BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> City Inn v. Shepherd Construction Ltd [2003] ScotCS 146 (20 May 2003) URL: http://www.bailii.org/scot/cases/ScotCS/2003/146.html Cite as: [2003] ScotCS 146 |
[New search] [Help]
SECOND DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord Justice Clerk Lord Kirkwood Lord McCluskey
|
A4322/01 OPINION OF THE COURT delivered by THE LORD JUSTICE CLERK in RECLAIMING MOTION in the cause CITY INN LIMITED Pursuers and Respondents; against SHEPHERD CONSTRUCTION LIMITED Defenders and Reclaimers: _______ |
Act: Keen, QC; McGrigor Donald
Alt: Currie, QC, Borland; Masons
20 May 2003
Introduction
The dispute
The contract
" ... the Contractor ... shall ... regularly and diligently proceed with the [works] and shall complete the same on or before the Completion Date."
Clause 24.2.1 provides inter alia as follows:
" ... the Contractor shall ... pay or allow to the Employer liquidated and ascertained damages at the rate stated in the Appendix ... for the period between the Completion Date and the Date of Practical Completion."
The rate stated in the Appendix is £30,000 weekly pro rata. It is agreed that that is a genuine pre-estimate of the employer's probable loss if the contractor should delay in completion.
Clause 25.3.3 provides inter alia as follows:
"After the Completion Date, if this occurs before the date of Practical Completion, the Architect may, and not later than the expiry of twelve weeks after the date of Practical Completion shall, in writing to the Contractor either
The relevant events are defined in clause 25.4 and are, in general, events over which the contractor has no control.
"13.8.1. Where, in the opinion of the Contractor, any instruction, or other item which, in the opinion of the Contractor, constitutes an instruction issued by the Architect, will require an adjustment to the Contract Sum and/or delay the Completion Date, the Contractor shall not execute such instruction (subject to Clause 13.8.4) unless he shall have first submitted to the Architect, in writing, within 10 working days (or within such other period as may be agreed between the Contractor and the Architect of receipt of the instruction, details of:
1. initial estimate of the adjustment (together with all necessary
supporting calculations by reference to the Contract Documents);
2. initial estimate of the additional resources (if any) required and his
method statement for compliance;
3. initial estimate of the length of any extension of time to which he
considers he is entitled under Clause 25 and the new Completion Date (together with all necessary supporting documentation by reference to the Master Programme);
4. initial estimate of the amount of any direct loss and/or expense to
which he may be entitled under Clause 26; and
13.8.3. If agreement cannot be reached within 5 working days of receipt by the Architect of the Contractor's estimate on all or any of the matters set out therein; then;
1. the Architect may nevertheless instruct the Contractor to comply with
the instruction; in which case the provisions of Clauses 13.5.25 and 26 shall apply; or
2. the Architect may instruct the Contractor not to comply with the
instruction, in which case the contractor shall be reimbursed all reasonable costs associated with the abortive instructive (sic).
13.8.5. If the Contractor fails to comply with any one or more of the provisions of Clause 13.8.1, where the Architect has not dispensed with such compliance under Clause 13.8.4, the Contractor shall not be entitled to any extension of time under Clause 25.3."
Clause 13.8.5 therefore has the effect that if the contractor on receipt of an instruction fails to take action under clause 13.8.1, he not only loses his entitlement to an extension of time under clause 25.3 (supra) but incurs a potential liability to pay liquidate damages under clause 24.2.1 (supra) if, by reason of the instruction, he should fail to meet the completion date.
The pleadings
"Ans. 8(i) clause 13.8.5 amounts to a penalty clause and as such is unenforceable. In the event of a breach by the defenders of clause 13.8.1, the effect of 13.8.5 would be to deprive the defenders of extensions of time to which they would otherwise have been entitled and to expose the defenders to liability for liquidate and ascertained damages to which they would not otherwise have been exposed. The rate of liquidate and ascertained damages was a pre-estimate of the loss and damage which the pursuers might sustain as a result of delay in completion and not of the loss and damage which they might sustain as a result of the breach of clause 13.8.1."
To this, the pursuers reply as follows:
"Clause 13.8 is not a penalty clause. It imposes a mandatory condition precedent to the defenders' entitlement to an extension of time. The satisfaction of that condition precedent was within the control of the defenders."
The defenders' averments on the trigger point are inter alia as follows:
"Ans 8(ii) clause 13.8.1. only applied if the defenders, upon receipt of the instruction, actually formed the opinion about the requirements of the instruction as set out therein."
To this, the pursuers reply inter alia as follows:
"The application of Clause 13.8 is conditional upon the defenders forming an opinion on certain matters. It is implicit in the terms of clause 13.8 that on receipt of an instruction the defenders required to address their minds (with a view to compliance with clause 13.8) to the question of whether or not the instruction would require an adjustment to the Contract Sum or delay the Completion Date. In all the circumstances of the present case it is believed and averred that the defenders did not address their minds to these matters with a view to compliance with clause 13.8. The defenders are not entitled to found on their own failure as a basis for denying the application of clause 13.8. The opinions formed by the defenders from time to time are uniquely within their knowledge ... "
The decision reclaimed against and the grounds of appeal
The Lord Ordinary's Opinion
The penalty clause point
The trigger point
Decision
The penalty clause point (answer 8(i))
(b) Whether clause 13.8.5 imposes a penalty
The trigger point (answer 8(ii))
Interlocutor