BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Ireland Decisions |
||
You are here: BAILII >> Databases >> High Court of Ireland Decisions >> Ashbourne Holdings Ltd. v. Bord Pleanala [2001] IEHC 98 (19th June, 2001) URL: http://www.bailii.org/ie/cases/IEHC/2001/98.html Cite as: [2002] 1 ILRM 321, [2001] IEHC 98 |
[New search] [Printable RTF version] [Help]
1. This
decision arises out of an application made on behalf of the first named
Respondent, following the judgment of this Court delivered on the 21st day of
March, 2001, whereby the Court has been asked to certify that its determination
of that date involves a point of law of exceptional public importance and that
it is desirable in the public interest that an appeal should be taken to the
Supreme Court.
2. In
this context, the Court was referred to the Judgment of McKechnie J in
Kenny
-v- An Bord Pleanala
(unreported Judgment delivered the 2nd day of March, 2001) which contains a
most helpful resume and review of the criteria applicable when considering this
section. His review of the case law indicates a considerable degree of
uncertainty and subjectivity in decisions whether or not to grant a
certificate. In accepting fully the statement of considerations enumerated at
pp. 3 - 4 of the Judgment of McKechnie J, I would simply add the observation
that the terminology of the section seems to clearly convey that the point of
law must arise out of the decision of the High Court itself, and not merely
from discussion or consideration of a point of law during the hearing, be it of
major or minor import, which did not go to the actual determination or decision
itself. In other words, there is no place for a moot on some interesting point
which may have arisen in the case. The point of law must be ‘of’
or in some way contained ‘in’ the decision or determination in the
first instance, and must at the same time transcend the case itself to meet the
requirements of exceptional public importance and public interest. On this
point, both parties have stressed, and I entirely agree, that “public
interest” is not to be confused with considerations of
‘newsworthiness’ or heightened public controversy surrounding the
particular case.
3. The
judgment delivered on the 21st day of March, 2001 related to certain conditions
attaching to a retention permission granted by the Respondents in relation to
the golf clubhouse which is part of the golf course development at the Old Head
of Kinsale in Cork. The judgment essentially decided or determined three
matters.
4. The
first related to the condition imposed upon the Applicant to maintain and
preserve the ruins of de Courcey Castle which is located immediately beside the
entrance to the Golf development and which said condition was upheld by the
Court.
5. The
second element in the judgment related to a condition requiring the developer
to provided access at all times during daylight hours for the public to the
lighthouse at the southern tip of the headland and for access to the cliff
paths and cliff edges for interest groups. This access was not by means of any
dedicated paths or routes. The Court found such a condition, which effectively
permitted members of the public to wander at will over playing areas of the
golf course, to be manifestly unreasonable to such a degree as to render
potentially inoperable the user of the headland as a golf course. This
condition was not upheld.
6. The
third element of the judgment related to a more specific form of public access
whereby members of the public were to be provided with access via a gravel path
between de Courcey Castle and a picnic area near the Old Lighthouse Compound,
all on the northern rim of the headland.
7. While
no public rights of way were asserted or established during the course of
hearing before this Court, the Court held that this third condition was not per
se either irrational or manifestly unreasonable, for reasons which included (a)
that it had been offered by the developer and (b) that it was a limited form of
public access via a dedicated path at a location on the headland which did not
impinge or interfere grossly with the Applicant’s ability to operate the
golf course.
8. However,
although the form of public access imposed by this particular condition had the
characteristics of a newly created public right of way, it was common case that
the second named Respondent had not followed the statutory procedures
appropriate to the creation of a right of way. It had been open to the
planning authority under Section 47 of the Local Government (Planning and
Development) Act, 1963 to enter into an agreement with the developer to create
a right of way on such terms as to payment or otherwise as might be agreed and
subject to such limitations or conditions as might be agreed affecting such
public right of way. Alternatively, it was open to the second named
Respondent, under Section 48 of the same Act, if it considered there was need
for a public right of way over the land, to make an order creating a public
right of way over the land, which would have had certain implications for the
payment of compensation to the developer.
9. Neither
of these options was pursued. Instead the second named Respondent by imposing
the condition in the manner in which it did shifted responsibility onto the
developer both to provide a designated form of public access in the nature of a
right of way, maintain it and charge for it, subject to the requirement
contained in the condition that any charge should not exceed the cost of
insurance and the administration of entrance control and should not be
increased in any event save with the consent of the planning authority.
10. The
Court accepted the Applicants submissions that the imposition of such a
condition operated to circumvent the existing statutory provisions, whilst at
the same time depriving the Applicant both of compensation and of the right to
derive a profit from his ownership in the property. The Court further found
that the charging provisions attached to the said condition were void for
uncertainty.
11. Following
delivery of the judgment, Counsel on behalf of the first named Respondent
advanced a number of points for consideration by the Court as being suitable
for certification by way of appeal to the Supreme Court under the statutory
provision already cited.
12. These
submission were received by the Court immediately in the aftermath of
delivering its judgment and further oral submissions were received by the Court
on the 13th day of June, 2001. On that occasion, Mr. Collins on behalf of the
first named Respondent effectively confined his submissions to the third
condition outlined above, namely, that which imposed a right of public access
via a dedicated route between de Courcey Castle and the Old Lighthouse Compound
on the northern rim of the headland.
13. I
will first state the suggested point of law in its essential short form and
then in the more detailed form in which it was formulated to the Court by Mr.
Collins, together with one amendment of my own which I have added to and
underlined in his original text, and as further enlarged following submissions
made by Mr. Gleeson on behalf of the Applicant.
14. In
short, the point upon which the opinion of the Supreme Court is sought is
whether or not a planning authority, where specific statutory measures exist
and are available to it for the creation of a public right of way, may
nonetheless chose to impose a condition which for all practical purposes
creates a right of way but which not only avoids the usual consequences which
attend the exercise of the specific statutory powers but which also imposes
further attendant obligations on a developer.
15. The
more detailed form of the question formulated by Mr. Collins for consideration
is as follows:-
16. On
behalf of the Applicant, Mr. Gleeson argued firstly, that no point of law
arises from these questions which meets the criteria of S. 82 (3B)(b)(i) and,
secondly, that the access provision could not be viewed in isolation from the
charging provision which was annexed to it and which the Court had found to be
void for uncertainty. He submits that this finding by the Court in its
judgment effectively subverts the meaningful consideration of any such point of
law as suggested by Mr. Collins.
17. It
seems to me that a point of law of exceptional public importance and public
interest does arise where uncertainty as to the powers of a planning authority
in such a vital area may be shown to exist and that I should refer to the
Supreme Court for its opinion and decision, the question just detailed. As the
short form statement of the point of law indicates, I have decided to add to
the list supplied by Mr. Collins the two following matters as being
appropriate to the issues the Supreme Court may require to consider:-