BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just ยฃ1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Education 4 Ayrshire Ltd v South Ayrshire Council [2009] ScotCS CSOH_146 (04 November 2009) URL: http://www.bailii.org/scot/cases/ScotCS/2009/2009CSOH146.html Cite as: 2009 GWD 36-609, [2009] CSOH 146, 2010 SLT 253, [2009] ScotCS CSOH_146, [2010] CILL 2814 |
[New search] [Help]
OUTER HOUSE, COURT OF SESSION
[2009] CSOH 146
|
|
CA37/09
|
OPINION OF LORD GLENNIE
in the cause
EDUCATION 4 AYRSHIRE LIMITED
Pursuers;
against
SOUTH AYRSHIRE COUNCIL
Defenders:
ญญญญญญญญญญญญญญญญญ________________
|
Pursuers: Young QC, Smith; MacRoberts
Defenders: Howie QC; Burness LLP
4 November 2009
Introduction - the Project Agreement
[1] By a contract ("the Project Agreement") entered into in December
2006, the pursuers ("the Contractor") agreed to carry out for the defenders
("the Authority") certain works ("the Works"), including the design and
construction of six schools listed in Part 2 of Schedule Part 4 thereof. The
schools included Prestwick Academy. The contract
was part of the South Ayrshire Schools PPP.
The pursuers sub-contracted the entire Works, that part relating to
construction being sub-contracted to Carillion (the "Building Contractor")
[2] In terms of clause 10.1 of the Project Agreement, the pursuers
were required to carry out the Works so that each Phase of a Project Facility
achieved Service Availability on the Target Service Availability Date ("TSAD")
for that Phase. These are all defined terms, but it is not necessary to set
out the definitions for present purposes. Prestwick Academy and the Site thereof was one such Project
Facility. The Works in relation thereto were to be carried out in three
Phases. Clauses 8A.3 and 17 of the Project Agreement contain provisions under
which the pursuers might be entitled to an extension of time, a postponement of
the TSAD and to payment of asbestosis compensation in the event that achieving
the TSAD was postponed as a direct result of the occurrence of a Works
Compensation Event.
The Notice provisions of the contract
[3] The Notice provisions relating to Extensions of Time are set
out in clause 17 of the Project Agreement. This provides as follows:
"17 EXTENSIONS OF TIME
17.1 Notice
If at any time of the Contractor becomes aware that there will be or is likely to be any delay in achieving a Target Service Availability Date or any delay to the Works the Contractor shall as soon as reasonably practicable and in any event within 20 Business Days give notice to the Authority to that effect specifying:
17.1.1 the reason for the delay or likely delay; and
17.1.2 an estimate of the likely effect of the delay in achieving the relevant Target Service Availability Date (taking into account any measures that the Contractor proposes to adopt to mitigate the consequences of the delay in accordance with Clause 17.3 (Duty to Mitigate)).
17.2 Supply of Information
Following service of a notice by the Contractor pursuant to Clause 17.1 (Notice) the Contractor shall promptly supplied to the Authority any further information relating to the delay which:
17.2.1 is received by the Contractor; or
17.2.2 is reasonably requested by the Authority.
17.3 Duty to Mitigate
The Contractor shall take all reasonable steps to mitigate the consequences of any delay to the Construction Programme.
17.4 Time for Completion of the Works
To the extent that (a) a delay in the Construction Programme or anticipated failure to meet a Target Service Availability Date or (b) the Contractor incurring or expecting to incur or losing or expecting to lose any revenue is directly attributable to:
17.4.1 a Works Compensation Event, then the provisions of Clause 17.5 shall apply; or
17.4.2 a Relief Event, then the provisions of Clause 54 (Relief Events) shall apply; or
17.4.3 a Force Majeure Event, then the provisions of Clause 39 (Force Majeure) shall apply.
17.5 Delays due to a Works Compensation Event
17.5.1 If as a direct result of the occurrence of a Works Compensation Event:
17.5.1.1 there is a delay to the Construction Programme or the issue of an Acceptance Certificate at a Project Facility on the relevant Target Service Availability Date or any delay to the Works thereafter; or
17.5.1.2 the Contractor is unable to comply with its obligations under this Agreement; or
17.5 1.3 the Contractor incurs expects to incur costs or losses or expects to lose revenue other than as a result of a Unitary Charge Adjustment pursuant to Part B of Schedule Part 7 (Payment Mechanism),
then, subject to Clause 17.6, the Contractor will be entitled to apply for relief in terms of this Clause 17 from its obligations and/or claim compensation under this Part 3 of this Agreement.
17.6 Procedure for relief
Subject to Clause 17.8, to obtain relief or claim compensation under this Clause 17 the Contractor must:
17.6.1 as soon as practicable, and in any event within 20 Business Days after it becomes aware that the Works Compensation Event has caused or is likely to cause delay, breach of an obligation under this Agreement or the Contractor to incur costs or lose revenue, give to the Authority a notice of its claim for an extension of time to the relevant Target Service Availability Date, payment of compensation and/or relief from its obligations under this Agreement;
17.6.2 within 15 Business Days of receipt by the Authority of the notice referred to in Clause 17.6.1 (or such longer period as the Authority acting reasonably may agree) give full details of the Works Compensation Event and the extension of time and any Estimated Change in Project Costs claimed (including evidence, on an open book basis, of the calculation of any Estimated Change in Project Costs); and
17.6.3 demonstrate to the reasonable satisfaction of the Authority that:
17.6.3.1 the Works Compensation Event was the direct cause of the Estimated Change in Project Costs and/or any delay in the achievement of the relevant Target Service Availability Date and there were no simultaneous occurrences of delay caused by other events which have been included in the calculation of the Estimated Change in Project Costs And the Delay in Achievement of the Target Service Availability Date; and
17.6.3.2 the Estimated Change in Project Costs, time lost and relief from the obligations under this Agreement claimed, could not reasonably be expected to be mitigated or covered by the Contractor acting in accordance with Good Industry Practice.
17.7 Giving of relief
Subject to Clauses 17.7.5 and 17.8, following compliance by the Contractor with the requirements of Clause 17.6, then:
17.7.1 the relevant Target Service Availability Date shall be postponed by such time as shall be reasonable for such a Works Compensation Event, taking into account the likely effect of delay;
17.7.2 in the case of an additional costs being incurred by the Contractor in respect of the events listed in the definition of Works Compensation Event:
17.7.2.1 as a result of Capital Expenditure being incurred by the Contractor; or
17.7.2.2 in relation to a Phase, on or before the Service Availability Date;
the Authority shall compensate the Contractor for the actual Estimated Change in Project Costs as adjusted to reflect the actual costs reasonably incurred within 30 days of its receipt of a written demand by the Contractor supported by all relevant information, provided however that in relation to Type 3 Asbestos the provisions of Clause 8A and Schedule Part 4 Part 3 will apply in relation to the quantum of any claim for compensation in that respect;
17.7.3 ...
17.7.4 the Authority shall give the Contractors such relief from its obligations under this Agreement as is reasonable for such a Works Compensation Event.
17.7.5 ...
17.8 Late provision of information
In the event that information is provided after the specified number of Business Days contained in Clause 17.6, then the Contractor will not be entitled to any extension of time, compensation, or relief from its obligations under this Agreement in respect of the period of time during which the information is delayed."
Clause 17.9 provides for the application of a Dispute Resolution Procedure in the event of parties failing to agree the extent of any compensation, delay or relief. Clause 72.1 deals with the requirements of formality in the giving of notices under the contract. Notices to the Authority have to be sent by first class post, facsimile or by hand, to the Chief Executive at County Buildings, Wellington Square, Ayr.
[4] Works Compensation Event, a term used in particular in clause
17.5, is also a defined term. It covers a wide range of matters. It includes,
for example, a breach by the authority of any of its obligations under the
Agreement. So far as is relevant to this case, it includes "the period of
time required for Type 3 Asbestos Removal Works being longer than the relevant
Type 3 Asbestos Works Period as a result of the nature and/or extent and/or
location of Type 3 Asbestos". There had been asbestos surveys for each of
the schools covered by the Project Agreement. The surveys had revealed areas
of the Site from which asbestos required to be removed and the time (the Asbestos
Works Period) estimated to be required for its removal. Type 3 Asbestos refers
to asbestos discovered in any relevant school to the extent that it exceeds in
nature, extent and/or location the asbestos already revealed by the relevant
survey. A Works Compensation Event relating to asbestos is, in effect, the
discovery that there is more asbestos to remove, or that it will take longer to
remove, than had been expected as a result of the relevant survey. The
Asbestos Works Period for Prestwick Academy was one week.
The issue
[5] The pursuers' case on Record is that there was a delay to the
Works at Prestwick Academy as a direct
result of the discovery of asbestos which was not revealed by the survey. They
conclude (1) for declarator that the Construction Programme, the issue of
Acceptance Certificates and the Works comprising Phases 1, 2 and 3 of the
Prestwick Academy Project Facility have been delayed by a period of 16 weeks
owing to a Works Compensation Event, namely the discovery of Type 3 Asbestos at
Prestwick Academy, (2) for declarator that they are entitled to a postponement
for 16 weeks of the TSAD for Phases 1, 2 and 3 at Prestwick Academy, and (3)
for payment of ฃ815,792.00 plus VAT and interest.
[6] The defenders contend inter alia that the pursuers
cannot claim such postponement or payment because they failed to give the
required notice or notices in terms of clause 17 of the Project Agreement
within the required time or at all. In answer to this, the pursuers aver that
the earliest that they could have become aware that there was likely to be a
delay in achieving the TSAD was when they received a report on 6 April 2007;
and that they gave notice to the defenders in terms of Clause 17 by letter to
their Chief Executive dated 2 May 2007. That is accepted to be a date within
20 Business Days of 6 April
2007. This is the important
communication. The pursuers accept that the other items of correspondence
referred to on Record cannot be relied upon as notices under Clause 17 because
they were variously wrongly directed, communicated in the wrong form and/or
sent out of time.
[7] The case was appointed to debate on the defenders' plea-in-law
to the relevancy of the pursuers' case. They contend, in short, that because
no valid notice was given in terms of clause 17, the pursuers' case in support
of their second and third conclusions must fail and should not be remitted to
probation. This leaves only the first conclusion which, on its own, does not
achieve anything of substance for the pursuers.
The Notice relied upon - the letter of 2 May 2007
[8] The letter of 2 May 2007 is of central importance to the argument and I should
therefore quote it in full. It reads as follows:
"Dear Sir
SOUTH AYRSHIRE SCHOOLS PPP
WORKS COMPENSATION EVENT
ASBESTOS - Prestwick Academy, Building 7
In accordance with Clause 17.1 of the project agreement, we hereby inform you that we anticipate a delay in achieving the Target Service Availability Date in relation to Prestwick Academy. Taking into account the measures we are proposing to adopt to mitigate the delay we estimate that delay will be 19 weeks and is due to the discovery of asbestos in Building 7.
To this end please refer to our previous correspondence of 18 April to Mr Roddy Macdonald and the attached correspondence from the Building Contractor dated the 30/4/07 which provides further details and includes the proposed programme for removal of asbestos.
We will submit our full claim in accordance with clause 17.6 of the project agreement.
By way of background we have held various discussions with the representative from the Health and Safety Executive to ensure all Health and Safety obligations are being met and we have also requested the Employer's Agent to provide a report on the financial effects of the delay.
Please be assured we will continue to work with all parties to ensure every effort is made to mitigate the delay and will keep the relevant people at the council informed as work progresses.
Yours faithfully"
[9] The letter mentions two other items of correspondence to which
it is necessary to refer. The first is an e-mail of 18 April 1007 from David Broad, the General Manager of the
pursuers, to Mr Roddy Macdonald, of the defenders, copied to a number of
others, saying that the pursuers had "been provided with further information on
the implications of the asbestos found during the type 3 survey" and suggesting
a contingency planning meeting. There is nothing of substance in this e-mail
and, lest there be any doubt, it is not in dispute that could not count as a
Notice under clause 17 for any number of reasons - it was sent by e-mail, it
was not sent to the Chief Executive, and it did not, on any view, seek to
invoke any of the provisions of the clause.
[10] The second is a letter from the Building Contractor to the
pursuers dated 30 April 2007 in which, under the heading "South Ayrshire
Schools, Prestwick Academy - Building 7 - Asbestos", the Contractor updates the
pursuers on the delay resulting from the discovery of Type 3 asbestos there and
requests a 19 week extension of time. The letter goes into considerable detail
about the likely effect on the programme. It identifies the delay to
particular areas on the site and concludes:
"The 17 week delay in the Asbestos Removal and Demolition of Building 7 will delay the Service Availability to Phase 1 of Prestwick Academy from 20 June 2008 to 17 October 2008.
The Service Availability to Phase 2 and Phase 3 of Prestwick Academy will also be delayed to 7 August 2009 and 8 January 2010. Please note that due to Christmas 2009, the delay to the Service Availability of Phase 3 will be 19 weeks.
We would therefore request a 19 week extension of time."
The letter goes on to identify the compensation to be claimed. It refers to Clause 8A.3 of the Building Contract (i.e. the sub-contract between the pursuers and the Building Contractors, Carillion) and calculates the compensation as 19 weeks multiplied by the 'A' Rate and the 'B' Rate. These rates are the same as the 'A' and 'B' Rates in the Project Agreement, but, unlike the Building Contract, the Project Agreement also has a 'C' Rate. That part of the letter asks the pursuers to note
"that the above noted compensation excludes any costs for the actual removal of asbestos (Asbestos Expenditure) or any compensation due to E4a (C Rate)";
and ends by referring to the continuing attempts by the Building Contractor to mitigate the delay.
Submissions
[11] In presenting his submissions for the defenders, Mr Howie QC
argued that compliance with the procedural requirements of clause 17 was a
suspensive condition of, or a condition precedent to, the right of the pursuers
to claim payment or an extension of time. It proved unnecessary for him to
develop this argument, however, since Mr Young QC, for the pursuers, intervened
to make it clear that he accepted that compliance with the provisions of clause
17.1 and 17.6 (whether 16.6.1, 17.6.2 or 17.6.3), as the case might be, was a
condition precedent to the relief sought. This concession was, to my mind,
properly made, standing the language of the various constituent parts of the
clause. The only qualification - and it is not so much a qualification as a
point of emphasis - was that the formalities prescribed in clause 72.1
("Notices"), to which I have referred in para.[3] above, applied only to formal
notices required under clause 17, i.e. the notices required in clause 17.1 and
17.6.1, and not to the provision of details or other information such as was
required by, for example, clause 17.6.2. Conversely, Mr Howie submitted that
the terms of clause 17.8 applied only to the provisions, such as clause 17.6.2,
requiring the giving of information and not to those, such as clause 17.1 and
17.6.1, requiring formal notices to be given. Although Mr Young did not accept
this, it seems to me to be correct, though nothing turns on it for the purpose
of the present dispute.
[12] On that basis, the only question for decision is whether the
letter of 2 May 2007 was capable of constituting a valid notice
for the purposes of clause 17. Mr Howie was prepared to accept that it
was arguable that it was sufficient for the purpose of clause 17.1. But that
was not sufficient to enable the pursuers to succeed. The pursuers also had to
serve a notice complying with clause 17.6.1. That notice had to be sent "as
soon as practicable, and in any event within 20 Business Days" after the
pursuers became aware that the Works Compensation Event "has caused or is
likely to cause delay, breach of an obligation under this Agreement or the
Contractor to incur costs or lose revenue". The letter of 2 May 2007 was the only candidate, being the only notice sent
within that period complying with the formal requirements of clause 72.1. However,
by such letter the pursuers had to give "notice of [their] claim for an
extension of time to the relevant Target Service Availability Date, payment of
compensation and/or relief from its obligations under this Agreement". The
letter of 2 May 2007 gave no notice of any such claim. It
expressly bore to give notice under clause 17.1, and in this context referred
to the details given in other correspondence. But it gave no notice of any
claim under clause 17.6. Indeed it referred to a claim under clause 17.6 in
the future tense: "We will submit our full claim in accordance with clause 17.6
...". That was insufficient. The purpose of the clause was clear. It was to
enable the defenders to know, at the appropriate level of seniority within the
company, that a claim is to be made for an extension of time, or for compensation,
or for other relief, or any combination of those. No doubt if a claim is
intimated in this way, the Chief Executive, or those in his office who deal
with such matters, can take such steps as are thought appropriate, maybe to
ensure that the information is given to others (for example, the Authority), or
to set up some system of checking and reporting on the progress of the works so
as to have all necessary information to consider in detail any claim made in
due course. The precise steps which the defenders might take after receiving
notice was a matter for them. But the very fact that strict formalities were
required for such a notice showed that a clear notice was required in order to
establish a formal regime regulating the position of the parties. The "notice"
could not be left to be inferred from that letter combined with other facts and
circumstances. The parties could not be left in limbo, uncertain whether the
pursuers had made a claim or not. Certainty was required.
[13] For the pursuers, Mr Young QC sought to put the letter of 2 May 2007, and the contractual terms, in context. The contract
was a Public Private Partnership (PPP) contract. The
Authority entered into the Project Agreement with the pursuers. The pursuers
were a special purpose vehicle set up for this purpose. They subcontracted the
building work to the Building Contractor on terms which were almost identical
with those of the Project Agreement. This was well known to the parties. In
addition, there were various provisions in the Project Agreement giving the
Authority a right to be told. I was referred to a number of clauses concerned
with site meetings, the Authority's right of inspection and the supply and
sharing of information; and to various documents showing how this worked in
practice. It was clear, he submitted, that the Authority were kept fully
informed of developments concerning the discovery of asbestos at Building 7 at Prestwick Academy. The Building Contractors sent the survey
report to Messrs MacRoberts, solicitors acting for the Authority, on 6 April 2007. On the same day they sent MacRoberts a letter
informing them that the Works were in delay and that there was likely to be a
delay in achieving the TSAD. This was followed by the e-mail of 18 April 2007 to which I have referred. There was a meeting of 19 April 2007 when representatives of the Authority were informed
of what had been found in the survey, the programme implications and the
options available. And on 27
April 2007 further
information was given. In light of this, there could have been no doubt as to
what was intended to be conveyed by the letter of 2 May 2007.
[14] Turning to the relevant parts of clause 17, Mr Young remarked
that clause 17.1 required a notice to be served on the Chief Executive of the
defenders. The notice had to be served "as soon as reasonably
practicable" after the Contractor became aware that there would be, or was
likely to be, a delay in achieving a TSAD. There was a long stop date of 20
Business Days for giving that notice. The notice needed to specify the reason
for the delay and an estimate of the likely effect of the delay in achieving
the relevant TSAD and what measures were proposed to mitigate the consequences
of the delay. There was a contrast in this respect between the content of a
notice given under clause 17.1 and that required under clause 17.6.1. Clause
17.1 did not set out the consequence of failure to serve the required notice
within the required time. Clause 17.4 introduced more specific requirements
depending upon the cause of the delay. Clause 17.4.1 applied to delay caused
by a Works Compensation Event. This pointed one to clause 17.5 and, in turn,
to clause 17.6. It was the language of the end of clause 17.5 which
pointed clearly towards clause 17.6 being a condition precedent to relief being
granted. Clause 17.6 was concerned with three matters: initial notification;
the subsequent provision of full details; and justification of the claim.
These were dealt with respectively in clauses 17.6.1, 17.6.2 and 17.6.3.
17.6.1 was concerned with the giving of notice. In the present case, the
commencement of the period within which notice had to be given was the same as
for clause 17.1. Thus, under clause 17.1 the Authority will have been given
notice of the reason for the delay and an estimate of the likely effect of the
delay in achieving the relevant TSAD. Clause 17.6.1 simply required the bare
notice of the claim. In addition, it needed to be made clear that the claim
arose out of a Work Compensation Event. But nothing more was required. Clause
17.6.2 laid down the period within which the pursuers were required to give
full details of the Works Compensation Event and the extension of time and
payment claimed. That period was within 15 Business Days of receipt by the
Authority of the notice sent under clause 17.6.1. In many cases that would be
too tight - full details might not be available within that time. In such a
case, he submitted, the Authority would have to act reasonably in deciding
whether or not to agree a longer period for accepting full details of the
claim. If information was handed over late without apparent objection by the
Authority, the Authority might be held by implication to have agreed to accept
it within that longer period.
[15] As to the letter of 2 May 2007, Mr Young submitted that the heading "Works
Compensation Event" showed that the circumstances fell not only within clause
17.1 but also within clause 17.4.1 and, therefore, 17.5. The first paragraph
of that letter clearly referred to clause 17.1 and "ticked all the boxes" for
the purpose of a notice under that clause. The third paragraph was clearly a
reference to clause 17.6. The expression "our full claim" suggests that what
was intended to follow were "full details" of the claim in terms of clause
17.6.2. On that basis that paragraph could be construed as the notification of
a claim in accordance with clause 17.6.1, to be followed with more detailed
information under clause 17.6.2. What that paragraph really meant was: "we are
now giving notice of a claim - full details will be submitted in due course in
accordance with clause 17.6.2". Further, it was clear from the letter of 30
April 2007 from the Building Contractor to the pursuers, which was referred to
in the letter of 2 May 2007 and attached to it, that the Building Contractor
was claiming a 19 week extension of time and was also claiming compensation at
the "A" and "B" Rates for the period of that delay. It would have been clear
to the recipient of the letter that the pursuers were passing up to the
Authority the claim intimated against them by the Building Contractor, with the
addition of a claim for compensation at the "C" Rate. All that was lacking in
the letter of 2 May 2007 was a formal statement that the pursuers
were claiming for an extension of time to the relevant TSAD, for payment of
compensation and/or for relief from their obligations under the Project
Agreement. To require such wording would be unduly formalistic. The notice
required to be sent as a time when it might well be too early to know the full
consequences of the delay or precisely the remedy being sought. In such
circumstances the pursuers would wish to serve a notice keeping open all of
their options. How could it help the Authority if at the end of the letter the
pursuers had written that they were claiming for an extension of time, for
payment of compensation and/or relief from their obligations under the Project
Agreement? Given that the Authority was being kept fully informed of the
likely delay caused by the discovery of Type 3 Asbestos and was aware of the
fact that claims from the Building Contractor would be passed up the line to
the Authority, the letter of 2 May 2007 and its attachment was sufficient to
bring home to the Authority that a claim was being made in terms of clause
17.6.1.
[16] In the course of his submissions Mr Young drew my attention to
two authorities, namely Steria Ltd. v Sigma Wireless Communications
Ltd. [2008] BLR 79, at paras.79-81 and London Borough of Merton v
Leach (1986) 32 BLR 51 at pp.86, 95-8.
Discussion
[17] I prefer the submissions advanced by the defenders. I can
express my reasons shortly. Once it is accepted that the requirement to give
notice in terms of clause 17.6.1 of the Project Agreement is a condition
precedent to the right of the pursuers to obtain relief or claim compensation,
then the question is simply: what does the clause require? The answer is
equally straightforward. The same factors which point to the clause being a
condition precedent also point to the need for any notice served in accordance
with the clause to comply strictly with its terms. The concluding words of
clause 17.5 make it clear that the Contractor's right to apply for relief is
"subject to Clause 17.6". Clause 17.6 states in terms that, to obtain relief,
the Contractor "must" do various things, the first of which is to serve a
notice in accordance with clause 17.6.1. Further, clause 17.7, in its
introductory wording, provides that any relief is conditional upon the
Contractor having complied with the requirements of clause 17.6. It is,
as I have said, conceded by Mr Young that compliance with the notice
requirements of clause 17.6.1 is a condition precedent to the entitlement to
the relief sought. But the point, to my mind, goes further than this. The
wording to which I have referred in clauses 17.5, 17.6 and 17.7 seems to me to
point to a requirement of strict compliance with the terms of the clause. The
notice has to be sent within a limited time, as soon as practicable "and in any
event within 20 Business Days ...". Clause 17.6.1 does not contain the wording
found in clause 17.6.2, "or such longer period as the Authority acting
reasonably may agree". The time requirement is strict. The requirement for
strict compliance is illustrated further by the fact that certain formalities
are insisted upon. Clause 72.1 requires the notice to be sent, not to anyone,
but to the Chief Executive of the Authority. Furthermore, it must be in
writing and sent by first class post, facsimile or by hand (e-mail will not
suffice). Clause 72.5 governs the question of when notices sent by post,
delivered by hand or given by facsimile become effective. All this implies a
level of formality which would, to my mind, be negated if the notice which had
to be sent in a particular way, to a particular person and by a particular
time, did not have to say what the clause appears to require it to say.
[18] The requirements of the clause are not onerous. Mr Young
submitted that a notice under clause 17.6.1 probably required to state that
they delay was caused by a Works Compensation Event. I am not sure that this
is right, since in the event of delay caused by a Works Compensation Event,
notice will also have to be given under clause 17.1; and a statement of the
reason for the delay is one of the requirements of the clause 17.1 notice. But
whether that is so or not, what is absolutely clear is that the notice must
give to the Authority a notice of the claim for an extension of time, for
payment of compensation and/or for relief from obligations under the Project
Agreement. There is no ambiguity in the requirements for a notice under the
clause. Nor does compliance cause any difficulty. Mr Young suggested that one
should make allowance for the fact that notices would be drafted by
businessmen, not lawyers. I do not accept this. It is within judicial
knowledge that parties to contracts containing formal notice provisions turn
immediately to their lawyers whenever there is a requirement to give notice in
accordance with those provisions. But even if that were not the case, there is
nothing in clause 17.6.1 that would not readily be understood by a businessman
unversed in the law.
[19] Where parties have laid down in clear terms what has to be done
by one of them if he is to claim certain relief, the court should be slow to
seek to relieve that party from the consequence of failure. In some cases
there is scope for the application of the principles of waiver or personal bar to
operate so as to prevent a party, who has proceeded on the basis of a defective
notice without taking the point, from subsequently raising it as a technical
defence to the claim. No such argument is raised here, no doubt for good
reason. Instead, the pursuers seek to advance a construction of the clause
which would, if successful, only introduce uncertainty. The points advanced in
argument by Mr Young appear to me to demonstrate that, at least on the ground,
the Authority knew about the delay likely to be caused by the discovery of Type
3 Asbestos. But clause 17.6.2 is not directed towards ensuring that the
Authority have knowledge at that level. Those arguments do not assist the
pursuers on the question of construction. The clause required that a notice be
sent within a particular time to the Chief Executive of the Authority giving
notice of what claim the pursuers were making. The letter of 2 May 2007 did not do that. It matters not that, at certain
levels, employees of the Authority may have been aware of what was going on.
Nor, to my mind, does it help the pursuers to say that the letter of 2 May
2007, when read with the letter of 30 April 2007 from the Building Contractor,
would have enabled the Authority to infer that the claim by the Building
Contractor against the pursuers was going to be passed up the line to them.
That may be so, but the purpose of the clause is to avoid such uncertainty.
The pursuers were required to tell the Authority what claim they were making.
It does not do for them to say: "here is what the Building Contractor has
written to us, you work it out for yourself". That is not a valid notice under
the clause. The failure to give a valid notice in accordance with clause
17.6.2 is fatal to the pursuers' claim for relief.
[20] It was not suggested that the authorities to which I was
referred do more than provide illustrations of how clauses have been construed
in similar types of contracts. They lay down no governing principles. I do
not propose to consider them in detail. Suffice it to say that the reasoning
in Steria was to the effect that the court should be slow to write into
a clause requirements for the content of the notice which were not spelt out in
the clause. That is a very different position from the present case. In the
London Borough of Merton case there was reference to the Architect, to whom
notice had to be given, not being a "stranger to the work". But that comment
was made in support of an argument that it was unnecessary to imply a
requirement for certain matters to be stated in the notice to be given to him.
That again is a very different situation from that with which I am concerned.
Bad weather
[21] The 16 weeks for which a postponement of the TSAD is sought, and
which forms the basis of the calculation of the sum claimed in the third
conclusion, includes some 12.5 days lost during bad weather, in particular high
winds, between December 2007 and March 2008. Bad weather is not a Works
Compensation Event under the Project Agreement. In their case on Record, the
pursuers justify including this period lost due to bad weather on the basis
that, had they been able to carry out the works without the delay caused by
Type 3 Asbestos, they would have finished the Works before the winter months.
Accordingly, the delay caused by the bad weather was a direct consequence of
the delay caused by Type 3 Asbestos, and was to be included in the calculation
of that delay. On that basis, it seems to me that the failure by the pursuers
to give proper notice under clause 17.6.2 of the claim for delay, is fatal to
this aspect of the claim too. The bad weather delay is simply one aspect of
the overall delay in respect of which the notice provisions provide the
defenders with a defence. However, Mr Young sought, somewhat tentatively, to
suggest in the alternative that the delay caused by the bad weather could be
claimed as an independent delay, and did not therefore fall by reason of the
arguments already discussed. This line of argument gives rise to its own
difficulties. Quite apart from the fact that it is not pled as an independent
cause of delay - and the first and second conclusions make it clear that the
delay claimed is all related to the discovery of Type 3 Asbestos - it is
difficult to understand how the bad weather could independently give rise to
any relief. As I have said, it is not a Works Compensation Event. Therefore,
although the pursuers would be required to give a notice under clause 17.1 in
the event that they became aware that there was likely to be delay in achieving
a TSAD because of bad weather, they would not thereby be entitled to a
postponement of the TSAD or to payment of compensation for such period of
postponement. In short, therefore, the delay caused by bad weather is either
parasitic on the delay caused by the discovery of Type 3 Asbestos, in which
case the claim fails for the reasons already discussed; or it is an independent
delay, in which case it affords the pursuers no right of relief.
Disposal
[22] For the reasons set out above, I would have been minded to
dismiss the action, on the basis that, not having given proper notice under
clause 17.6.1, the pursuers were not entitled to the declarator and payments
sought in the second and third conclusions; and that the first conclusion,
standing by itself, was irrelevant. However, Mr Young submitted that it would
be preferable to put the case out By Order. Mr Howie was content that I
should follow this course.
[23] Accordingly, I shall put the case out By Order for a time and
date to be fixed.