that under a certain heading he did not have certified as high a figure as can later be seen to be appropriate but that under another heading he has to accept that the figures certified can be shown to have been an over-certification. At the interim stage it cannot always be a wholly exact science. Its purpose is not to produce a final determination of the remuneration to which the contractor is entitled but is to provide a fair system of monthly progress payments to be made to the contractor."
"What will be adequate in some cases will be inadequate in others. Large complex construction operations will no doubt require complex highly structured mechanisms. Equally, simple, straightforward construction operations may be satisfactorily served by a very simple mechanism. I do not accept that I can determine as a matter of law whether the contractual mechanism in this case is adequate, whether by reference to the scheme or otherwise. The adequacy of the mechanism is a question of fact "