BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> CNO Plant Hire Ltd v Caldwell Construction Ltd [2024] EWHC 2188 (TCC) (21 August 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/2188.html Cite as: [2024] EWHC 2188 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS IN LEEDS
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
____________________
C.N.O PLANT HIRE LTD |
Claimant |
|
- and - |
||
CALDWELL CONSTRUCTION LIMITED |
Defendant |
____________________
Mr David Fearon (instructed by Gunner Cooke LLP) for the Defendant
____________________
Crown Copyright ©
Her Honour Judge Kelly
Background
"Phase 1, 1a and 1b
Earthworks – Plots and External Areas £367,774.47
Phases 2 & 3
Earthworks – Plots and External Areas £119,462.45
Roads & Footpaths – All Phases
See schedule for breakdown £173,031.28
Piling Mats – All Phases
See schedule for breakdown £30,732.14
Variations
Refer to Variations tab for breakdown £668,842.09"
The Law
(1) Where a valid application for payment has been made, an employer who does not issue a valid payment notice or pay less notice must pay the 'notified sum' in accordance with section 111 of the Act;
(2) Failure to pay the notified sum entitles the contractor to seek payment of the sum by obtaining an adjudication award;
(3) Unless otherwise directed by the adjudicator, the parties are required to comply with the decision immediately;
(4) The courts take a robust approach to enforcement, regardless of errors of procedure, fact or law, unless in excess of jurisdiction or breach of natural justice;
(5) When a party is required to pay a 'notified sum', that party may embark upon a true valuation of the work done, but only after it has complied with the immediate payment obligation under section 11 of the Act.
(1) S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448 - where a party is required to pay a notified sum but fails to do so, it may not commence a true value adjudication.
(2) Broseley London Limited v Prime Asset Management Limited [2020] EWHC 944 (TCC) - the principle set out in Grove prevents a paying party from commencing a true value adjudication without first paying the amount awarded in a previous adjudication decision.
(3) Sudlows Limited v Global Switch Estates 1 Limited [2023] EWCA Civ 813 – to decide whether an adjudicator lacks jurisdiction as to a dispute previously referred, the adjudicator should give a robust and common sense answer, looking to see what the earlier adjudication actually decided and considering the need for flexibility to prevent a party re-adjudicating a claim.
(4) Lidl Great Britain v Closed Circuit Cooling Limited [2023] EWHC 3051 (TCC) - whilst there is no blanket principle on commencing a true value adjudication before satisfying an award made in respect of an interim payment application, the Grove principle does prevent a paying party from commencing a true value adjudication on matters which were subject to a decision on the same payment cycle "insofar as they are matters which could have been the subject of the pay less notice served in respect of the particular notified sum in question".
"The general position is that adjudicators' decisions which direct the payment of money by one party to another are to be enforced summarily and expeditiously ... No set off or withholding against payment of that amount should generally be permitted…
"There are, however, at least three limited exceptions to this general position:
(i) a first, "relatively rare", exception will be where there is a specified contractual right to set off…
(ii) a second exception may arise where it follows logically from an adjudicator's decision that the adjudicator is permitting a set off to be made against the sum otherwise decided to be payable…
(iii) a third exception may arise in an appropriate case, at the discretion of the court, where there are two valid and enforceable adjudication decisions involving the same parties whose effect is that monies are owed by each party to the other…"
"(a) First, it is necessary to determine at the time when the court is considering the issue whether both decisions are valid; if not or if it cannot be determined whether each is valid, it is unnecessary to consider the next steps.
(b) If both are valid, it is then necessary to consider if, both are capable of being enforced or given effect to; if one or other is not so capable, the question of set off does not arise.
(c) If it is clear that both are so capable, the court should enforce or give effect to them both, provided that separate proceedings have been brought by each party to enforce each decision. The court has no reason to favour one side or the other if each has a valid and enforceable decision in its favour.
(d) How each decision is enforced is a matter for the court. It may be wholly inappropriate to permit a set off of a second ?nancial decision as such in circumstances where the First Decision was predicated upon a basis that there could be no set off".
The Issues
(1) As the Defendant has not issued enforcement proceedings in respect of the second adjudication, should the court consider exercising its power to order a set off?
(2) Should the court permit a set off on the facts of this case?
As the Defendant has not issued enforcement proceedings in respect of the second adjudication, should the court consider exercising its power to order a set off?
Should the court permit a set off on the facts of this case?