BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> J & B Hopkins Ltd v A & V Building Solution Ltd [2023] EWHC 1483 (TCC) (16 June 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/1483.html Cite as: [2023] EWHC 1483 (TCC) |
[New search] [Printable PDF version] [Help]
Case No: HT-2023-000006 |
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Rolls Building London, EC4A 1NL |
||
B e f o r e :
Sitting as a Deputy High Court Judge
____________________
J & B HOPKINS LIMITED |
Case No: HT-2022-000444 Claimant |
|
- and – |
||
A & V BUILDING SOLUTION LIMITED |
Defendant |
|
And Between: |
||
A & V BUILDING SOLUTION LIMITED |
Case No: HT-2023-000006 Claimant |
|
- and – |
||
J & B HOPKINS LIMITED |
Defendant |
____________________
Alex Paduraru (a director of the Defendant Company) for the Defendant.
Hearing date: 1 June 2023
____________________
Crown Copyright ©
Mr Roger ter Haar QC :
(1) To determine the amount of interest to be awarded in J&BH's favour in action 444 of 2022;
(2) To determine the appropriate award of costs in action 444 of 2022;
(3) To determine A&V's application for a stay of execution in action 444 of 2022;
(4) To determine J&BH's application for a stay of action 6 of 2023 until the enforcement judgment in action 444 of 2022 has been complied with;
(5) To determine J&BH's application for summary judgment and/or a strike out of the Claim Form in action 6 of 2023;
(6) To determine J&BH's application for security for costs in action 6 of 2023;
(7) To determine A&V's application for Judgment in Default to be entered for A&V against J&BH in the sum of £370,611.63.
Background
(1) Declaring that:
a) Application 14 was not a valid payment application under the Sub-Contract because it was issued too late;
b) Payment Notice 14 was a valid payment notice under the Sub-Contract;
c) [A&V] was not entitled to any payment in respect of Application 14.
(2) Ordering A&V to pay J&BH's costs of the proceedings summarily assessed in the sum of £27,750.
"The Adjudicator is requested to review and decide the matters pertaining to the Referring Party's claim for the breaches and subsequent Final Account for outstanding monies/late payment considered due for the works to the Moulescoomb project in the sum of £455,526.53 plus VAT or other such sums as the Adjudicator shall determine …."
Interest in action 444 of 2022
J&BH's costs in action 444 of 2022
A&V's application for a stay of execution in action 444 of 2022
"2. This Witness Statement is made in support of the Defendant's Application for a Stay of Execution of the Approved Judgment [HT-2022-000444] dated 15 February 2023.
"3. I make this Statement from the facts and matters within my own knowledge, which are contained within the files maintained by the Defendant in respect of this matter. Where I refer to facts and matters outside my own knowledge, I identify the source of those facts and matters. I confirm that the contents of this Statement are true to the best of my knowledge and belief.
"4, I make this statement to support that everything [which] is stated in the Defendants [A&V] submissions in relation to the Approved Judgment and Cost is true."
"Ground 1:
"Pending the outcome of the High Court "Sealed" Claim Number – HT-2023-000006 [Judgment in Default] [please refer to appendix 1 below] which was duly served on the Claimant [JBH] on 1st of February 2023, an acknowledgment of service was issued on 2 February 2023 by JBH legal representatives [please refer to appendix 2 below] and JBH's Defence to A&V's claim is due to be provided by 1 March 2023.
"Ground 2:
"The Defendant is unable to pay to the Claimant the judgment sum of £110,880.88 if ordered to do so [please refer to appendix 3 below]
"Ground 3:
"The Defendant will be forced to stop trading and go into insolvency if ordered to pay the judgment sum of £110,880.88 [please refer to appendix 4 below]
"Ground 4:
"The Defendant cannot afford to refer this dispute to a Court of Arbitration if A&V must pay the summary judgment first in the sum of £110,880.88.
"Ground 5:
"The Defendants' rights and the fair opportunity to refer this dispute to a Court of Arbitration will be prevented if A&V must pay the summary judgment sum first."
The Claim Form in Action 6 of 2023
"Brief details of claim
"1. The Claimant issued its Letter of Claim dated 2 December 2022 in accordance with Pre-Action Protocol for Construction and Engineering Disputes via email and post on 2 December 2022.
"2. The Letter of Claim was received by the Defendant on 5 December 2022 via the post office.
"3. The Defendant acknowledge[d] receipt of the Letter of Claim via email on 16 December 2022.
"4. In Accordance with paragraph 8.5 of the Protocol the Defendant should have [sent] a letter of response to the Claimant within 28 days from the date of receipt of the Letter of Claim (on or before 2 January 2023)
"5. Today's date is 9 January 2023 (7 days behind the allowed timeframe) and the Defendant has not provided any Response, Defence or Counterclaim. The Defendant failed to comply with the Protocol.
6. The Defendant has not complied with the Protocol. It has made no payments to the Claimant in respect to the Final Account.
"The Claimant therefore seeks Judgment in Default to be entered against the Defendant.
"Value
"1. £276,917.63 plus VAT and Court Fee (sum due for the Final Account of the Sub-Contract)
"2. £34,800 (sum due for [Adjudicator] Mr Keith Blizzard for Adjudication 1)
"3. £9,600 (legal cost incurred by the Claimant in Part 8 proceedings related to Final Account)
"4. £7,140 (legal cost incurred by the Claimant in Enforcement proceedings related to Final Acc)
"5. £21,840 (legal cost incurred by the Claimant in Court of Appeal proceedings related to F. Acc)"
"The Parties:
"The Claimant is and was at all material times a mechanical sub-contractor.
"The Defendant is and was at all material times a mechanical and electrical services contractor.
"Summary:
"The Claimant is entitled to and hereby seeks Judgment in Default to be entered against the Defendant and claims all the sums 1,2,3,4 and 5 shown in Value above as a debt due under the Sub-Contract, and the cost of [these] proceedings to be paid by the Defendant.
"Further to the Claimant Final Account letter dated 26 May 2022 (letter attached) matters of the Final Account have not been satisfactorily concluded between the parties. The Defendant has not provided any meaningful response to the Claimant and matters of the Final Account only being commented upon by the Defendant in Adjudication 3. The Claimant have sought to proceed to refer the matter to the Courts and issued its Letter of Claim on 2nd December 2022 via email and recorded delivery and in accordance with the Pre-Action Protocol for Construction and Engineering Disputes (letter attached). The Defendant acknowledges receipt of the Letter of Claim via email on 16 December 2022 (email/letter attached). In accordance with paragraph 8.5 of the Protocol, the Defendant should have sent a letter of response to the Claimant within 28 days from the date of receipt of the Letter of Claim respectively on or before 2 January 2023. To date 9 January 2023 (7 days behind the allowed timeframe) the Defendant has not provided any response, defence or counterclaim. The Defendant has failed to comply with the Pre-Action Protocol for Construction and Engineering Disputes. In Accordance with paragraph 8.6 of the Protocol the Claimant is now permitted to commence proceedings against the Defendant without further compliance with the Protocol as no response has been received by the Claimant within 28 days.
"The true value of the Sub-Contract works was £675,687.27 and based on the Defendant's previous payments to date (£364,909.64) this notes a total sum due and outstanding of £276,917.63 plus VAT.
"Failure to comply with the Protocol
"As a result of the Defendant's failure to comply with the Pre-Action Protocol for Construction and Engineering Disputes, the Claimant is now entitled to commence proceedings without further compliance with the Protocol.
"The Claimant is entitled to and hereby seeks Judgment in Default to be entered against the Defendant and claims all the sums 1,2,3,4 and 5 shown in Value above as a debt due under the Sub-Contract, and the costs of [these] proceedings to be paid by the Defendant."
J&BH's Applications in Action 6 of 2023
"An application for:
"(1) A stay of these proceedings unless and until the Claimant complies with an adjudicator's decision in the Defendant's favour on the final account. The Defendant has already obtained a judgment from the Court enforcing the decision.
"(2) Summary judgment and/or strike our under CPR 3.4(2) of the whole, alternatively parts of, the Particulars of Claim on the Claim Form because the Claimant does not have a better than arguable case and/or there are no reasonable grounds for bringing the claim those parts of Claim Form. The Defendant's attention is drawn to CPR 24.5(1).
"(3) If the claim for the final account sum is pursued on a true value basis, strike out of paragraph 1 under "Value" on the Claim Form under CPR 3.4(2)(b) and/or (c) because the lack of particulars is likely to obstruct the just disposal of the proceedings and/or a failure to comply with the CPR rules. In the alternative, JBH seeks an order requiring the Claimant to [serve an] amended CPR compliant Particulars of Claim.
"(4) Security for costs under CPR 25.12, namely an order that the Claimant gives security for the Defendant's costs of these proceedings up [to] the first CMCC by paying into court the sum of £30,000, or such other sum as the court deems fit, within 7 days of the order. The application is made because the Defendant considers that the condition in CPR 25.13(2)(c) is satisfied: the Claimant is a company and there is reason to believe that it will be unable to pay the Defendant's costs if ordered to do so.
"(5) An extension of time for the Defence until after the above applications are decided."
J&BH's Strike Out Application in action 6 of 2023
(1) The Final Account claim for £276,917.23 plus VAT;
(2) The claim for £34,800 in respect of Mr. Blizzard's fees;
(3) The three claims (no. 3 for £9,600, no. 4 for £7,140 and no. 5 for £21,840) for "legal cost".
(1) Sets out how the figure of £276,917.63 is calculated;
(2) To the extent that it is dependent upon quantities of work and materials, specifying those quantities;
(3) To the extent that it is dependent upon variations, identifying the relevant instructions and the value of such instructions;
(4) To the extent that it is dependent upon alleged breaches of contract, identifying the relevant contractual provisions, the nature of the breaches and the costs flowing from such breaches (this would appear to encompass delay related costs).
A&V's Application for Judgment in Default in action 6 of 2023
A&V's Application for a Stay of Execution in action 444 of 2022
"(a) there are special circumstances which render it inexpedient to enforce the judgment or order, or
(b) the applicant is unable from any reason to pay the money."
(1) The burden is on an applicant to show that it is unable to pay, including that no funds would be made available to it including by its owner (at paragraph [11]):
"…where this ground is relied on the onus rests firmly on the applying party, here the Defendant, to make good that case. Further, it was not in dispute that Lord Wilson JSC's dictum in Goldtrail Travel Limited (in liquidation) v Onur Air Tasimacilik AS [2017] UKSC 57, [2017] 1 WLR 3014, at [23] to [24] applies by analogy. As Lord Wilson JSC said in those paragraphs:
"In this context the criterion is: 'Has the appellant company established on the balance of probabilities that no such funds would be made available to it, whether by its owner or by some other closely associated person, as would enable it to satisfy the requested condition?'
"… In cases … in which the respondent to the appeal suggests that the necessary funds would be made available to the company by, say, its owner, the court can expect to receive an emphatic refutation of the suggestion both by the company and, perhaps in particular, by the owner. The court should therefore not take the refutation at face value. It should judge the probable availability of the funds by reference to the underlying realities of the company's financial position; and by reference to all aspects of its relationship its owner with, including, obviously, the extent to which he is directing (and has directed) its affairs and is supporting (and has supported) it in financial terms.""
(2) Even if the Court is satisfied that the applicant is unable to pay, it must still consider its discretion as to whether to grant the stay sought (at paragraph [12]).
(3) A no-set off clause is a very strong factor in the discretionary exercise.
"52. Further or alternatively, even if the Court considers (contrary to the above) that A&V has demonstrated it is unable to pay the Enforcement Sum, JBH submits that the Court should refuse to exercise its discretion to do so. JBH relies, in particular, on the following factors:
"52.1 Firstly, the "pay now, argue later" policy behind adjudication and clause 20.3 of the Sub-Contract ("The decision of the adjudicator shall be binding until the dispute is finally determined by legal proceedings or by agreement." [D/8/47]) are analogous to a no-set off clause. Applying the principles set out in Andrew v Flywheel, it should be a very rare case in which the Court would grant a stay of execution of a judgment enforcing an adjudicator's decision until legal proceedings on the same dispute are determined.
"52.2 This principle applies even more strongly in this case given that it was A&V which commenced the Final Account Adjudication. A&V chose to pursue the dispute as to the final account in adjudication first….."
2022 | 2021 | |
£ | £ | |
Fixed Assets | 3,050 | 4,575 |
Current Assets | 37,176 | 70,355 |
Creditors: amounts falling due within one year | - | (20,117) |
Net current assets (liabilities) | 37,176 | 50,238 |
Total assets less current liabilities | 40,226 | 54,813 |
Creditors: amounts falling due after more than one year | (141,259) | (50,000) |
Total net assets (liabilities) | (101,033) | 4,813 |
Capital and reserves | (101,033) | 4,813 |
"We write with reference to the forthcoming hearing on 1 June 2023 and to seek clarification of A&V's financial position following the filing of A&V's accounts at Companies House on 20 April 2023 (attached for ease of reference).
"Please respond to the following queries:
"1. The lack of any creditors/amounts falling due within one year indicates that A&V did not trade. Please confirm whether or not A&V was trading in the accounting period following 31 January 2022.
"2. The accounts state that no amounts are falling due within one year. This appears to be contrary to both:
"a. Natwest's letter to us dated 13 May 2022, in which Natwest confirmed that A&V was in debit across a number of current and loan accounts in the total sum of £181,922.39; and
"b. HMRC's letter to A&V dated 2 June 2022, in which HMRC refer to an agreement to repay a debt of £143,295.28 by instalments.
"Please explain why these amounts do not seem to be reflected in A&V's accounts.
"3. Similarly, the amounts falling due after more than one year of £141,259 do not reflect the sums due to Natwest or HMRC (which together total £325,217.67). Please provide a simple breakdown of the £141,259 owed to creditors after more than one year to include the name of the creditor and the sum owed.
"4. The accounts do not seem to reflect A&V's claim or its liabilities to JBH. Please explain why not.
"5. In order to ensure that the Court has up to date information regarding A&V's financial position, please provide us with a summary of A&V's balanced sheet and copies of its management accounts for the period ending 31 January 2023.
"6. Given the negative 'capital and reserves value of (£101,033), it appears that A&V is insolvent. Please confirm how A&V intends to support itself going forward….."
"We are in receipt of your email/letter dated 05.05.2023.
"Please note that I am on my annual leave until the 22nd of May 2023. Therefore, I am unable to respond or to get in contact with our accountant until the 22nd of May 2023.
"However, and until then [22.05.2023] I can assure you that A&V Building Solution is not and has never been insolvent.
"Also, I can assure you that the up to date information regarding A&V's financial position and your client [J&B] breaches would be formally provided to the Court prior to the forthcoming application hearing dated 01.06.2023.
"Until then, I would suggest that HK Legal and your client J&B Hopkins stop searching for my name on LinkedIn and all others social media profiles. I believe that our case/dispute it is commercial dispute between two companies and not a personal matter."
(1) Fee Invoices from a member of the Bar, Mr. Charles Edwards: I refer to these further below.
(2) Reference by A&V to a letter to J&BH dated 30 January 2023 which shows that A&V has a bank account with Metro Bank as well as with Natwest;
(3) A letter from HMRC dated 22 March 2023 showing that A&V still owes HMRC monies: the figures are said to be "£55,343.13/£46,516.12/£33,485.73"; and
(4) Bank statements for the 4 NatWest accounts.
(1) On any view A&V is a small company;
(2) It appears no longer to be actively trading;
(3) It owes its banker and HMRC together sums well in excess of £300,000.
(1) Answering the points raised in Hawkswell Kilvingtom's letter of 5 May 2023;
(2) Exhibiting full bank statements in respect of all A&V's bank accounts with any bank or other financial institution so far as those can be obtained from such bank or institution;
(3) Explaining the current position of A&V with the tax authorities;
(4) If possible, producing accounts to 31 January 2023;
(5) Setting out how the Company's activities (including funding adjudications and litigation) have been financed since the end of A&V's presence on Site;
(6) Setting out the support which has been given to A&V by Mr. Paduraru and any other person, whether such support is likely to continue, and, if not, why not.
The Other Applications