BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Workman Properties Ltd v Adi Building And Refurbishment Ltd [2024] EWHC 2627 (TCC) (21 October 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/2627.html Cite as: [2024] EWHC 2627 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KB)
London, EC4A 1NL |
||
B e f o r e :
(sitting as a High Court Judge)
____________________
WORKMAN PROPERTIES LIMITED |
Claimant |
|
- and – |
||
ADI BUILDING AND REFURBISHMENT LIMITED |
Defendant |
____________________
James Thompson (instructed by Pinsent Masons LLP) for the Defendant
Hearing date: 8 October 2024
Draft judgment circulated: 15 October 2024
____________________
Crown Copyright ©
His Honour Judge Stephen Davies:
The approach of the parties to the suitability issue
Suitability by reference to the issue of contract interpretation
"I have little reason to suppose that the context at the time of concluding the First Reseller Agreement is genuinely contentious (given the evidence I have seen to date) and it is difficult to see that the court's understanding or assessment of that context will be affected to any material degree by the evidence at trial. No doubt there would be more details as to the approach each party took to the Reseller Agreements, their subjective intentions and the negotiations, but little, if any of this is likely to be admissible and accordingly it is very unlikely that the court's understanding of the overall picture will really change. PTAP could have done more to seek to convince the court that the picture at trial will be different, but where it has apparently chosen not to engage with that exercise, it cannot expect the court to shy away from the invitation to grasp the nettle."
Suitability by reference to wider issues
"a. The design contained in the Employer's Requirements was not:
i. generally a completed RIBA Stage 4 design; and
ii. except in relation to containment, a completed stage 4(i) design for Building Services.
b. WPL warranted to ADI that:
i. the design included in the Employer's Requirements had been taken to the end of RIBA Stage 4; and
ii. the design of the Building Services had been developed to RIBA Stage 4(i).
c. ADI is entitled to damages for breach of contract and/or the Warranty caused by:
i. the failure of the design included in the Employer's Requirements to achieve RIBA Stage 4; and
ii. the failure of the design of the Building Services to achieve RIBA Stage 4(i).
d. The Contract terms in relation to extensions of time under Section 2 continue to apply and the obligation to complete under those terms has not been replaced by an obligation to complete within a reasonable time.
e. The liquidated damages regime at Clause 2.29 of the Contract continues to apply.
f. Works carried out by ADI to develop the design from that set out in the Employer's Requirements so as to achieve RIBA Stage 4 and to achieve RIBA Stage 4(i) for the Building Services constitute Change(s) under Clause 5.1 of the Contract.
g. WPL's breach of the Warranty constitutes a Relevant Event under clause 2.26 of the Contract and a Relevant Matter under Clause 4.21."
The contract
The Employer's Requirements
"The Contractor will enter into a contract under the JCT Design and Build 2016 (DB2016) as amended by Schedule of Amendments contained within this Employer's Requirements document and will be fully responsible for the complete design, construction, completion, commissioning and defects rectification of the works.
Significant design has been developed to date which has been taken to end of RIBA Stage 4 with some parts of contractor specialist design elements together with Services design to Stage 4 (i) with generic design and performance requirements in order to deliver what the Employer is requiring within their controlled budget."
The contract terms
The claimant's submissions
"In my judgment the obligation of Boot under Clause 2.1.2 of the Conditions was to complete the design of the contiguous bored piled walls, that is to say, to develop the conceptual design of CHW into a completed design capable of being constructed. That process of completing the design must, it seems to me, involve examining the design at the point at which responsibility is taken over, assessing the assumptions upon which it is based and forming an opinion whether those assumptions are appropriate. Ultimately, in my view, someone who undertakes, on terms such as those of the Contract (that is to say, including Clause 2.7) an obligation to complete a design begun by someone else agrees that the result, however much of the design work was done before the process of completion commenced, will have been prepared with reasonable skill and care. The concept of "completion" of a design of necessity, in my judgment, involves a need to understand the principles underlying the work done thus far and to form a view as to its sufficiency. […] If and insofar as the design of the walls remained incomplete at the date of the Contract, Boot assumed a contractual obligation to complete it, quite apart from any question of producing working drawings. […]".
The defendant's submissions
Conclusions on the question of contract interpretation
The declarations sought
i) The defendant has taken full responsibility for and taken the risk of the entirety of the design of the Works, including as to the adequacy of the design contained in the Employer's Requirements.
ii) The defendant is contractually obliged to complete any and all necessary works to complete the design of the Works as a whole, including any outstanding design works required to develop the design up to and beyond RIBA Stage 4/4(i).
iii) The claimant has not contractually warranted or undertaken to the defendant that the design contained in the Employer's Requirements (or the majority thereof) had been adequately developed up to RIBA Stage 4/4(i).
iv) The defendant is in any event contractually estopped from denying that it had thoroughly examined the design contained in the ERs and/or that the design contained in the Employer's Requirements had been adequately developed up to RIBA Stage 4/4(i).
v) The defendant is not entitled to damages for breach of contract and/or breach of a warranty, even if the design contained in the Employer's Requirements did not achieve RIBA Stage 4/4(i).
vi) The design works (if any) carried out by the defendant to develop the design in the Employer's Requirements to achieve RIBA Stage 4 / 4(i) do not amount to a Change under clause 5.1, a Relevant Event under clause 2.26 and/or a Relevant Matter under clause 4.21 of the Contract.
vii) The defendant is not contractually entitled to any additional time, costs and/or loss and expense for design works (if any) carried out by it to develop the design in the Employer's Requirements up to RIBA Stage 4/4(i).
viii) Any other declarations that the Court considers to be appropriate.
A final observation about venue
Note 1 This was in the voluminous hearing bundle before me, but I was not specifically referred to it at the hearing. [Back]