BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> The House Maker (Padgate) Ltd v Network Rail Infrastructure [2022] EWHC 1482 (TCC) (05 April 2022) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2022/1482.html Cite as: [2022] EWHC 1482 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS IN MANCHESTER
TECHNOLOGY & CONSTRUCTION COURT (QBD)
1 Bridge Street West, Manchester M60 9DJ |
||
B e f o r e :
Sitting as a Judge of the High Court
____________________
THE HOUSE MAKER (PADGATE) LIMITED |
Claimant |
|
- and - |
||
NETWORK RAIL INFRASTRUCTURE |
Defendant |
____________________
Unit 1 Blenheim Court, Beaufort Business Park, Bristol, BS32 4NE
Web: www.epiqglobal.com/en-gb/ Email: [email protected]
(Official Shorthand Writers to the Court)
Dates of hearing: 29-31 March 2022
Date of judgment: 5 April 2022
(Approved on 20 June 2022)
____________________
Crown Copyright ©
HIS HONOUR JUDGE HODGE QC:
I: Introduction and background
II: The trial
III: Findings of fact
IV: Scope of duty
V: Breach
VI: Loss;
VII: Conclusion
I: Introduction and background
II: The trial
III: Findings of fact
(a) On 1 March 2017 I reported flooding of the development land to Network Rail and the complaint log was started. I took photographs of the flooding on or around 1 March 2017.
(b) On or around 7 March 2017 United Utilities visited the adjacent land the development land and confirmed that the blockage was on the adjacent land and that the culvert was backing up and the water rising. I was present when United Utilities attended.
(c) On or around 7 March 2017 I chased an update from Network Rail regarding when remedial works would be done.
(d) On or around 7 March 2017, Network Rail's own signaller reported flooding on the railway track on the adjacent land. I have obtained this information from the complaint log with Network Rail.
(e) On or around 22 March 2017 I chased an update from Network Rail, further noting the serious consequences that flooding on the track could have for Network Rail.
(f) By 22 March 2017 Network rail had inspected the drain on Network Rail's land and had passed the issue to Network Rail's drainage team for work to be carried out.
(g) On or around 3 April 2017 I chased Network Rail for an update and to ascertain when the work would be carried out as the flooding was backing up on to the development land.
(h) On or around 11 April 2017 Network Rail informed me that its drainage engineers visited the adjacent land on or around 28 March and confirmed that there was a blockage within Network Rail's track drainage system on the adjacent land causing the flow to back up and partially flood the adjacent railway land (being the development land). Further that the flood water was contaminated with domestic effluent and that a full drainage renewal scheme was due to be implemented at this location in the future.
We act for The House Maker who have an option agreement to purchase the land adjacent to Padgate Station called Millman Coaches Station Yard …
We write in relation to an ongoing complaint that you have failed to resolve. Our client's claim against Network Rail is in private nuisance relating to blocked drains on your land which is backing up and causing issues on the land.
We have been provided with a copy of the complaints log and upon review we consider that this matter should be dealt with in accordance with the Practice Direction on Pre-Action Conduct and Protocols contained in the Civil Procedure Rules … Ignoring this letter may lead to our client commencing proceedings against you and may increase your liability for costs.
Background
Our client's intention is to develop the land for residential properties. Our client has carried out all its due diligence and necessary reports and has prepared architects' drawings ready for submission for planning. However, they cannot submit a planning application of this nature without also providing a 'drain design', such a report cannot be concluded until you have resolved your drainage issues.
Our client reported this matter to you on or around 1 March 2017, and on 7 March 2017 your signaller also reported flooding on the tracks caused by the blocked drain.
Our client continuously chased you for confirmation as to when you would rectify the problem and after much chasing is very concerned to be told that you consider it a major job as track will need to be removed and that this has been added to a list for planned works but with absolutely no timescale. Rather alarmingly our client was then told on 11 April 2017 that the flood water is contaminated with domestic effluent. We remind you that this is not just on your tracks but is backing up on to our client's land. You cannot ignore this serious issue or delay it any further. We note with some relief that you are investigating whether there are any short-term solutions, but our client has received no further update in this regard since 11 April 2017.
Breach of duty of care
The flooding of domestic effluent on to our client's adjoining site is actionable in tort as a private nuisance and also requires reporting to the Health and Safety Executive.
Your client owes a common law duty of care to our client as a neighbouring landowner. In this regard, liability falls on your failure to take action to remedy the flooding of human waste, resulting in the flooding of this on the land.
Our client is unable to proceed with submitting a planning application and therefore unable to progress developing the land, which is obviously causing a significant financial loss to our client, who is a property developer.
Quantum
The financial losses (including the increasing costs of construction) to our client are significant and arise solely from the fact that no remedial action has been carried out promptly or at all. It is over two months since this was reported to you and no works have been carried out to stop the flooding.
We will provide full details of our client's financial claim in due course.
Continuing nuisance and injunctive relief
In the event you fail to remedy the flooding and confirm the satisfactory timescale to us within the next 14 days we are likely to be instructed to apply to the court by way of injunctive relief to seek a mandatory court order requiring you to remedy the fault.
If such action is necessary, then the costs of and incidental to preparing an application for injunctive relief will also be sought from you.
The next steps
We require a response within 14 days of the date of this letter. If you fail to provide a full letter of response within the time allowed, we are instructed to issue and serve proceedings without further notice and without further compliance with the Protocol.
Our client is of course open to a discussion as to the action plan for remedial works, but your failure to provide one with a reasonable timescale will result in our client taking court action.
We look forward to hearing from you.
Yours faithfully, etc
On or around 23 May 2017 Network Rail informed [him] that one of its drainage engineers had recently inspected the adjacent land on 17 May 2017 and that a further visual site inspection was due to be carried out but this had been cancelled due to a lack of access to the railway line being granted. Further, that a Minor Works remit had also been raised to undertake intrusive investigation work; ideally within the next 28 days although this would be dependent on works-resource and track-access availability.
Mr George confirms that following 23 May 2017 neither he nor anyone else from the claimant had any further communication with Network Rail and that all further correspondence was effected through the claimant's solicitors, Blackstone Solicitors.
We have been advised by our client that Network Rail have attended the site to investigate the sewer blockage on Network Rail's land. It is noted that has been verbally accepted by the surveyor that the blocked drain is on Network Rail's land and that a new drainage system needs to be laid. In this regard, we would be grateful if you could confirm when this will be undertaken.
You should note that our client intends to commence building works on the site late August 2017 and therefore the new drainage needs to be laid as a matter of urgency.
Please note that Counsel is in the process of preparing proceedings to ensure that Network Rail remedy the drain blockage as a matter of urgency. We require an exact date as to when the works will be started and an undertaking to assure that the new drainage system will be completed by late August 2017.
We look forward to hearing from you by no later than Friday 4 August 2017 in this regard.
We write in relation to the above matter further to our correspondence dated 2 August 2017 and 11 August 2017.
We note that we are yet to receive a response to the above-mentioned correspondence. We have telephoned on a number of occasions however Simon Pugh and Leila Evans have been unavailable. Members of Network Rail staff have advised on two occasions that Simon Pugh would return our call however no communication has been forthcoming.
We have provided you with the necessary evidence to prove that our client is the registered owner of the land on the north-east side of Green Lane, Padgate, Warrington and on the south-west side of Station Yard, Green Lane, Padgate, Warrington.
We note that Network Rail through their surveyor have verbally accepted that the blocked drain is on Network Rail's land and that a new drainage system needs to be laid. We are still waiting for confirmation as to when this work would be done.
As you have been advised, our client hoped to commence building works on the site late August 2017 however, this has not occurred as the drainage has not been fixed. You will appreciate that the delay in build is causing our client significant concern and will result in a substantial financial loss for our client. Therefore the new drainage system needs to be laid as a matter of urgency.
Please note that we have instructed Counsel to prepare proceedings to ensure that Network Rail remedy the drain blockage as a matter of urgency. We require an exact date as to when the works will be started and an undertaking to assure that the new drainage system will be completed as a matter of urgency.
We look forward to hearing from you by no later than Friday 8 September 2017 in this regard. Should a response not be received we will have no other option than to commence proceedings.
Our client is aware that improvements are needed to the drainage which sits in part beneath the station platforms and/or railway lines. For some time our client has been planning and designing a solution to remedy problems with the drainage but has been severely hampered by the location of the drain and the complexity of the proposed solution. A solution has been found and the necessary works have been fully designed, but to put the problem and the proposed solution into context, the remedial scheme will certainly cost a minimum of £400,000. It is not therefore something which can be implemented quickly.
As this is a major investment in infrastructure it must form part of our client's programme for capital expenditure and the maintenance generally of the railway network. The works are planned to take place during the year commencing in April 2019.
Reference was then made to a temporary solution in the form of the construction of a pumping station, but the costs were substantial and pumping stations were said to be something to be avoided wherever possible because they were noisy when in operation and might itself lead to nuisance complaints from neighbouring properties. Reference was also made to the potential inadequacy of the claimant's proposed undertaking in damages and therefore Addleshaw Goddard indicated that if the claimant was intent on proceeding, they would expect a personal guarantee from a director or directors supported by evidence of means. The letter concluded by inviting the claimant to withdraw the injunction application.
The Remedial Scheme is scheduled to take place in the period between April 2019 and April 2020 and will be dealt with as a priority item. No finalised construction plan has been issued yet as the proposed works are still in development, however it is anticipated that the works will take approximately three months. However, this timeframe is subject to railway access and possessions opportunities and undertake the works.
It follows that during the stay presently sought by the parties all that can be discussed is the design of the remedial scheme. It is of course hoped that the parties can reach an agreement about this. However, it is the defendant's position that the works will not be done before October or November 2019 and, as we say, we do not want either the claimant or the court to be misled by the defendant agreeing to a further stay of two months.
That letter made it clear that by then the remedial scheme had not been fully designed. In cross-examination, Mr Hellings accepted that the statements in these two letters were at odds with each other.
IV: Scope of duty
A discrete body of law has developed concerning the extent of the landowner's liability for natural nuisances. 'Natural nuisances' is a term used by some commentators to describe nuisances which are caused by the operation of nature rather than any act of the landowner.
An occupier of land owed a general duty of care to a neighbouring occupier in relation to a hazard occurring on his land, whether such a hazard was natural or man-made; that the duty was to take such steps as were reasonable in all the circumstances to prevent or minimise the risk of injury or damage to the neighbour or his property of which the occupier knew or ought to have known; that the circumstances included his knowledge of the hazard, the extent of the risk, the practicability of preventing or minimising the foreseeable injury or damage, the time available for doing so, the probable cost of the work involved and the relative financial and other resources, taken on a broad basis, of the parties.
The label nuisance or negligence is treated as of no real significance. In this field, I think, the concern of the common law lies in working out the fair and just content and incidents of a neighbour's duty rather than affixing a label and inferring the extent of the duty from it.
In the circumstances of the present case, therefore, I am content to adopt, and apply, the measured duty of care, particularly since I am satisfied that it makes no practical difference to its outcome.
Where then does the law now stand in relation to the liability of landowners for nonfeasance in respect of natural nuisance? I would not presume to paraphrase the vast body of learning which has accumulated on this topic. Nevertheless I extract from the authorities discussed above the following principles which are relevant to the determination of this appeal.
(i) A landowner owes a measured duty in both negligence and nuisance to take reasonable steps to prevent natural occurrences on his land from causing damage to neighbouring properties.
(ii) In determining the content of the measured duty, the court must consider what is fair, just and reasonable as between the two neighbouring landowners. It must have regard to all the circumstances, including the extent of the foreseeable risk, the available preventive measures, the costs of such measures and the resources of both parties.
(iii) Where the defendant is a public authority with substantial resources, the court must take into account the competing demands on those resources and the public purposes for which they are held. It may not be fair, just or reasonable to require a public authority to expend those resources on infrastructure works in order to protect a few individuals against a modest risk of property damage.
At paragraph 50, Jackson LJ explained that: "… the judge is required to carry out a somewhat daunting multifactorial assessment".
V: Breach
VI: Loss
VII: Conclusion