BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Vainker & Anor v Marbank Construction Ltd & Ors (Re Costs) [2024] EWHC 1686 (TCC) (20 May 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/1686.html Cite as: [2024] EWHC 1686 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Strand, London, WC2A 2LL Start Time: 10.46 Finish Time: 11.52 |
||
B e f o r e :
____________________
(1) BRENDA VAINKER (2) FRANCOIS VAINKER |
Claimants |
|
- and - |
||
(1) MARBANK CONSTRUCTION LTD (2) MERCER & MILLER (A FIRM) (3) SCD ARCHITECTS LTD |
Defendants |
____________________
2nd Floor, Quality House, 6-9 Quality Court, Chancery Lane, London WC2A 1HP.
Telephone No: 020 7067 2900. DX 410 LDE
Email: [email protected]
Web: www.martenwalshcherer.com
ROBERT CLAY for the First Defendant
The Second Defendant was not present or represented
BENJAMIN FOWLER for the Third Defendant
____________________
Crown Copyright ©
MRS JUSTICE JEFFORD:
i) As pleaded in the Particulars of Claim, the claimants' claim was for a total of £889,000 against all three defendants, that is including M&M, the second defendant. They have recovered approximately £435,000 before the addition of interest. That does not immediately suggest a case in which the claim was exaggerated and the recovery is so disproportionate to the amount claimed that the court ought to regard the claim as an exaggerated one and hesitate to award the claimants their costs.
ii) In fact, if the recovery on the counterclaim of £81,000 odd is taken into account, the figure is in the region of the sum of £350,000 for which the claimants, by letter dated 1st August 2022, offered to settle against all three defendants. That is not suggested to have been a Part 36 offer and/or one which the claimants have bettered, but Mr Crowley relies on it as relevant both to the proportionality of recovery and the claimants' conduct.
iii) The claimants are individuals who have privately funded the claim and ultimately succeeded. There has been, Mr Crowley submits, nothing unreasonable in their conduct which should be penalised in costs. They have been unsuccessful on some issues but not to an extent where it can be said that they have unreasonably pursued a claim, issue or allegation. There is no reason for the court to make an issue based costs order or to order payment of a portion only of the claimants' costs.
iv) The defendants' principal means of protecting their position on costs was to make effective Part 36 offers. No such offers were made.
"The fact that the judge has such a wide discretion under Rule 44.2 means that predicting the outcome of an issue-based approach is extremely difficult. Different judges may take strongly diverging approaches in similar cases without falling into error and their decisions being amenable to appeal. Criticism has been made of 'a growing and unwelcome tendency' by first instance courts and by the Court of Appeal to depart from the 'starting point' of the general rule 'too far and too often'."
The citation given for that is Fox v Foundation Piling Ltd [2011] EWCA Civ 790 at paragraph 62 as per Jackson LJ. Continuing the quote:
"That criticism applies principally to departures from the general rule by the adoption of an issue-based approach.
Propositions that may be derived from the authorities and which may be stated with a degree of confidence are as follows:
1. The rules themselves impose no requirement to the effect that an issue-based costs order should be made only 'in a suitably exceptional case', and none is to be implied, although 'there needs to be a reason based on justice' for departing from the general rule, and that the question of the extent to which costs of a particular issue are to be disallowed should be left to the evaluation and discretion of the judge, 'by reference to the justice and circumstances of the particular case' (F&C Alternative Investments (Holdings) Ltd v Barthelemy No 3 [2012] EWCA Civ 843, [2013] 1 WLR 548 CA at [47] and [49] per Davis LJ ) (a case where a proportionate costs order, made in relation to two issues on which the parties who had succeeded overall had not succeeded, was upheld.))
2. The reasonableness of taking failed points can be taken into account and the extra costs associated with them should be considered". [Two references are given for that proposition which I do not intend to recite.]
"3. Where the circumstances of the case require an issue-based order in the form of an order expressed by reference to the costs of the issue, that is what the judge should make; however, generally because of the practical difficulties which this causes, the judge should hesitate before doing so and, where practicable, the order should be expressed as a percentage or with reference to a distinct period of time. (Rule 44.2(7)) (Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2008] EWHC 2280 (TCC), Jackson J at [72(iv)].
4. There is no automatic rule requiring an issue-based costs order in the form of a reduction of a successful party's costs if he loses on one or more issues. HLB Kidsons v Lloyds Underwriters [2007] EWHC 2699 (Comm), Gloster J at [10]. "The mere fact that the successful party was not successful on every last issue cannot of itself justify an issue-based costs order (J Murphy & Sons Ltd v Johnston Precast Ltd (No 2) [2008] EWHC 3104 (TCC), Coulson J at [10].).
5. The courts recognise that in any litigation, especially complex commercial litigation but including personal injury litigation, any winning party is likely to fail on one or more issues in the case (possibly issues on which the losing party could have taken steps to protect himself, at least to an extent, to costs liability). That point is frequently made…." [A number of authorities are cited in support of that proposition, which again I do not intend to recite].
Marbank
i) So far as claims are concerned Mr Clay relies firstly on the fact that the claimants' claim failed on item 10 (Accoya) item 11 (the Bauder green roof), item 12 (the stairwell rooflight) and item 28 (Brise Soleil), and that, as opened, the claimants' claims in respect of these items totalled approximately £160,000. In respect of these claims he submitted that they featured prominently in the evidence for trial and occupied considerable time at trial.
ii) The claim for alternative accommodation included two years' of alternative accommodation for Mrs Vainker. I found that period to be unreasonable for the carrying out of remedial works to the glass balustrades. There was a claim for £110,000 for lost rental income because the rental property was used as accommodation for Mrs Vainker's son and his family. I found this claim to be too remote. Mr Clay also pointed to the claim for lost liquidated damages which was made and could only be made against M&M.
iii) As to these two latter points, the alternative accommodation and lost liquidated damages, they did not occupy any or any significant time at trial and I take the submission to be that they are relevant to the extent to which the claimant succeeded against Marbank.
iv) Mrs Vainker's contract with Marbank was under seal and there were no limitation issues so far as Marbank was concerned. The position was entirely different so far as SCd was concerned and, as I said in giving judgment, that was why the claimants' focus in respect of some of the larger claims was on the Defective Premises Act 1972. Mr Clay submitted that the only reason for the DPA claim was the fact that the claimants wished to pursue SCd and could only realistically do so under the Defective Premises Act because of the limitation defences available to SCd in contract and tort. He argued that that had a significant impact on the brickwork claims in particular, because the evidence was expanded to advance the case that the property at completion was unfit for habitation. The claim for breach of the DPA failed because I found the discolouration or staining of the brickwork to be an aesthetic defect only.
i) Firstly, the Particulars of Claim gave no credit for any sum outstanding. When the Counterclaim was pleaded the claimants' response was to deny any liability.
ii) Secondly, the claimants' quantum expert, Mr Finn, was not instructed to and did not address the Counterclaim at all in his report, although Marbank's expert did. I note in that context that Mr Crowley drew attention to the fact that in their first joint statement the quantum experts agreed at paragraph 1.8 that: "The experts have not been provided with information on this counterclaim to make an assessment in this QS 1st JS".
iii) Thirdly, Mr Finn only addressed the counterclaim at the last minute. One reason given was that he had not had relevant substantiating documents, such documents did not exist and this was not the product of a failure in disclosure. As a result, he gave figures as figures for some items (not all items) and expressed a view on reasonableness. He could have done so earlier. The other reason given for the timing of his second report was a lack of funds.
SCd
"The principles which guide the court in applying those rules where one party has succeeded overall but has lost on one or more issues and the unsuccessful party seeks an issue-based costs order have been considered in many cases." He then set out the multiple cases that he had been referred to which wholly or largely reflect the cases referred to in the White Book note which Mr Crowley relies upon. He then said this at paragraph 6:
"I would summarise those principles as follows:
(1) The mere fact that the successful party was not successful on every issue does not, of itself, justify an issue-based costs order. In any litigation, there are likely to be issues which involve reviewing the same, or overlapping, sets of facts and where it is therefore difficult to untangle the costs of one issue from another. The mere fact that the successful party has lost on one or more issues does not by itself normally make it appropriate to deprive them of their costs.
(2) Such an order may be appropriate if there is a discrete or distinct issue, the raising of which caused additional costs to be incurred. Such an order may also be appropriate if the overall costs were materially increased by the unreasonable raising of one or more issues on which the successful party failed.
(3) Where there is a discrete issue which caused additional costs to be incurred, if the issue was raised reasonably, the successful party is likely to be deprived of its costs of the issue. If the issue was raised unreasonably the successful party is likely also to be ordered to pay the costs of the issue incurred by the unsuccessful party. An issue may be treated as having been raised unreasonably if it is hopeless and ought never to have been pursued.
(4) Where an issue-based costs order is appropriate, the court should attempt to reflect it by ordering payment of a proportion of the receiving party's costs if that is practicable.
(5) An issue-based costs order should reflect the extent to which the costs were increased by the raising of the issue; costs which would have been incurred even if the issue had not been raised should be paid by the unsuccessful party.
(6) Before making an issue-based costs order, it is important to stand back and ask whether, applying the principles set out in CPR Rule 44.2, it is in all the circumstances of the case the right result. The aim must always be to make an order that reflects the overall justice of the case."
"In light, though, of your observation that a costs plus offer may be of interest to your clients and your express view that it would be possible to hive off costs attributable to your pursuit of our client, perhaps you could give us an indication of the level of costs you say are so attributable."
There was no response to this email.
"Third, I accept Lord Marks' submission that, in those circumstances, the judge should have approached the question of costs on the basis that the very best Quayside could do - on the basis of an application of the general rule and before he came to consider the Calderbank offers - was to secure an order that Walker pay a proportion of its costs; and that that approach should then have governed the judge's approach to the Calderbank offers when he came to consider them.
86. Fourth, the judge, when considering Walker's Calderbank offer dated 5 January 2011 does not appear to have given appropriate weight to the fact that Walker could not realistically have made a Part 36 offer in January 2011, because that would have had the automatic consequence that, if the offer were accepted, Quayside would have been entitled to all its costs of the proceedings to date; see CPR 36.10(1)…
87. However the judge does appear to have recognised at paragraph 18 of his costs judgment that, if Walker had accepted Quayside's Part 36 offer made on 3 May 2011, that would have involved Walker in:
'having to pay costs assessed on the basis of the counterclaims that then stood at £169,000, producing a wholly disproportionate sum of costs'.
But, as Lord Marks pointed out, exactly the same consideration would have applied to the making of a Part 36 offer instead of a Calderbank offer in January 2011…
91. In other words the judge appears to have accepted that a figure in the region of, or possibly in excess of, £30,000 had been incurred by 5 January 2011 in respect of costs on the indemnity basis. As Lord Marks submitted, the judge should then have asked himself whether the allowance of about £19,000 for costs, in Walker's Calderbank offer, given Quayside's ultimate recovery of about £11,000, represented a reasonable offer on costs. I accept Lord Marks' submission that such an offer was indeed a reasonable and proportionate one. The judge was entitled to look at the matter with the benefit of hindsight and in the knowledge that Quayside had made a very small recovery on its counterclaim. Whether or not he went into the detailed arithmetic, there were certainly grounds for calculating on a rough and ready basis that, against a figure of £30,000 plus of costs on the indemnity basis, substantial deductions would have needed to have been made to reflect…"
Her Ladyship then set out a number of reasons why that figure would have been reduced.
"In my judgment, on any realistic appraisal of the position as at 5 January 2011, the judge should have come to the conclusion that, given the ultimate outcome, an offer to pay costs in a net sum of £19,000 as at 5 January 2011 was in fact generous and that Quayside had not beaten that offer. He should consequently have found that Walker's Calderbank offer of £30,000 inclusive was an offer which Quayside should have accepted. Moreover a reality crosscheck would have demonstrated that a recovery of £19,000 in respect of costs at the early stages of this case was proportionate. There was therefore no reason for Walker to have accepted Quayside's subsequent Calderbank offer dated 8 March which invited Walker to pay £40,000 inclusive of costs."
Interim payment on account of costs
Interest
The reserved costs