OUTER HOUSE, COURT OF SESSION
[2006] CSOH 94
|
CA240/01
|
OPINION OF
LORD DRUMMOND YOUNG
in the cause
CITY INN LIMITED
Pursuers;
against
SHEPHERD
CONSTRUCTION LIMITED
Defenders:
ннннннннннннннннн________________
|
Pursuers: Keen, QC; McGrigor
Donald
Defenders: Borland; Pinsent
Masons
20 June 2006
The background to the action
[1] The pursuers and the defenders are respectively the employer
and the contractor under a building contract for the construction of a hotel at
Finnieston Quay, Glasgow. The contract was governed by the JCT Standard
Form of Building Contract Private Edition with Quantities (1980 Edition),
together with the Scottish Supplement and a number of amendments prepared
specifically for the purposes of the contract; these are contained in a
Schedule of Amendments. Clause 23.3.1 of
the conditions applicable to the contract obliges the contractor to complete
the works on or before the Completion Date; the Completion Date specified in
the contract was 20 August 1999. Clause 24.1 provides that, if the contractor
fails to complete the works by the Completion Date, the contract architect is
to issue a certificate to that effect.
Clause 24.2.1 provides that the contractor is obliged to pay liquidated
and ascertained damages for the period between the Completion Date and the date
of practical completion. The rate of
liquidated and ascertained damages was fixed by the parties' contract at
г30,000 per week. The foregoing
provisions are, however, subject to the possibility of an extension of time
under clause 25 of the conditions.
Clause 25 permits the architect to grant an extension of time, and in
consequence to fix a new Completion Date in terms of clause 25.3.3, if any one
or more of the relevant events specified in clause 25.4 has occurred. The relevant events listed in clause 25.4
cover a wide range of circumstances, but the feature that they have in common is
that their occurrence is not the fault of the contractor.
[2] The
foregoing provisions are subject to clause 13.8 of the Schedule of Amendments
prepared for the purposes of the parties' contract. Clause 13.8 is in the following terms:
"13.8.1
Where, in the opinion of the Contractor, any instruction, or other item which,
in the opinion of the Contractor, constitutes an instruction issued by the
Architect, will require an adjustment to the Contract Sum and/or delay the
Completion Date, the Contractor shall not execute such instruction (subject to
Clause 13.8.4) unless he shall have first submitted to the Architect, in
writing, within 10 working days (or within such other period as may be agreed
between the Contractor and the Architect[)] of receipt of the instruction,
details of:
1. Initial estimate of the adjustment (together
with all necessary supporting calculations by reference to the Contract
Documents);
2. Initial estimate of the additional resources
(if any) required and his method statement for compliance;
3. Initial estimate of the length of any
extension of time to which he considers he is entitled under Clause 25 and the
new Completion Date (together with all necessary supporting documentation by
reference to the Master Programme);
4. Initial estimate of the amount of any direct
loss and/or expense to which he may be entitled under Clause 26; and
5. any such other information as the Architect
may reasonably require.
"13.8.2
The Contractor and the Architect shall then, within 5 working days of receipt
by the Architect of the Contractor's estimates, agree the Contractor's
assessments. Following such agreement,
the Contractor shall immediately thereafter comply with the instruction and the
Architect shall grant an extension of time under Clause 25.3 of the agreed
length (if any) and the agreed adjustments (if any) and the agreed adjustments
(if any) in relation to clauses 13.8.1.1 and 13.8.1.4 shall be made to the
Contract Sum.
"13.8.3
If agreement cannot be reached within 5 working days of receipt by the
Architect of the Contractor's estimate on all or any of the matters set out
therein; then;
1. the Architect may nevertheless
instruct the Contractor to comply with the instruction; in which case the
provisions of Clauses 13.5, 25 and 26 shall apply; or
2. the Architect may instruct the Contractor
not to comply with the instruction, in which case the contractor shall be
reimbursed all reasonable costs associated with the abortive [instruction].
"13.8.4
The Architect may, by notice to the Contractor before or after the issue of any
instruction, dispense with the Contractor's obligation under Clause 13.8.1, in
which case the Contractor shall immediately comply with the instruction and the
provisions of Clauses 13.5, 25 and 26 shall apply.
"13.8.5
If the Contractor fails to comply with any one or more of the provisions of
Clause 13.8.1, where the Architect has not dispensed with such compliance under
Clause 13.8.4, the Contractor shall not be entitled to any extension of time
under Clause 25.3".
[3] On
21 August 1999 the architect issued a certificate of non-completion
certifying that the defenders had failed to complete the works by the
Completion Date. On 28
March 2000
the architect issued a certificate of practical completion certifying that
practical completion of the works was achieved on 24 March
2000. The result of these certificates was that the
pursuers were entitled under clause 24 to deduct liquidated and ascertained
damages for the 31-week period from 20 August 1999 to 24 March
2000 at a
weekly rate of г30,000. The pursuers in
fact deducted a total of г660,000, representing liquidated and ascertained
damages for 22 weeks. By the time the
deductions were made an adjudicator had granted an extension of time of nine
weeks, thus reducing the period of delay from 31 weeks to 22 weeks.
[4] The
defenders referred certain disputes between the parties to adjudication by
notices of adjudication dated 5 November 1999 and 21 July
2000. In the first of these adjudications the
adjudicator decided that the defenders were entitled to a nine-week extension
of time as a result of variations to the scope of the piling works instructed
by an architect's instruction. That was
the extension of time reflected in the deduction of liquidated and ascertained
damages. In the second adjudication the
adjudicator decided that the defenders were entitled to a fourteen-week
extension of time in consequence of the timing and effect of a number of
architect's instructions. Those
decisions of the adjudicator are of course not conclusive, and their effects
may be reversed by subsequent court proceedings. The present action has been raised by the
pursuers in order to obtain a decision by the court on the matters determined
by the adjudicator.
[5] The
pursuers contend that the defenders were not entitled to any extension of time
beyond the original contractual Completion Date of 20 August
1999. The first conclusion of the summons is for
declarator that the Completion Date is 20 August 1999.
The second end third conclusions are for payment of the total sum of
liquidated and ascertained damages that would have been due by the defenders if
no extension of time had been granted and the Completion Date was 20
August 1999. Any entitlement that the pursuers have to
those sums obviously follows from whether they are correct in contending that
no extension of time should have been granted.
[6] As
the contract works proceeded certain further disputes were referred to two
further adjudications, started by notices of adjudication dated 10
July 2001
and 11 December 2001.
In these two adjudications the adjudicators decided that the defenders
were entitled to payment of certain sums by the pursuers. The pursuers now seek to reopen the matters
that were in dispute in those adjudications, and the third and fourth
conclusions of the summons are for repayment of the sums paid in consequence of
the adjudicators' decisions. The present
opinion is not, however, concerned with that aspect of the action.
[7]
The defenders have lodged a counterclaim in which they raise a number of issues. Only one of these is relevant to the present
opinion. This relates to the system of
piling used in the foundations of the hotel.
The defenders aver that they were originally invited to tender on the
basis that the piling works would be a combination of continuous flight auger
vertical piles and short raking piles.
In the course of discussions following the submission of the defenders'
tender, the defenders proposed a value engineering solution whereby only vertical
piles would be used. The defenders aver
that this was accepted by the pursuers and that the contract was concluded on
that basis. The architect then varied
the piling works by instructing (in architect's instruction no 5, issued on 18
August 1998)
a combination of vertical piles and long raking piles in accordance with
certain drawings. The accompanying
specification required that, where instability might occur due to inadequate
lateral support to the ground or the effect of groundwater, permanent casings
should be used on the piles. Difficulties
were encountered in installing the vertical piles, and as a result the
architect agreed that permanent casings could not be used but failed to
instruct an alternative. That left the
defenders and their piling subcontractor to devise an alternative. The alternative that was devised was a
so-called "hybrid piling solution".
The architect confirmed that it had no objection to the use of that
solution, but stated that it had no authority to issue an instruction for its
use. The defenders proceeded with the
hybrid piling solution in the absence of an instruction. They aver that the additional work involved
in that solution delayed completion of the works, and that the architect ought
to have instructed that solution to enable the defenders to carry out and
complete the works in accordance with the parties' contract. Against that background the defenders
conclude for declarator that (a) the hybrid piling solution constituted a
variation to the contract works, (b) the architect's decision not to issue an
instruction requiring the hybrid piling solution as a variation was incorrect,
and (c) the defenders are entitled to such an instruction and a consequential
extension of time in so far as compliance therewith caused delay in completion
of the works. As an alternative, the
defenders seek declarator that the architect's failure to issue an instruction
requiring the hybrid piling solution as a variation was a breach of contract,
with the result that time for completion of the works was rendered at large and
the defenders have no liability to the pursuers in respect of liquidated and
ascertained damages.
[8] The
pursuers have tabled pleas to the relevancy of the defences and the
counterclaim. In the course of the case
management procedure they intimated that they wished to insist on those pleas,
and produced a note of argument. I
accordingly ordered a debate on the issues raised in the note of argument. Three distinct matters were argued in the
course of the debate. I will deal with
each of these in turn.
The application of clause 13.8: acquiescence, personal bar and waiver
[9] Clause
13.8, quoted above at paragraph [2], sets out certain procedures that are to be
followed if the contractor considers that any architect's instruction or the
equivalent will require either an adjustment to the contract sum or delay the
Completion Date. An identical provision
was considered by Lord Macfadyen in an earlier case relating to another
contract between the same two parties, City
Inn Ltd. v Shepherd Construction Ltd.,
2002 SLT 781. Lord Macfadyen made the
following comments (at 793):
"[30] In
my opinion, the language of clause 13.8 is
prima facie applicable to all architect's instructions, including those in
respect of the expenditure of provisional sums.
There is no qualification of the reference in clause 13.8.1 to
architect's instructions to suggest that any subcategory of such instructions
is to be excluded from the scope of the clause.
The repetition of the substance of clause 13.3.1 in clause 13.8.6, although
apparently redundant, lends support to the contention that clause 13.8 applies,
without distinction, to all architect's instructions.
...
"[32] In
my view a distinction falls to be drawn between, on the one hand, a late
instruction which, simply because of its lateness, gives rise to a need to
adjust the contract sum and/or grant an extension of time and, on the other
hand, an instruction which, although late, is of such a nature that it would,
whenever issued, have given rise to a need to make such an adjustment or grant
such an extension. The latter category
of instruction falls, in my view, within the scope of clause 13.8, whereas the
former does not. It is in my view difficult
to formulate the distinction more precisely in the abstract. It would, in my view, be wrong to say simply
that clause 13.8 has no application to late instructions. On the other hand, a failure to comply with
clause 13.8 will not, in my view, exclude a claim for extension of time in so far
as the extension is made necessary by the lateness of the instruction as
distinct from its content.
...
"[35] In
my opinion the architect's power under clause 25.3.3 [to grant extensions of
time] must be read subject to the special provision of clause 13.8.5. Clause 13.8.5 defines the effect of failure
to comply with the provisions of clause 13.8.1 as being that 'the Contractor
shall not be entitled to any extension of time under clause 25.3'.... The
contractor's right to [an extension] is, therefore, in my opinion, removed, in
terms of clause 13.8.5, if the contractor fails to comply with the provisions
of clause 13.8.1".
The defenders reclaimed against the
Lord Ordinary's decision, but his opinion on the foregoing matters was not
challenged.
[10] In
the principal action the pursuers contend that the defenders were not entitled
to any extension of time beyond the original contractual Completion Date of 20
August 1999. In relation to the matters raised in the
first adjudication, they aver that the architect's instruction that gave rise
to that adjudication was not a variation to the contract. If it was a variation, they aver that the
defenders have not complied with the provisions of article 13.8.1 and that the
architect did not dispense with compliance therewith under clause 13.8.4. In relation to the matters raised in the
second adjudication, the pursuers aver that the defenders failed to comply with
the provisions of article 13.8.1 and that the architect did not dispense with
compliance under clause 13.8.4. On that
basis the pursuers say that the defenders are not entitled to an extension of
time.
[11] In
response to the pursuers' averments relating to clause 13.8, the defenders
deploy a number of arguments. In the
first place they contend that the clause does not apply where delay in completion
of the works was caused by the late receipt of instructions from the architect,
and that that covers the delays on which they have founded in claiming an
extension of time. In the second place,
they contend that in any event the pursuers had, either themselves or through
the contract architect, who was their agent, acquiesced in the defenders'
failure to comply with clause 13.8.1. In
the third place, the defenders contend that the pursuers waived compliance with
clause 13.8.1 as a condition precedent to an extension of time under clause
13.8.5. In the fourth place, they
contend that in the circumstances of the works carried out under the contract
it would have been impossible for the defenders to comply fully with the
requirements of clause 13.8.1 and to meet the Completion Date.
[12] At
debate, counsel for the pursuers submitted that the defenders' averments on the
second and third of the above arguments, those relating to acquiescence and
waiver, were irrelevant and should not be remitted to probation. Those averments are in summary as
follows. At an early stage of the works,
the then architect, RMJM, issued architect's instruction no 5, relating to the
piling works. This was issued "for
construction", which indicated that the architect required the defenders
to proceed to execute the instruction forthwith. Further discussion of the piling took place
between RMJM and the defenders, and by letter dated 1 September
1998 RMJM
confirmed the instructions regarding piling and stated that they trusted that
that would allow the defenders to mobilize their piling subcontractor. The defenders then issued a delay notice
under clause 25 of the contract conditions in relation to AI no 5, and
discussions took place between them and RMJM regarding the delay. RMJM requested further particulars in support
of the application for an extension of time.
The defenders aver that that request was consistent with the defenders'
application for an extension of time being dealt with under clause 25. On 26 November 1998 RMJM were replaced as contract
architect by Keppie Architects, and the defenders aver that, following Keppie's
appointment, they proceeded to deal with the defenders' application in terms of
clause 25.
[13]
The defenders further aver that, in each case where an architect's instruction
was given, it was evident that they were proceeding to execute it without the
estimates or method statements referred to in clause 13.8.1. Nevertheless, during the course of the works
and thereafter notices of delay under clause 25 were given and continued to be
given to the architect. No response
founding upon clause 13.8.5 was made to the notices of delay. Instead, the architect dealt with the notices
of delay and extensions of time under clause 25; no attempt was made to found
on clause 13.8 until the second adjudication.
Extensions of time were pursued, argued and dealt with under clause 25.
In these circumstances the defenders aver that the pursuers and the architect
as their agent acted from the start of the project in such a way as to justify
the defenders in believing that extensions of time were being, and would fall
to be, dealt with on the basis of clause 25 of the contract conditions only,
without the necessity of the defenders' complying with the provisions of clause
13.8 if they wished to seek an extension of time and thereby protect themselves
against liquidated damages. If the
pursuers or the architect had indicated earlier that they would seek to rely on
clause 13.8, the defenders aver that they would have taken steps to protect
their position by either seeking a dispensation from the architect from
compliance with clause 13.8.1 or implementing clause 13.8.1.
[14] In
relation to the foregoing averments, counsel for the pursuers submitted that it
was erroneous of the defenders to assert that there had been any failure by
them to comply with clause 13.8.1 which could be acquiesced in by the
pursuers. Clause 13.8.1 did not give
rise to any obligation on the part of the defenders. It should rather be characterized as a
provision dealing with the allocation of a known risk, namely the risk that an
architect's instruction would delay completion of the works and thereby cause
extra costs. The function of the clause
was to determine whether the employer or the contractor should bear the cost of
such delay. It was thus a clause that
could be invoked by the defenders if they chose. The pursuers could not acquiesce in the
defenders' failure to invoke the clause; acquiescence only made sense if the
defenders were subject to an obligation.
In any event, on the defenders' averments all that the pursuers had done
was to fail to refer to clause 13.8 in dealing with applications made under
clause 25. Acquiescence can only be
based on silence or failure to object in cases where the party concerned is
under a legal duty to speak or object:
William Grant & Sons Ltd. v Glen
Catrine Bonded Warehouse Ltd., 2001 SC 901, per LP Rodger at paragraph
[49]. Counsel further submitted that the
defenders' case based on general personal bar was ill-founded. It was based on the proposition that the
defenders had failed in obligations that they had under clause 13.8. That was wrong; clause 13.8 did not give rise
to any obligations. Thus the foundation
for the case of personal bar was not there.
[15] Counsel
for the pursuers further submitted that the defenders' case based on waiver was
irrelevant. Clause 13.8 did not impose
any obligation on the defenders, or confer any correlative right on the
pursuers; consequently there was nothing that the pursuers could waive. He referred to Armia Ltd. v Daejan
Developments Ltd., 1979 SC (HL) 56, where Lord Fraser referred to waiver as
involving the idea of giving up or abandoning a right. On the basis of that authority, he submitted
that there were three requirements of waiver: first, there must be a definite
right; secondly, it must be determined whether that right had been permanently
abandoned; and, thirdly, it was necessary to identify conduct which had been
carried on in reliance on the permanent abandonment of the right. Counsel further referred to Oak Mall Greenock Ltd. v McDonald's
Restaurants Ltd., 9 May 2003, and E & J Glasgow Ltd. v UGC
Estates Ltd., 16 May 2005.
In the latter case Lord Eassie held that a contractual term which is
definitional of a contractual entitlement may be waived. Counsel submitted that the present case did
not involve a definitional term; clause 13.8.1 provided the contractor with an
additional right, but the employer was not given any right that it could waive. Reference was also made to Evans v Argus Healthcare (Glenesk) Ltd.,
2001 SCLR 117, where Lord Macfadyen indicated (at paragraph [11]) that
circumstances that are consistent with retention of the right in question will
not support an inference that the right has been abandoned.
[16] In
the light of those cases, counsel submitted that certain conclusions
followed. First, the pursuers had no
right to insist that the contractor should invoke clause 13.8.1. That was sufficient to preclude waiver, which
required abandonment of a right.
Secondly, even if the pursuers had such a right but did not invoke
clause 13.8.1, they did not thereby waive any right under clause 13.8.5; the
latter clause merely set out the circumstances in which the contractor would be
entitled to an extension of time under clause 25. Thirdly, clause 13.8.4 provided expressly
when there was to be a dispensation from the requirements of clause 13.8; this
involved a notice from the architect.
The defenders did not aver that any such notice had been given by the
architect. Fourthly, counsel submitted
that the circumstances that the defenders did aver were not inconsistent with
retention of any right to insist on compliance with clause 13.8. All that the defenders said was that the architect
had received notices under clause 25 and dealt with them under that
clause. It was not possible to infer
from that fact that the pursuers' rights under clause 13.8 been abandoned. Fifthly, the defenders did not specify when
the pursuers abandoned permanently any rights.
The result was that the averments of waiver were irrelevant.
[17] On
the question of waiver, counsel for the defenders submitted that the principle
of waiver can operate to prevent a defence from being stated; it is not confined
to the waiver of an affirmative right.
That was the position in the present case. The pursuers sought to invoke clause 13.8, in
particular clause 13.8.5. Under clause
13.8, if the defenders were to have an entitlement to an extension of time,
they had to satisfy the contractual parameters set out in the clause. The right that was waived by the pursuers was
the right to due fulfilment of those contractual parameters. That was what the defenders had averred in
the passage summarized at paragraphs [12] and [13] above. The import of those averments was that the
defenders and the architect had gone through the clause 25 procedures in
detail, without any attempt by the pursuers or the architect to invoke clause
13.8.5. That meant that the inference
could legitimately be drawn from the averments that the parties conducted
themselves under reference to clause 25 only, with any entitlement under clause
13.8 being waived. This result was in
accordance with the decision of Lord Eassie in E & J Glasgow Ltd. v UGC
Estates Ltd, supra.
[18] On
the question of acquiescence, counsel for the defenders submitted that the
defenders' averments were capable of supporting an inference of acquiescence by
the pursuers. In effect, what was said
was that the pursuers had acquiesced in the defenders' presenting claims under
clause 25 without reference to the procedures set out in clause 13.8. In relation to general personal bar, counsel
for the defenders submitted that his averments were once again sufficient. He referred to the decision of the Second
Division in City Inn Ltd. v Shepherd
Construction Ltd., supra, at paragraph [24], where the Lord Justice Clerk
stated, in relation to clause 13.8, that it "merely provides the
contractor with an option to take certain action if he seeks the protection of
an extension of time in the circumstances in which the clause
applies". According to the
defenders' averments, the pursuers had acted from the start of the project in
such a way as to justify the defenders in believing that extensions of time
would be dealt with on the basis of clause 25 only, and that the defenders did
not require to invoke the protection accorded by clause 13.8. Reference was made to Gatty v Maclaine, 1921 SC
(HL) 1. Counsel further submitted that it could not be said that the defenders'
averments on acquiescence and personal bar were bound to fail; consequently
they should not be refused probation at this stage.
[19]
In my opinion the defenders' averments founded on waiver, acquiescence and
personal bar should be remitted to probation in their entirety. I will deal first with waiver. Waiver has been described as the abandonment
or giving up of a right: Armia Ltd. v Daejan Developments Ltd, supra, at 1979
SC (HL) 69 per Lord Fraser of Tullybelton and 72 per Lord Keith of Kinkel. The
pursuers' primary argument focused on the word "right"; only a legal
right could be waived, and clause 13.8 did not confer any such right on the
pursuers. On that basis, the precise
characterization of the entitlement that is conferred on the employer by clause
13.8.5 is of importance. In my view that
entitlement should properly be characterized as an immunity; if the contractor
fails to comply with clause 13.8.1, and the architect has not dispensed with
compliance under clause 13.8.4, the employer is immune from any claim by the
contractor for an extension of time.
Correspondingly, the contractor is disabled from making any such
claim. (In characterizing the employer's
entitlement and contractor's disability in this way, I rely on the well-known
analysis of legal rights by W.N. Hohfeld in Fundamental Legal Conceptions as
Applied in Judicial Reasoning (New Haven, 1923)). The critical question is accordingly whether
an immunity of this nature can be the subject of waiver. In my opinion it can. The term "right" is commonly,
albeit loosely, used to describe a range of legal entitlements. The basic meaning is the claim right (once
again Hohfeld's terminology), or right having a correlative obligation, but
that is merely one of such entitlements. An immunity, or freedom from a power
vested in another person, is another. I
can see no reason for limiting the doctrine of waiver to the claim right with a
corresponding obligation. In my opinion
it makes perfectly good sense to talk about the abandonment of an
immunity. An immunity is a right to
prevent the exercise of a legal power (in the present case, the power to claim
an extension of time if certain conditions are fulfilled). If the person having the immunity abandons
it, either expressly or impliedly, the result is that the power may be
exercised. I consider that that falls
squarely within the concept of waiver as described in Armia. Indeed, that is
recognized in the decision of Lord Eassie in E & J Glasgow Ltd. v UGC Estates Ltd., supra. The question that arose in that case related
to a clause in a contract to lease property that was in the process of
development. That clause permitted the
prospective tenant to request variations or amendments to the development, but
certain requirements had to be fulfilled before such a request could be
made. The prospective tenant averred
that the developer had, by its actings, abandoned the right to insist upon
strict compliance with those requirements by the prospective tenant. Lord Eassie refused to hold those averments
irrelevant. He stated (at paragraph
[33]):
"However,
while it is of course the case that in his speech in Armia Lord Keith described the doctrine of waiver as connoting the
abandonment of a right, I am not persuaded by the principal proposition for the
[developer] that waiver cannot be deployed so as to cause something which does
not come within the terms of a contractual provision to be treated as if it
did. In a contractual context, waiver of
a contractual term may necessarily imply that something which does not satisfy
all the contractual provisions is yet to be treated as being within those
provisions because the party having an interest to insist on full satisfaction
has either expressly, or by implication arising from the factual circumstances,
waived his right to insist on one or more of the contractual conditions being
duly fulfilled. In ordinary usage, waiving
a contractual term is indeed to say that one is not insisting on one's right to
require due observance of the term.... [T]he authorities illustrate that a
contractual term which is definitional of a contractual entitlement may be
waived".
Two cases, Donnison v Employers Accident
and Livestock Insurance Company Ltd., 1897, 24 R 681, and Minevco Ltd. v Barrett (Southern) Ltd.,
unreported, 16 March 2000, were cited in support. I respectfully agree with Lord Eassie's
analysis, which amounts to holding that legal entitlements in the widest sense
can be the subjects of waiver.
[20] That
is in my opinion sufficient to reject the pursuers' argument. The defenders' averments amount to an
assertion that the pursuers impliedly abandoned their entitlement to insist
that the defenders go through the procedures set out in clause 13.8.1 before
any claim for an extension of time could be made. That entitlement is properly characterized as
an immunity, and an immunity is one of the categories of "right", in the
broadest sense, that can be the subject of waiver.
[21]
In the course of his submissions counsel for the pursuers provided an analysis
of clause 13.8.1. He commented in
particular that the clause did not give rise to any obligation on the part of
the defenders, but should be characterized as a provision dealing with the allocation
of the risk that an AI would cause delay and extra expense. No doubt the application of clause 13.8 has
an effect on the allocation of the risk in question. Nevertheless, neither the language of the
clause nor its underlying conceptual structure says anything about the
allocation of risk. The clause is rather
framed in terms of powers and immunities.
Clause 13.8.1 confers power on the contractor, if he wishes to seek the
protection of an extension of time in the circumstances to which the clause
applies, to submit certain estimates to the architect. That is subject to
clause 13.8.4, which confers power on the architect to dispense with the
requirements of clause 13.8.1. If the
contractor does not make use of the power in clause 13.8.1, and the architect
does not dispense with the requirements of that clause under clause 13.8.4,
clause 13.8.5 confers on the employer an immunity against any claim for an
extension of time. All of those
provisions are framed in typical legal language applicable to powers,
immunities and the like. There is no
reference to "allocation of risk", or anything of that nature. This is hardly surprising. The law is normally structured in terms of
"rights" (using that expression in the widest sense) and correlative
duties or liabilities. It is not
structured in terms of the allocation of risk, which is an essentially economic
or commercial concept. For this reason I
do not agree with the attempt to analyze the clause in terms of the allocation
of risk.
[22] A
further argument for the pursuers was that the circumstances averred by the
defenders were not inconsistent with the retention of the immunity in clause
13.8. In Evans v Argus Healthcare (Glenesk) Ltd. supra, Lord Macfadyen stated (at paragraph [11]):
"[C]ircumstances
which are also consistent with retention of the right in question will not
support an inference that the right has been abandoned".
The defenders averred that the
architect had received notices under clause 25 and had dealt with them under
that clause, but that was consistent with retention of the immunity; clause
13.8 was separate from clause 25, and operating clause 25 did not give rise to
any inference about the pursuers' attitude to clause 13.8. Thus the architect, faced with a claim for
extension of time, might form the view that no relevant event was disclosed in
terms of clause 25. In such a case he
could reject the claim on that ground without any consideration of clause
13.8. If he did so that was consistent
with the pursuers' retaining the right to insist on the application of clause
13.8 in an appropriate case.
[23] In
my opinion there might be considerable force in an argument of this
nature. That is particularly so if it
appeared that applications for extension of time were simply rejected on
grounds arising under clause 25, without any further discussion of the claims
or requests for further particulars. If, however, the architect entered into
discussion of the merits of the claims, that takes some force out of the
argument. In such a case the clause 13.8
point would be a complete answer to the pursuers' claim, and failing to invoke
it at the outset might be taken to suggest that clause 13.8 was being
waived. In the present case the
pursuers's averments suggest that the successive architects did enter into some
discussion of the merits of the applications for extension of time. Thus in relation to AI no 5, dated 17 August
1998, the defenders aver that when they applied for an extension of time the
original architect, RMJM, asked for further particulars in support of the
application. It is further averred that,
once Keppie had replaced RMJM as architect, they proceeded to deal with the
defenders' application in terms of clause 25.
Reference is made to certain correspondence between the defenders and
Keppie. On the basis of that
correspondence, it does appear that Keppie may have entered into detailed
discussion of the claim for an extension of time in terms of clause 25,
including requests for further particulars.
No such detail is given in relation to later requests for an extension
of time, but the discussions regarding AI no 5 appear to have been the first
occasion when an extension was applied for, and consequently the architect's
conduct in relation to that instruction may be of particular significance. In any event, without examining that
correspondence in detail, I do not think that it is possible to hold that the
other applications for an extension of time were simply rejected on clause 25
grounds. At present I am concerned with
the relevancy of the defenders' averments, and on that basis I am of opinion
that I cannot sustain the pursuers' argument at this stage. At proof the
detailed terms of the correspondence can be considered, and in the light of
that it will be possible to reach a considered view of the architect's conduct.
[24] Counsel
for the pursuers also argued that the defenders did not specify when the
pursuers abandoned permanently any rights that they had under clause
13.8.5. In my opinion it is not
necessary to specify precisely when a right is said to have been
abandoned. In perhaps the majority of
cases where implied waiver is claimed, the actings that are said to give rise
to abandonment of the right in question are likely to have taken place over a
period. In such a case all that matters
is that at the end of the series of actings the inference can be drawn that the
right has been abandoned. No doubt that
involves an element of vagueness, but the law can readily tolerate that degree
of imprecision; the critical question is whether waiver can be inferred by the
time when the right said to have been waived has been invoked. Where a claim for an extension under clause
25 is dealt with under that clause without invoking the qualifications in
clause 13.8, the material time would in my opinion be when clause 13.8 is
subsequently invoked by the pursuers.
The defenders' averments, if established, appear to point to abandonment
by that time. Counsel for the pursuers
also placed some stress on the proposition that waiver involves the permanent
abandonment of a right. That is
undoubtedly correct. Nevertheless, there
is an ambiguity in the notion of permanent abandonment in a case such as the
present. The immunity in clause 13.8.5
may be abandoned permanently in relation to one specific application for an extension
of time, or it may be abandoned generally on a permanent basis. The defenders' averments contain elements of
both of these; indeed, specific abandonment in relation to particular
applications for an extension is relied on as one of the factors pointing
towards general abandonment. At this
stage of relevancy I do not think that it is necessary, or indeed possible, to
separate out the different ways in which waiver could occur, either
specifically or generally. Instead, the
whole case of waiver must proceed to proof before answer.
[25] Before
leading the topic of waiver, I should mention clause 13.8.4, which confers on
the architect and express power to dispense with the contractor's obligation
under clause 13.8.1. That is a form of
waiver that is specifically contemplated by the parties' contract. The defenders do not aver that that power was
ever used. Nevertheless, I do not think
that the existence of an express power to dispense with contractual
requirements has the effect of excluding waiver at common law, if the necessary
conditions are satisfied. The power in
clause 13.8.4 is conferred on the employer's representative, the architect, and
it seems likely that it will be exercised in the interests of the employer,
where dispensing with the requirements of clause 13.8.1 is thought desirable in
the interests of the proper progress of the works. Waiver at common law, by contrast, may
operate to protect the interests of either party. The inference of waiver may be drawn from
circumstances that might not prompt the architect to consider the application
of clause 13.8.4. For these reasons I
think that the two possibilities, waiver at common law and the dispensing power
in clause 13.8.4, are conceptually quite distinct, and neither has any necessary
bearing on the other. The existence of
the contractual power might possibly have a bearing on the inferences to be
drawn from the architect's conduct, but that is an issue that must be reserved
for proof.
[26] Counsel
for the pursuers also challenged the relevancy of the defenders' averments
relating to acquiescence and personal bar.
I am of opinion that these averments too must be remitted to
probation. Counsel submitted in this
connection that clause 13.8 did not give rise to any obligation on the part of
the defenders. That is correct. The clause does, however, create a power in
the defenders to qualify for an extension of time by performing the acts set
out in clause 13.8.1, and if that power is not exercised clause 13.8.5 confers
on the pursuers an immunity against any such claim for an extension. In my opinion it is possible to apply the
principle of acquiescence to such a structure.
The defenders' case is, in essence, that they made claims for extension
of time without going through the procedures in clause 13.8.1, and the
pursuers, through their agent, the architect, did not seek to invoke the
immunity conferred by clause 13.8.5.
That, it is said, amounts to acquiescence in the defenders' making claims
for an extension of time without going through the contractual mechanism in
clause 13.8. In my opinion it is not
possible to hold that those averments cannot give rise to acquiescence.
[27] In
relation to acquiescence, counsel for the pursuers further founded on certain
parts of the decision in William Grant
& Sons Ltd. v Glen Catrine Bonded
Warehouse Ltd., supra. He relied
first on a passage that occurs at paragraph [48] of the Lord President's
opinion:
"While
acquiescence may indeed be capable of barring action in the case of future wrongs,
it will have that effect only in those rare cases where it can be inferred that
the pursuer intended to consent not only to wrongs which had occurred without
objection, but also to all similar wrongs, whenever they might occur".
This passage is obviously concerned
with the question of whether acquiescence extends not only to the immediate act
that is acquiesced in but also to similar acts that may take place in
future. It assumes that acquiescence is
effective in relation to the immediate act.
In the present case, the defenders rely to some extent on the pursuers'
acquiescence in specific applications for extension of time that were made
without using the procedures in clause 13.8.1.
To that extent, the passage that I have quoted is not relevant. The defenders also rely, however, on
acquiescence as having a future effect; they say, in summary, that the
architect did not invoke the immunity conferred by clause 13.8.5 on a number of
occasions, and as a result of that the inference should be drawn that the
pursuers acquiesced in claims for extension of time they made in future without
going through the clause 13.8.1 procedure.
In my opinion it is not possible at this stage to hold that that case is
irrelevant. It is clear from the passage
that I have quoted that acquiescence is capable of having future effect, even
though such instances may be rare. If a
party to a contract acquiesces in a departure from contractual procedures on a
sufficient number of occasions, it may be possible to draw the inference that
he acquiesces in the departure from those procedures on future occasions. That is essentially a question of fact, and
is one that must I think be reserved for proof.
[28] A
second passage in William Grant &
Sons Ltd. v Glen Catrine Bonded
Warehouse Ltd., supra, was founded on by counsel for the pursuers. At paragraph [49] of his opinion the Lord
President stated
"I should add
that the defenders' plea of acquiescence is based on an inference which they
seek to draw from the pursuers' silence or failure to object. Inferences of that kind are legitimate only
where a party concerned is under a legal duty to speak or object".
Counsel submitted that in the present
case there was no duty on the pursuers, or the architect, to speak or object
when the defenders considered claims for an extension of time under clause 25
without going through the clause 13.8.1 procedure. In this connection, it is important in my
opinion to consider the context of the passage quoted above.
William Grant & Sons Ltd. v
Glen Catrine Bonded Warehouse Ltd., supra, involved an allegation that the
defenders had passed off their goods as the pursuers'. The defenders countered by alleging that the
pursuers had acquiesced in their using the pursuers' name on their goods. It was that contention that was rejected on
the ground that there was no duty to speak or object. It is clear, however, that the defenders'
activities in producing and marketing their goods proceeded wholly without
reference to the pursuers. It is in that
context that the Lord President's remarks must be read. In the present case, by contrast, the
pursuers and the defenders were in a continuing contractual relationship. In that situation, if one party to the
contract makes claims without going through contractual procedures, and the
other party deals with those claims without objection, I think it clear that
acquiescence is capable of operating. It
could be said that, standing the continuing contractual relationship, there is a
duty to speak or object. Alternatively,
it might be said that the absence of a duty to speak or object is simply
irrelevant where the parties have a continuing consensual legal
relationship. On either basis, I do not
think that the passage quoted can be determinative of the present case.
[29] In
relation to general personal bar, counsel for the pursuers argued that the
defenders' case was based on the proposition that they had failed in the
obligations incumbent upon them under clause 13.8. They had no such obligations, and
consequently this part of the case was irrelevant. It is clear that this part of the argument
mirrored the argument on waiver. In my
opinion it should be rejected at this stage, for essentially the same reasons
as the argument on waiver. The defenders
found not on an obligation to use the procedures in clause 13.8.1 but on a
power to do so. They assert, as I
understand their averments, that the pursuers are personally barred from
relying on the immunity conferred by clause 13.8.5 because of their agent's
failure to invoke that immunity at an earlier stage when claims for an
extension of time were first made. I do
not think that such a case can be rejected as a matter of relevancy.
Status of the hybrid piling solution and any consequential extension of
time
[30] In
their counterclaim the defenders aver that they encountered difficulties in
installing the piling system instructed by the architect, but that the
architect failed to instruct an alternative, leaving it to the defenders and
their subcontractors to do so. The
defenders ultimately adopted a hybrid piling solution. They now claim that the architect should have
instructed a variation, and that they are therefore entitled to an extension of
time for delays that arose out of the hybrid piling works. The relevant averments
are summarized at paragraph [7] above.
[31]
In relation to these averments, counsel for the defenders submitted that the
piling works were performance specified work in terms of the parties'
contract. As a result, the defenders
were obliged to provide piles to satisfy the structural arrangement and
loadings specified by the architect, but the choice of pile type, pile design
and method of installation was left to the defenders. It followed that the use of a hybrid piling
solution was a matter for the defenders to decide, and was not a matter in
respect of which the architect was obliged to issue an instruction. All that the architect required to do in
terms of the contract was to comment on any detailed proposals in relation to
pile design produced by the defenders.
In these circumstances counsel argued that the hybrid piling solution
did not constitute a variation to the works.
As a result the pursuers' averments were irrelevant. As an alternative, counsel submitted that the
defenders should be taken to have treated the architect's comments on their
proposed hybrid piling solution as constituting an instruction to vary the
works and progress them in accordance with that solution. In that event, if they were to claim an
extension of time the defenders required to comply with clause 13.8.1 of the
contract. They did not, however, make
any averments to that effect.
[32] Counsel
for the defenders drew attention to the specification that had been attached to
architect's instruction no 5, dealing with the piling works. This provided (at paragraph 0501) that "Permanent
casings shall be required for those piles where instability may occur due to
inadequate lateral support from the ground or the effect of groundwater". That specification, he submitted, had the
force of an architect's instruction.
Moreover, the accompanying drawing (no 1056.10 (16) 001), dealing with
the piles and pile layout, was described as an "instruction". In that drawing considerable specification
was provided, covering the concrete, its reinforcement and the required loading
capacity. What the defenders averred was
that piling in accordance with those instructions had not been successful, and
the architect had agreed that it was not possible but had failed to instruct an
alternative. The defenders sought to
have the court remedy that under clause 41C.2 of the JCT form. Their case was based on the particular
circumstances averred, where the architect had, in architect's instruction no
5, prescribed what was to be done when ground instability was encountered but
subsequently accepted that its solution was unworkable. In that event, regardless of whether the
piling was performance specified work or not, the architect had taken it upon
itself to prescribe by means of an architect's instruction what the contractor
was required to do in a particular situation.
Evidence might be required on this matter, however, in order to
determine whether the issuing of architect's instruction no 5 should be
characterized as design work carried out by the architect. In that event, clause 2.4.5 of the particular
conditions applicable to the parties' contract could be relevant; it provided
that the contractor should not be responsible for design work which had been
prepared by the employer's professional consultants. In relation to the alternative argument
presented by counsel for the pursuers, counsel for the defenders submitted that
his pleadings were based on the proposition that the architect did not issue
any instruction in relation to the hybrid piling solution. Consequently the hypothesis on which the
pursuers' alternative argument proceeded, namely that the architect's comments
should be treated as an instruction, was incorrect.
[33] The
piling works are identified as performance specified work in the relevant
appendix to the parties' contract.
Performance specified work is dealt with by clause 42 of the JCT
standard form of contract. The
expression refers to work identified as such for which certain requirements
have been predetermined and are shown on the contract drawings. The performance required by the employer for
such work must be stated in the contract bills.
Under clause 42.2, before carrying out any performance specified work,
the contractor is obliged to provide the architect with a document, known as
the "contractor's statement", setting out how the contractor proposes
to execute the performance specified work.
The contractor is obliged to carry out such work in accordance with that
statement. Clause 42.11 provides that
the architect may issue instructions under clause 13.2 requiring a variation to
performance specified work. Clause 42.14
states that the architect shall, within a reasonable time before the contractor
intends to carry out the performance specified work, issue any instructions
necessary for the integration of such work with the design of the general
contract works. The contractor is
obliged to comply with any such instruction.
In addition to the provisions of the JCT form the parties agreed certain
additional contractual provisions. One
of these is significant for present purposes.
Clause 2.4.5 of the additional conditions provides that the contractor
will not be responsible for any design work which has been or will be prepared
by the professional consultants appointed by the employer from time to time in
connection with the works.
[34] In
my opinion the defenders' averments relating to the hybrid piling solution and
the consequential claim for extension of time should be remitted to proof
before answer; I do not think that they can be held irrelevant at this
stage. It is true, as counsel for the
pursuers submitted, that normally the manner in which performance specified
work is carried out is a matter for the contractor; that is clear from the
general provisions of clause 42 of the JCT form. There may be exceptions to this general rule,
however. Clause 42.11 permits the
architect to issue instructions under clause 13.2 to require a variation to
performance specified work. That is
hardly surprising, because the whole project must obviously remain under the
control of the architect, and if the architect thinks that there is good reason
to vary any part of the works he should be free to do so. If the architect does issue an instruction
under clause 42.11, that inevitably involves an element of design of his part,
although obviously the element of design may be greater or lesser in its
scope. In that event, clause 2.4.5 of
the parties' additional conditions excludes responsibility on part of the
contractor for any design work that has been carried out by the architect. Once again, that is hardly a surprising
provision.
[35] The
defenders' averments relating to the hybrid piling solution must be considered
against that contractual background.
What they aver is that architect's instruction no 5 amounted to a
variation of the piling works. In the
course of the debate reference was made to the drawing (no 1056.10 (16) 001)
and specification that accompanied the instruction. It is clear that these are detailed
documents, and at this stage I do not think it possible to hold that they could
not amount to a variation. I am likewise
of opinion that it cannot be held as a matter of relevancy that architect's
instruction no 5 and the accompanying drawing and specification did not involve
design work on the part of the architect; that too is a matter that must be
decided at proof. In view of the terms
of clause 42.11, if these documents do amount to a variation, it is immaterial
that it relates to performance specified work; it still has the contractual
force of a variation, and to the extent that it represents design work by the
architect clause 2.4.5 excludes the contractor's responsibility. Against that background, the defenders aver
that the solution put forward in the variation proved unworkable in practice,
in that permanent casings could not be used.
They aver that the architect agreed with that conclusion, but failed to
instruct an alternative, leaving it to the defenders and their subcontractors
to do so. The defenders then put forward
the hybrid piling solution but, it is averred, the architect stated that it had
no objection but had no authority to issue any instructions. If architect's instruction no 5 and its accompanying
documents did amount to a variation involving design work by the architect, it
is in my opinion arguable that the architect had to take responsibility for
dealing with the consequences if that instruction proved unworkable. At the very least the instruction would
require to be cancelled (although that might have happened impliedly in the
present case). It is arguable, however,
that more is required, and that the architect must devise an alternative
solution; the fact that a variation was issued might be said to indicate that
the architect wished to qualify the contractor's own proposed solution. All of these, however, are matters that
should properly be the subject of proof before answer. At that stage it can be discovered whether
architect's instruction no 5 amounted to a variation involving design
work. If it did, it can then be decided
whether the architect thereby became responsible for issuing an alternative
instruction at the stage when its first proposals were discovered to be
unworkable.
[36] The
pursuers' alternative argument was that the defenders had made a claim for
extension of time without going through the procedures in clause 13.8.1. On this matter I am of opinion that the
submission by counsel for the defenders was correct. The defenders' case is based on the proposition
that the architect failed to issue an instruction. They make the following particular averments:
"At a
meeting on 9 November 1998, the Architect agreed that permanent
casings could not be used, but failed to issue an alternative.... On 16
November 1998,
the Architect confirmed that it had no objection to the use of that solution,
but when the defenders sought an instruction for its use on 17
November 1998,
the Architect responded on 18 November 1998 stating that it had no authority to
issue such an instruction".
Moreover, the defenders go on to aver
that they, together with their piling subcontractors, devised an alternative
solution. In these circumstances, it is
apparent that the defenders are alleging that neither an instruction nor any
"other item which, in the opinion of the Contractor, constitutes an
instruction" (the wording of clause 13.8.1) was issued. In those circumstances their case is that the
necessary precondition of clause 13.8.1 was not satisfied, and that clause
never came into operation. The averments
in question must obviously be the subject of proof, but I am of opinion that at
this stage I cannot hold them irrelevant.
Averments of breach of contract
[37] In
their defences to the principal action, the defenders make certain further
averments that are based on the proposition that the pursuers were in breach of
contract by reason of the architect's failure to issue an instruction relating
to the hybrid piling solution. In answer
7 they make the following averment:
"Explained further
and averred esto the defenders are not entitled under the contract to said
extensions of time (which is denied) then the defenders having been prevented
from completing the works to time by breach of contract of the pursuers, the
time for completion under the contract is rendered at large and the pursuers
are not entitled to liquidate and ascertained damages".
The pleadings then make reference to
the counterclaim. The defenders further
aver, in answer 7.3, that it would have been impossible for them to comply
fully with the provisions of clause 13.8.1, and to meet the contractual
Completion Date; the provisions of clause 13.8.1 inevitably involved delay for
which there was no provision for extension of time. In those circumstances, it is averred, either
the pursuers are disabled from relying upon clause 13.8 to defeat the
defenders' entitlement to an extension of time or the time for completion under
the contract is rendered at large, with the consequence that the pursuers are
not entitled to liquidate and ascertained damages. Those averments are expanded upon in the
counterclaim.
[38]
In the counterclaim the defenders seek a number of declarators. These are expressed as follows:
(a) For declarator that the hybrid piling
solution constructed by the defenders constituted a Variation to the Works.
(b) For declarator that (i) the Architect
(RMJM Scotland Ltd) decided not to issue an instruction requiring the hybrid
piling solution as a Variation, and (ii) the said decision was incorrect.
(c) For declarator that the defenders are
entitled to an instruction requiring the hybrid piling solution as a Variation
and an extension of time in so far as compliance therewith caused delay in
completion of the Works.
(d) Separatim, esto in the event that the
defenders are not entitled to an extension of time as concluded for at 1(c),
for declarator that the Architect's failure to issue an instruction requiring
the said hybrid piling solution as Variation was a breach of contract, with the
result that (i) time for completion of the Works was rendered at large, and
(ii) the defenders have no liability to the pursuers in respect of liquidated
and ascertained damages under the Contract.
The essential averments in the
counterclaim are as follows. On 18
August 1998
the architect issued AI no 5, which instructed a combination of vertical piles
and long raking piles, with permanent casings where instability might
occur. When the defenders attempted to
install vertical piles at the eastern end of the site they were unsuccessful
owing to ground instability. At a
meeting on 9 November 1998 the architect agreed that permanent
casings could not be used but failed to instruct an alternative. The defenders and their subcontractors were
left to devise an alternative, and they proposed the hybrid piling solution
mentioned above. On 16
November 1998
the architect confirmed that it had no objection to the use of that solution,
but when the defenders sought an instruction for its use on 17
November 1998
the architect responded on 18 November to state that it had no authority to
issue such an instruction. As the piling
works were critical to completion of the Works, the defenders had no option but
to progress them in accordance with the hybrid piling solution in the absence
of an instruction. The additional work
in carrying out the hybrid piling solution delayed completion of the Works.
[39] The
defenders then make the following averments:
"It was
reasonably necessary for the Architect to instruct the hybrid piling solution
in order to enable the Contractor to carry out and complete the Works in
accordance with the Contract. The
Architect was obliged to do so in accordance with clause 5.4 of the
Contract. If doing so required a
Variation to the Works then the Architect should have instructed a variation in
accordance with clause 13.2 of the Contract.
The Architect refused to do so".
Thereafter the defenders aver that
the architect erred in deciding not to issue an instruction requiring a
variation. They aver that they are
entitled to an extension of time in terms of clause 25.4.5.1 because they have
been delayed in completion of the Works as a result of carrying out the work
that should have been the subject of that instruction. A declarator to that effect is sought in the
counterclaim, that being declarator (c) in paragraph [38] above.
[40] In
the alternative, the defenders aver that the architect acted as the pursuers'
agent in this regard, and that the pursuers are accordingly in breach of
contract on account of the architect's failure to issue the necessary
instruction. Reliance is placed on
clauses 5.4 and 13.2 of the parties' contract.
The defenders aver that, in the event that they are not entitled to an
extension of time because of that breach of contract, time for completion was
rendered at large; consequently the defenders have no liability to pay
liquidated and ascertained damages under the contract. A declarator to that effect is also sought,
in the form of declarator (d) in paragraph [38] above.
[41] A
further alternative case is then set out.
This may be summarized as follows.
Esto the architect did not apply his mind to clause 13.8, the pursuers
were thereby rendered in breach of contract.
In terms of clause 13.8.4, the architect may, before or after the issue
of an instruction, dispense with the contractor's obligations under clause
13.8.1. In order to be able to exercise
the discretion contemplated by clause 13.8.4, the architect requires to apply
his mind to clause 13.8, and in particular as to whether or not to dispense
with the contractor's obligation under clause 13.8 in the circumstances of a
particular instruction. In these matters
the architect was acting as the agent of the pursuers. Consequently, in the event that the architect
failed to apply his mind to clause 13.8, and in particular to the issue of
dispensation under clause 13.8.4, the pursuers were thereby rendered in breach
of contract. In these circumstances, it
is said, clause 13.8 has no application.
[42] Counsel
for the pursuers attacked these averments on a number of grounds. In the first place, he attacked the
defenders' averments of breach of contract in the defences, on the basis that
no specification was given of the relevant obligations, how they were breached,
how this made it impossible for the defenders to comply with clause 13.8.1, and
how this would have made it impossible to meet the completion date. These
criticisms were to some extent developed in relation to the counterclaim. In the second place, counsel for the pursuers
attacked the defenders' reliance in the counterclaim on clauses 5.4 and 13.2 of
the JCT conditions. Neither of these, it
was said, placed any contractual obligation upon the pursuers or the architect
to instruct variations. On that basis it
was said that the averments founded on those clauses were irrelevant and should
not be remitted to probation. In the
third place, counsel for the pursuers attacked the defenders' alternative case
as set out in paragraph [40] above.
Counsel submitted that clause 13.8 imposed no contractual obligation
upon the architect to apply his mind to the clause unless an application was
made by the defenders under clause 13.8.1.
The defenders did not aver that any such application was made. In addition, clause 13.8.4 did not impose any
obligation on the architect. It other
conferred a discretion upon him which he might or might not exercise. On that basis it was said that the relevant
averments were irrelevant and should not be remitted to probation. Conclusion 1(d), which relied on those
averments, should accordingly be repelled.
I will first of all consider the second of these arguments, which I
think is the most fundamental in nature.
Thereafter I will deal with the first and third arguments.
[43] The
second argument was an attack on the defenders' reliance in the counterclaim on
clauses 5.4 and 13.2 of the JCT conditions.
In this part of the defenders' case the primary obligation relied upon
is that mentioned in paragraph [39] above.
The defenders' contention is that clause 5.4 imposed an obligation on
the architect to give an instruction relating to the hybrid piling
solution. A secondary obligation is also
averred: if the instruction required a variation that should also have been
instructed in accordance with clause 13.2.
Clause 5.4 is in the following terms:
"As and
when from time to time may be necessary the Architect without charge to the
Contractor shall provide him with 2 copies of such further drawings or details
as are reasonably necessary either to explain and amplify the Contract Drawings
or to enable the Contractor to carry out and complete the Works in accordance
with the Conditions".
In my opinion that clause, which uses
the verb "shall", imposes an obligation. That obligation is obviously fairly general
in nature. It requires the provision of
such drawings as are "reasonably necessary" to proceed with and
complete the Works. Consequently the
question whether it applies in any particular case must depend on the facts and
circumstances of that case.
Nevertheless, I do not think that this form of vagueness detracts from
the obligatory nature of the clause; ultimately the court must decide what is
"reasonably necessary".
Moreover, the obligation does appear fundamental to the contractual
scheme; it is the primary obligation on the architect to provide any necessary
information that goes beyond the original contract drawings. In London
Borough of Merton v Stanley Hugh
Leach Ltd., 1985, 32 BLR 51, Vinelott J commented on the equivalent of
clause 5.4, clause 3(4), in the 1963 edition of the JCT Contract; the two
clauses were in almost identical terms.
Vinelott J stated (at 82)
"Clause
3(4) imposes on the architect an obligation to furnish the contractor with
drawings and details as and when necessary".
That is in accordance with my own
view of the clause.
[44] The
piling work was performance specified work governed by clause 42, but nothing
in the latter clause excludes the application of clause 5.4. Indeed, clause 42 specifically contemplates
that instructions may be given by the architect in respect of such work. Thus clause 42.1.3 contemplates that
requirements for the performance specified work will be predetermined and shown
on the contract drawings. Clause 42.11
authorizes the architect to issue instructions under clause 13.2 requiring a
variation to performance specified work.
Clause 42.14 provides that the architect should give any instructions
necessary for the integration of the performance specified work with the design
of the works. These provisions are in my
opinion a clear indication that the architect may be obliged to provide
drawings relating to aspects of performance specified work, and that clause 5.4
may thus operate.
[45] Clause
13.2, unlike clause 5.4, is permissive rather than obligatory in nature; it provides
that the architect "may" issue instructions requiring a variation
subject to the right of the contractor to make reasonable objection. Nevertheless, the defenders' reference to
clause 13.2 (quoted at paragraph [38] above) does not, I think, suggest that
clause 13.2 is the source of any obligation.
It proceeds rather on the premise that the obligation is found in clause
5.4, and the power in clause 13.2 is one that the architect should use if that
proves necessary in the course of fulfilling his duties under clause 5.4. Overall, therefore, I am of opinion that the
defenders rely on obligations that may be incumbent on the architect, in
appropriate circumstances. Whether those
obligations to apply in the present case is, of course, a matter that must
await proof.
[46] Counsel
for the pursuers' first argument was an attack on the specification, and to
some extent the relevancy, of the defenders' averments of breach of contract as
contained in the defences and, to some extent, the counterclaim. In my opinion this argument is largely
justified. In answer 7 of the defences
it is averred, in a passage quoted at paragraph [37] above, that the defenders
were prevented from completing the works to time by the pursuers' breach of
contract, with the consequence that time for completion was rendered at
large. No specification is given in
answer 7 of the breach of contract that is referred to. Reference is made to the counterclaim, where
it is averred that the pursuers, through the architect, were in breach of
clause 5.4. No indication is given,
however, as to how the failure to issue an instruction in relation to the
hybrid piling solution prevented the defenders from completing the works
timeously. The adoption of that solution
might have caused delay and hence a failure to complete on time, but in that
event it is the works themselves, rather than the lack of an instruction, that
is the clause. Likewise, the architect's
failure to issue an instruction might have disabled the defenders from making
use of the procedure in clause 13.8.1, but I find it impossible to see how that
can have caused any delay. For these
reasons I am of opinion that the passage quoted in paragraph [36] above is
irrelevant.
[47] The
pursuers also challenge the specification of the averments in answer 7.3 where
the defenders say that, because of the pursuers' or their architect's breach of
express and implied obligations under the contract, it would be impossible for
the defenders to comply fully with the provisions of clause 13.8.1 and to meet
the contractual completion date. In my
opinion the criticism of this part of the defenders' pleadings is also
justified. The obligations in question
are not specified, beyond a reference to the counterclaim. The reference to implied obligations seems to
go beyond the obligation contained in clause 5.4. In my opinion the obligations should be set
out properly in answer 7.3. In any
event, for the reasons stated in the last paragraph, I do not understand how
the failure to issue an instruction under clause 5.4 could itself cause delay;
any delay is likely to have been caused by the additional work that was
required rather than the failure to issue an instruction. Answer 7.3 also seems to suggest that the
failure to issue an instruction prevents the pursuers from relying on clause
13.8 to defeat the defenders' entitlement to an extension of time. In this respect, I do not think that the
answer is clearly expressed. What is
intended may be that, because no instruction was issued, the defenders could
not follow the procedures in clause 13.8, which relate specifically to an
instruction or a document which in the opinion of the contractor constitutes an
instruction. If that is so, however, I
think that it should be more clearly stated.
In addition, in the principal action the defenders have no plea in law
dealing with breach of contract and its consequences. For these reasons I propose to hold that the
whole of the existing answer 7.3 is irrelevant.
It may be that the foregoing criticisms can be cured by amendment, and I
will give the defenders an opportunity, if they wish, to produce a minute of
amendment.
[48] Counsel
for the defenders submitted that the necessary specification in relation to
answer 7, and in particular answer 7.3, was given in the counterclaim. He founded particularly on the averments
summarized in paragraph [38] above.
These are designed to support the claim for an extension of time that is
specified at head (c) of the declaratory conclusion of the counterclaim. In my opinion those averments do set out with
reasonable clarity a case for an extension of time. In particular, the averments specify the
breach of contract that is relied on, namely the failure to issue an
instruction, and if appropriate a variation, in terms of clause 5.4 of the
contract. No doubt there is a dispute as
to whether the architect was justified in not issuing an instruction; that is
an issue that must await proof. The nature
of the obligation asserted by the defenders, however, seems clear. The consequence that is said to follow from
the breach of contract is that the defenders were unable to claim an extension
of time according to the terms of clause 25.4.5.1. The result, it is said, is that they can now claim
to be put in the same position as they would have been in had the instruction been
properly issued. This point could
perhaps be spelled out more clearly in the pleadings, but I think that it is
sufficiently clear to satisfy the test of relevancy so far as the counterclaim
is concerned. In relation to the
principal action, however, for the reasons set out in the last paragraph I am
of opinion that the defenders' pleadings in answer 7.3 are irrelevant, and
are not saved by reference to the counterclaim.
[49] Counsel
for the defenders further submitted that the breach of contract has a further
consequence in relation to the operation of clause 13.8. That clause could not apply in a situation
where no instruction was issued. I can
understand the latter point. According
to its terms clause 13.8.1 applies where any instruction or other item
constituting an instruction will require adjustment to the contract sum or
delay the completion date. It is thus
dependent on the issue of an instruction or equivalent document. If there is no instruction, and in particular
if there is a refusal to issue an instruction, it is difficult to see how the
clause can come into operation. The
difficulty so far as the defenders' pleadings is concerned, however, is that
this link is not spelled out in the counterclaim. It is perhaps hinted at in answer 7.3, where
it is averred that, because of the architect's breach of its obligations,
"it would have impossible for the defenders to fully comply with the
provisions of clause 13.8.1... and to meet the Completion Date". The problem with that averment is that it
appears to suggest that the impossibility of complying with clause 13.8 was
somehow linked with an inability to meet the completion date. I do not understand how that is said to
follow; the architect's breach of its obligations would rather disable the
defenders from making use of the clause 13.8 procedure. In that event, the defenders' remedy would
seem to be a claim that they should be placed in the same position financially
as they would have been in had an instruction been issued; that is the normal
remedy for a breach of contract. That is not spelled out in answer 7.3,
however; nor does it appear in the counterclaim. For this reason I do not think that the
defenders' case in relation to breach of contract and clause 13.8 has been relevantly
averred. As indicated above, I propose
to exclude the averments in answer 7.3 from probation.
[50]
Counsel for the pursuers' third ground of challenge to the damages claim was to
the defenders' alternative case as set out in paragraph [41] above. Counsel submitted that clause 13.8 imposed no
contractual obligation upon the architect to apply his mind to the clause
unless an application was made by the defenders under clause 13.8.1. It rather
conferred a discretion upon him which he might or might not exercise. In any event, the defenders did not aver that
any such application had been made. On
that basis it was said that the averments in question were irrelevant and
should not be remitted to probation.
Conclusion 1(d), which relied on those averments, should accordingly be
repelled. Counsel for the defenders
submitted that there was an obligation on the architect to apply his mind to
the discretion under clause 13.8.4 before issuing any instruction. He drew attention to the fact that clause
13.8.4 allowed the architect to dispense with the obligation under clause
13.8.1 by notice to the contractor either before or after the issue of any
instruction.
[51] In
my opinion the pursuers' argument on this matter is correct. According to its terms, clause 13.8.4 confers
a discretionary power on the architect.
Discretionary powers arise in a wide range of contexts. In some cases the holder of such a power may
be under a duty to exercise it, as may occur with some powers of apportionment
conferred on trustees. In other cases
there is no duty to exercise the power but the holder may be subject to a duty
to consider the exercise of the discretion.
That is true of many trust powers, for example those relating to the
application of income or the advancement of capital; in such cases the trustees
are obliged to keep the application of income under constant review and to
consider from time to time whether it is appropriate to make advances of
capital. In yet other cases the power is purely discretionary, and that is no
general obligation to consider its exercise.
The question as to which of these categories applies to any particular
power must obviously depend upon the context in which the power arises. Clause 13.8.4 is a contractual power, and
must be looked at in the context of the parties' contract, and in particular
clause 13.8 of that contract.
[52] In
my opinion the power in clause 13.8.4 falls into the third of the foregoing
categories; there is no general obligation on the architect to consider whether
or not to exercise it. I reach this
conclusion for two reasons. First,
clause 13.8.4 permits the architect to dispense with certain contractual
requirements, namely those in clause 13.8.1-.3; those requirements apply unless
the power is exercised. It follows that
the requirements of clause 13.8.1-.3 are the norm, and the power in clause
13.8.4 is exceptional in nature. In such
a case I consider that it is unlikely that there will be any continuing duty to
consider whether the power is exercised; the power is to deal with exceptional
circumstances, and it is only if the architect thinks that there are
exceptional circumstances that he is any need to consider the exercise of the
power. Secondly, it appears likely that
the power, which is conferred on the employer's representative, is most likely
to be exercised in the interests of the employer, to ensure the proper progress
of the works. It may be invoked, for
example, if urgent action is required or if it is clear that an instruction is
necessary, regardless of its implications for the progress or costs of the
works. A power of that nature need not
in my view be the subject of constant consideration; it is only when the
architect thinks that the contractual procedures in clause 13.8.1-.3 are
inappropriate that he requires to consider the exercise of the power. It follows that the architect is not required
to address his mind to clause 13.8.4 before issuing any instruction. It is true
that the power in that clause may be exercised before the issue of an
instruction, but in my view that does not alter the fundamental nature of the
power. I will accordingly hold the
defenders' alternative case, based on the architect's failure to apply his mind
to clause 13.8, to be irrelevant, and I will exclude the averments relating to
that argument from probation.
Conclusion
[53] For
the foregoing reasons I will sustain the pursuers' pleas to the relevancy of
the defenders' averments, but only to the extent indicated in paragraphs [46],
[47] and [52] above. I will exclude from
probation the passage in answer 7 quoted in paragraph [37], the whole of answer
7.3, and the passage at the end of statement 3 of the counterclaim dealing with
the architect's failure to apply his mind to clause 13.8. Otherwise I will allow a proof before
answer. I will have the case put out by
order to discuss further procedure, including the possibility of a minute of
amendment by the defenders. A further
issue is whether the scope of any proof should be restricted. In this connection parties may care to
consider whether the next stage in procedure should be a proof before answer
restricted to questions of waiver, acquiescence and personal bar.